Application of Big Lost River Irrigation District

307 P.2d 788, 78 Idaho 591, 1957 Ida. LEXIS 175
CourtIdaho Supreme Court
DecidedFebruary 26, 1957
Docket8493
StatusPublished
Cited by3 cases

This text of 307 P.2d 788 (Application of Big Lost River Irrigation District) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Application of Big Lost River Irrigation District, 307 P.2d 788, 78 Idaho 591, 1957 Ida. LEXIS 175 (Idaho 1957).

Opinion

PORTER, Justice.

In the year 1952 the Big Lost River Irrigation District filed an application with the State Reclamation Engineer for approval of plans, drawings and specifications for raising the reservoir level at Mackay Dam in Custer County an additional height of fifteen feet. The State Reclamation Engineer approved the raising of the reservoir level an additional five feet in height. The spillway of the Mackay Dam is some seventy-five feet in width. The approved plans called for the installation of Tainter gates in such spillway to raise the same an additional five feet.

The raising of the reservoir level an additional five feet in height was not carried out by the District.

In March, 1956, the District submitted proposed plans, drawings and specifications to amend its application by proposing the installation of an OG structure in the spillway of a height of five feet instead of the installation of Tainter gates. Tainter gates are gates which can be raised from *594 the bottom and permit water to escape before it flows over the top. By OG construction is meant the installation in the spillway of a concrete barrier five feet in height with a specially curved top to expedite the flow of water over the top of the barrier.

The State Reclamation Engineer disapproved the proposed amendment. The Irrigation District appealed to the district court in and for Custer County. A trial de novo was had before the court sitting without a jury. The court made findings of fact and conclusions of law favorable to the Irrigation District and entered judgment approving the installation in the spillway of an OG barrier instead of the installation of Tainter gates. From such judgment the State Reclamation Engineer has appealed to this court.

Appellant makes eight assignments of error. By Assignment of Error No. 1, he contends the court erred by attempting to limit the issues to a smaller compass than as presented by the pleadings.

At the beginning of the trial the court observed as follows:

“I have examined the Petition and briefly the answer filed, and it appears therefrom that the principal issue would be one of fact as to whether the proposed change in the plans — of the Ogee spill-way — whether the substitution of the Ogee spillway for the Taint-er gates heretofore approved by the Department in 1952 would be sufficient to protect the dam; and, of course, the property and lives of people below it. Is that substantially correct, the issues, gentlemen?”

To this observation, the attorney for the District and the attorney for the State Engineer each answered, “That is the way I understand it.” We find no error under this assignment.

By Assignment of Error No. 2, appellant urges the court erred by interjecting his own opinions in the course of the examination of witnesses and in assuming the status of counselor by interrogating appellant’s witnesses rather in the nature of cross-examination. Appellant does not point out any specific remarks or questions to witnesses by the court upon which appellant relies as showing prejudicial error. No showing is made that any particular conduct of the court affected the substantial rights of appellant. Boise Street Car Co. v. Van Avery, 61 Idaho 502, 103 P.2d 1107; Richardson v. Bohney, 26 Idaho 35, 140 P. 1106; Hooton v. City of Burley, 70 Idaho 369, 219 P.2d 651.

By Assignments of Error Nos. 3, 5, 6 and 7, appellant makes the contention that there was no competent evidence to sustain the court’s findings and conclusions approving the installation of the OG structure in the spillway. It is the contention *595 of appellant that the competent evidence on behalf of the Irrigation District was not sufficient to overcome the expert testimony on behalf of appellant.

The Irrigation District produced as witnesses the President of the Board of Directors and a former member of the Board of Directors both of whom testified as to conditions surrounding the maintenance and operation of the Mackay Dam, and the filling of the reservoir. In addition, the court had before it the plans, drawings and specifications of the Engineer of the Irrigation District showing the proposed OG structure. On the other hand, appellant introduced his own testimony and the testimony of a licensed engineer from his office. Both testified in effect that the Tainter gates provided an additional safety factor in case of a sudden flood which safety factor they deemed advisable.

The Mackay Dam in its present form has been maintained and operated since before 1923. The existing outlet works consist of five large gates each four by eight feet in size or thereabouts and a tunnel of ten feet in diameter or thereabouts. These outlet works have always been sufficient to take care of any sudden rise in the reservoir. The evidence shows that it has never been necessary to use more than three of such gates to control the height of water in the reservoir. The evidence indicates that appellant and the engineer from his office did not take fully into consideration the additional capacity of the outlets available for control of any sudden flood of water into the reservoir.

Appellant contends the evidence of the laymen was not competent as against the evidence of the licensed engineers on the question of safety. Expert opinions are not ordinarily conclusive but are generally advisory in character to assist the triers of fact to understand and apply other evidence. Nistad v. Winton Lumber Co., 61 Idaho 1, 99 P.2d 52; Evans v. Cavanagh, 58 Idaho 324, 73 P.2d 83; 20 Am. Jur., Evidence, Sec. 1208, pp. 1059-1060; Walker v. Distler, 78 Idaho 38, 296 P.2d 452; Arais v. Kalensnikoff, 10 Cal.2d 428, 74 P.2d 1043, 115 A.L.R. 163. The court’s finding “that there is no necessity for tainter gate structures within the spillway or any other provisions or manner for regulating the five feet of additional storage above the present spillway level independent of the existing tunnel and outlet works” is supported by competent, substantial, though conflicting evidence. It has become axiomatic in this jurisdiction that under such circumstances such finding will not be disturbed on appeal.

By Assignment of Error No. 4, appellant complains that Findings of Fact Nos. VI to X are not findings of fact but a series of orders or decrees. These findings provide that respondent take such steps as are reasonably necessary during *596

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Myers
494 P.2d 574 (Idaho Supreme Court, 1972)
George Lee Mims, Sr. v. United States
375 F.2d 135 (Fifth Circuit, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
307 P.2d 788, 78 Idaho 591, 1957 Ida. LEXIS 175, Counsel Stack Legal Research, https://law.counselstack.com/opinion/application-of-big-lost-river-irrigation-district-idaho-1957.