Applied Contracting Corp. v. Ohio Dept. of Transp.

2011 Ohio 5320
CourtOhio Court of Claims
DecidedAugust 22, 2011
Docket2008-07195
StatusPublished

This text of 2011 Ohio 5320 (Applied Contracting Corp. v. Ohio Dept. of Transp.) is published on Counsel Stack Legal Research, covering Ohio Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Applied Contracting Corp. v. Ohio Dept. of Transp., 2011 Ohio 5320 (Ohio Super. Ct. 2011).

Opinion

Court of Claims of Ohio The Ohio Judicial Center 65 South Front Street, Third Floor Columbus, OH 43215 614.387.9800 or 1.800.824.8263 www.cco.state.oh.us

APPLIED CONTRACTING CORP.

Plaintiff/Counter Defendant

v.

OHIO DEPARTMENT OF TRANSPORTATION, et al.

Defendants/Counter Plaintiffs

and

STATE OF OHIO

Defendant Case No. 2008-07195

Judge Joseph T. Clark

DECISION

{¶1} Plaintiff/counter defendant, Applied Contracting Corp. (Applied), brought this action alleging breach of contract and unjust enrichment. Defendants/counter plaintiffs, Ohio Department of Transportation (ODOT) and Ohio Department of Administrative Services (DAS), asserted counterclaims for breach of contract and for liquidated damages. The issues of liability and damages were bifurcated and the case proceeded to trial on the issue of liability. {¶2} In July 2006, DAS and Applied entered into a contract under which Applied would serve as the lead contractor for the “District 8 Wash Bay Additions” project, which involved making additions to existing structures at two ODOT facilities. (Plaintiff’s Exhibit A1.) Specifically, a vehicle wash bay was to be built at ODOT’s Wilmington Outpost, and both a wash bay and a service bay were to be built at ODOT’s Blue Ash Outpost. {¶3} While Applied was the lead contractor for the project, DAS also contracted with Airstream Mechanical, LLC (Airstream) for the installation of mechanical, electrical, and plumbing components. Additionally, DAS contracted with Alan Scherr Associates, LLC (ASA) to serve as the associate for the project, in which capacity it provided professional design services and contract administration. {¶4} On July 20, 2006, DAS issued a “Notice to Proceed” to Applied, directing it to commence work “within one week from the date of this notice, and to complete the work by January 3, 2007.” (Plaintiff’s Exhibit A3.) Over the course of the project, however, there arose various issues which resulted in the parties agreeing through change orders to extend the contract completion date three times, with the final such date being March 3, 2007. (Defendants’ Exhibit 9.) {¶5} Donald Legg, President of Applied, testified that although Applied substantially completed its work by the March 3, 2007 deadline, ASA deferred the completion date for certain items such as landscaping, execution of punch lists, and remedial work which ASA and defendants requested concerning the floor of the wash bay at the Wilmington Outpost. Legg testified that Applied timely completed all of the deferred work except for a portion of the remedial work which Applied refused to perform because he felt that it was unnecessary; this work included smoothing the concrete floor of the wash bay and then applying an epoxy coating over the floor. {¶6} The relationship between the parties unraveled as a result of the dispute over the remedial work at the Wilmington Outpost. According to Ryan Meeds, who was the project manager for ASA, Applied completed all of its other work by the beginning of May 2007 and withdrew from the project, in spite of multiple requests from ASA and defendants to complete the few remaining remedial tasks. Legg stated that when ASA sent him a proposed certificate of contract completion, which noted that remedial work remained at the Wilmington Outpost, he refused to sign. (Plaintiff’s Exhibit U.) {¶7} On June 5, 2007, Applied sent ASA a two-page letter titled “Final Notice of Claim and Request for Contract extension to September 1, 2007.” (Plaintiff’s Exhibit V.) Therein, Applied listed twelve issues that had allegedly delayed the project by a total of 241 days, “as a result of the owner failing to adequately provide management, administration and redesign solutions through the course of the project * * *”; Applied requested additional compensation at a rate of $317.69 per day of delay, for a total of $76,563.29. On June 21, 2007, Applied also sent ODOT several one-page invoices which again requested $76,563.29 for delays, and included various other requests totaling $32,520.70. {¶8} Applied’s June 5 and June 21, 2007 requests for payment were declined by defendants. Further, John Burnie, an ODOT facilities manager who supervised construction at both project sites, testified that defendants terminated Applied’s contract and hired another contractor, ISPN, to perform the remaining work at the Wilmington Outpost. {¶9} On June 16, 2008, Applied filed the instant complaint, asserting that defendants committed a breach of contract both by causing project delays and by wrongfully withholding payments owed under the contract; that defendants were unjustly enriched; and that defendants committed a breach of its contract with Airstream, to which Applied was a third-party beneficiary.

DELAYS {¶10} In Count One of its complaint, Applied alleges that defendants committed a breach of contract by causing twelve separate project delays totaling 241 days, as set forth in the June 5, 2007 “notice of claims” that Applied submitted to ASA. The court shall address the alleged delays individually.

{¶11} “Utility pole relocation necessitated by failure to properly design the project. 30 days.” {¶12} On July 20, 2006, Legg sent a request for information to ASA in which he noted that a utility pole at the Wilmington Outpost needed to be relocated in order to begin excavation. (Plaintiff’s Exhibit F.) Burnie and Meeds stated that ASA arranged for the owner of the pole, Dayton Power & Light, to relocate the pole outside the project site, and that the site was ready for work on August 18, 2006. According to Legg, this issue delayed Applied from working at the Wilmington Outpost from July 26, 2006, to August 18, 2006. {¶13} On December 15, 2006, the parties signed Change Order No. G-02, which states, in part: “This Change Order is to provide the contractor a no cost, time exten[s]ion to the project completion date due to previous weather related conditions and unforseen utility relocation requirements. During this time exten[s]ion there will be no cost penalties assessed to the contractor for lack of project completion. If however the projects are not completed by this new [February 18, 2007] completion date penalties will be assessed per the original bid documents.” (Defendants’ Exhibit 6.) (Emphasis added.) All change orders executed during the project also stated: “This Change Order identifies and provides full and complete satisfaction for all direct and indirect costs, including interest and all related extensions to the time for Contract Completion, for the described changes in the Scope of the Work.” {¶14} Burnie testified that he believed the change order resolved all issues concerning the utility pole relocation. Legg also admitted that the parties intended for the change order to resolve the utility pole relocation, and he acknowledged that all change orders signed by the parties were negotiated. Legg stated, though, that he later decided that the change order failed to adequately redress the issue and that he therefore requested additional compensation in the June 5, 2007 notice of claim. {¶15} Article GC 7 of the contract provides, in part: {¶16} “7.1.1 The Department, without invalidating the Contract, may order changes in {¶17} the Work consisting of additions, deletions or other revisions, including without limitation revisions resulting from an extension granted in accordance with Paragraph GC 6.4. To the extent the time for Contract Completion or the Contract Price is affected, the Contract may be equitably adjusted by Change Order in accordance with this Article and the Change Order Procedure and Pricing Guidelines (CO).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lee Turzillo Contracting Co. v. Frank Messer & Sons, Inc.
261 N.E.2d 675 (Ohio Court of Appeals, 1969)
Struna v. Ohio Lottery Comm., Unpublished Decision (10-21-2004)
2004 Ohio 5576 (Ohio Court of Appeals, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
2011 Ohio 5320, Counsel Stack Legal Research, https://law.counselstack.com/opinion/applied-contracting-corp-v-ohio-dept-of-transp-ohioctcl-2011.