Applegate v. United States

28 Fed. Cl. 554, 1993 U.S. Claims LEXIS 66, 1993 WL 204579
CourtUnited States Court of Federal Claims
DecidedJune 14, 1993
DocketNo. 92-832L
StatusPublished
Cited by4 cases

This text of 28 Fed. Cl. 554 (Applegate v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Applegate v. United States, 28 Fed. Cl. 554, 1993 U.S. Claims LEXIS 66, 1993 WL 204579 (uscfc 1993).

Opinion

OPINION

NETTESHEIM, Judge.

This case is before the court after argument on defendant’s motion to dismiss for lack of subject matter jurisdiction due to the bar of the six-year statute of limitations. Plaintiffs sue under the fifth amendment to the United States Constitution seeking recovery of compensation for erosion and flood damage to their properties allegedly caused by the Army Corps of Engineers (the “Corps”) in constructing and maintaining a harbor project. Plaintiffs also pray for an injunction requiring the building and operation of a sand transfer facility or, in the alternative, an award of damages to cover the costs of such construction.

FACTS

The following facts are undisputed and, except as noted, derive from the complaint. Plaintiffs1 are owners of beachfront property nearby or adjacent to Port Canaveral and Sebastian Inlet in Brevard County, Florida. This coastline fronts on the Atlantic Ocean to the south of the projection of Cape Canaveral (“the Cape”). Prior to the events giving rise to this action, the area consisted of a 41-mile long arc of white sandy beaches. Due to a natural southerly littoral flow of sand,2 the beaches south of the Cape accreted two to three feet each year. This littoral sand flow both created the beaches and replenished them with sand.

In 1945 Congress passed the River and Harbor Act of 1945, Pub.L. No. 79-14, §§ 1-2, 59 Stat. 10,16 (1945) (partially codified at 33 U.S.C. § 603a (1988)), which authorized “the construction of works of improvement, for navigation or flood control” in numerous areas of the country, including Canaveral Harbor. The Act also provided for the operation and maintenance of the Canaveral Harbor Project (the “Project”) by the Corps. Plaintiffs allege that the Project as constructed included the following components: 1) dredging of a channel in the Atlantic Ocean; 2) cutting a passage from the Atlantic through a barrier island into the Banana River Lagoon; 3) constructing a harbor and turning basin in the lagoon; and 4) building two jetties to protect the harbor entrance. Construction commenced in 1950. In November 1953 the Corps completed the south jetty; in September 1954 the north jetty was completed. At oral argument plaintiffs represented several additional facts. Since 1955 the Project also included maintenance dredging of the channel connecting the ocean to the harbor, performed every 18 months. Plaintiffs pointed out that in 1956-57 the Corps deepened and widened the port. In 1958 the Corps extended the north jetty; in both 1961 and 1975, the Corps deepened the channel. In 1986 the port was further enlarged.

The Corps’ construction of the protruding jetties and commencement of maintenance dredging blocked the southward littoral flow of sand. During oral argument plaintiffs stated that erosion and flooding began in 1952. Consequently, the shoreline north of harbor entrance accreted, while the coastline to the south receded. Plaintiffs contend that, although these phenomena manifested themselves immediately after the Corps began construction, beach erosion continues to the present day. The Project’s blocking of the sand flow also caused flooding of plaintiffs’ land upland of the mean high tide line. This flooding, in turn, has contributed to continued beach erosion. Moreover, the mean high tide line has moved progressively west[557]*557ward. Plaintiffs claim that the resultant flooding inundated each of their properties. In 1966 the public became aware that the Project caused beach erosion in the vicinity. Plaintiffs assert that the Corps foresaw that the Project’s activities would cause erosion and flooding. To date approximately 400 feet of beachfront has eroded away.

In 1962, pursuant to the River and Harbor Act of 1962, Pub.L. No. 87-874, § 101, 76 Stat. 1173,1174 (1962) (partially codified at 33 U.S.C. § 426e-g (1988)), Congress authorized the construction of a sand transfer plant at Canaveral Harbor. Congress appropriated $5,076,000.00 for this purpose. In 1967 the Corps presented a $1,300,000.00 plan to rebuild the beaches and construct a sand transfer plant. In 1968 the Senate Public Works Committee and the Florida Department of Natural Resources approved the sand transfer/beach rebuilding plan. After letting out bids, in August 1971 the Corps announced an indefinite delay in construction in order to conduct further research and development. The Corps also proposed an interim beach renourishment plan. In October 1988 the Corps proposed a $5,000,000.00 plan to construct a sand transfer facility system to transfer sand from north of Canaveral Harbor to the south. Plaintiffs allege reliance on the Corps’ various pronouncements. To date the Corps has not built a sand transfer facility, and, as previously noted, erosion and flood damage continue.

According to plaintiffs, the jetties and periodic channel dredging have so far blocked $68,000,000.00 worth of sand. But for the Project, this sand would deposit on plaintiffs’ properties south of the Canaveral Harbor. Consequently, the State of Florida and local jurisdictions placed zoning restrictions on plaintiffs’ properties. Specifically, plaintiffs claimed at oral argument that setback restrictions now limit the structures that plaintiffs may erect on their properties due to the ocean’s proximity. These restrictions have limited plaintiffs’ ability to enjoy their properties. Plaintiffs allege that the beach erosion and attendant flooding will eventually completely destroy, i.e., wash away, their properties.3

Although this particular case is of recent genesis, one plaintiff previously brought suit concerning the same matter. In 1970 Robert G. Pitman, Jr., filed an action in the United States Court of Claims under the fifth amendment and the Tucker Act, 28 U.S.C. § 1491 (1964), to recover compensation for the taking of five acres of beachfront property. Pitman v. United States, 198 Ct.Cl. 82, 457 F.2d 975 (1972). The parties agree that the Pitman property constitutes at least part of the properties at issue in the case at bar. The Court of Claims dismissed the complaint on defendant’s motion for summary judgment, holding in part that defendant had not directly invaded or appropriated Mr. Pitman’s property. 198 Ct.Cl. at 87, 457 F.2d at 977-78 (citing cases).

On December 4, 1992, plaintiffs filed suit in the Court of Federal Claims. Plaintiffs pray for damages in excess of $100,000,-000.00 for defendant’s alleged taking without compensation, and, by a proffered amendment to their complaint, an order requiring the Corps to construct and operate a sand transfer facility, as well as interest, attorneys’ fees, and costs.

DISCUSSION

1. Defendant moves to dismiss the complaint pursuant to RCFC 12(b)(1) for lack of subject matter jurisdiction and Rule 12(b)(4) for failure to state a claim upon which relief can be granted. The former ground is the gravamen of defendant’s motion, since defendant takes the position that plaintiffs’ claim is time barred; dismissal is sought under Rule 12(b)(4) only with respect to the prayer for an order that the Corps take steps to restore the littoral flow of the river of sand. Conceding defendant’s motion as to the latter ground, plain[558]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
28 Fed. Cl. 554, 1993 U.S. Claims LEXIS 66, 1993 WL 204579, Counsel Stack Legal Research, https://law.counselstack.com/opinion/applegate-v-united-states-uscfc-1993.