Appeal of Offray

CourtVermont Superior Court
DecidedOctober 4, 2000
Docket166-9-98 Vtec
StatusPublished

This text of Appeal of Offray (Appeal of Offray) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Appeal of Offray, (Vt. Ct. App. 2000).

Opinion

STATE OF VERMONT

ENVIRONMENTAL COURT

} In re: Appeal of } Claude V. Offray and Gloria Offray } Docket No. 166-9-98 Vtec } }

DECISION and ORDER

Appellants Claude and Gloria Offray appealed from a decision of the Zoning Board of Adjustment (ZBA) of the Town of Lincoln, granting a conditional use permit to Appellee- Applicant Willard Jackson for the operation of a gravel pit. He had originally also applied for a variance to conduct a portion of the operation close to the property line, but the application for variance was withdrawn and the remaining conditional use application was limited to the area for which no variance was necessary. Appellants are represented by John F. Evers, Esq.; Appellee-Applicant Willard Jackson appeared and represented himself with the assistance of David Wetmore, who is not an attorney; the Town of Lincoln entered an appearance by George R. Vince, Esq., but did not take an active role in this appeal. An evidentiary hearing was held in this matter before Merideth Wright, Environmental Judge. The parties were given the opportunity to submit written requests for findings and memoranda of law. Upon consideration of the evidence and the written memoranda and proposed findings, the Court finds and concludes as follows. Appellee-Applicant owns a 134-acre parcel of land off the Gap Road in the Town of Lincoln, which contains a former gravel pit operated from the 1940s through the early 1970s, located near the center of the property near its northerly boundary. Appellee- Applicant proposes to operate a gravel pit on a 7-acre portion of his property designated on Exhibit 3, third page, and on Exhibit 4, with no more than 5 acres to be under excavation at any time. All topsoil removed is proposed to be stockpiled in berms, to be located to the extent possible to shield Appellants= property and Town Highway #1 from the noise of the site=s operations, and to be used in the reclamation of the site. The zoning district in which the property is located requires a conditional use permit for a sand and gravel pit in the

1 proposed location. At present there is no local source for sand and gravel within the town; any sand and gravel used by the Town or by residents of the Town is brought in over local roads from elsewhere. The land is a mix of forested and open meadow areas, and contains a gravel deposit on a knoll of land near its westerly boundary. A road on the site (the Aaccess road@) runs from the location of the proposed gravel extraction operation to Town Highway #1. Its configuration is proposed to be changed to reduce its slope and to make a 90 degree intersection with Town Highway #1, and its speed limit is proposed to be 15 miles per hour. The speed limit on Town Highway #1 is 35 miles per hour at the entrance to the project=s access road. The ZBA decision appealed from imposed a requirement that Applicant install a stop sign on the access road as it exits onto Town Highway #1, that Applicant arrange for the installation of Atrucks entering@ warning signs in both directions on Town Highway #1 approaching the access road intersection, and that Applicant impose a 10 mile per hour speed limit on the last 500 feet of access road approaching the intersection with Town Highway #1. Appellee-Applicant did not file any cross-appeal of these requirements. Appellants= 69-acre parcel adjoins the subject parcel. Because of the size of Applicant=s parcel, other properties in the area are located a substantial distance from the proposed excavation site. Most of the properties in the area are agricultural and residential, except for the Lincoln School, the Town shed, and a pallet mill qualifying as light manufacturing. Appellee-Applicant proposes to remove a maximum of 20,000 cubic yards of material annually, over the seven month operating season from mid-April through mid- November. The trucks anticipated to be used have an average capacity of eleven cubic yards, so that an average of 260 truck round trips per month would be required to remove that amount of material. Operating 6 days a week would result in approximately ten truck round trips per day. Appellee-Applicant proposes to operate extraction, processing, and loading of material onto trucks Monday through Friday from 7 a.m. to 5 p.m. and to operate without excavation or processing on Saturdays from 7 a.m. to noon. The normal processing

2 equipment would be a gravel sorting screen. Appellee-Applicant expects to need to operate gravel crushing equipment only approximately four weeks (two two-week periods) a year. Appellee-Applicant proposes to conduct excavation and , if necessary, blasting, no closer than 200 feet from the property boundary, and to operate processing and sorting equipment no closer than 300 feet to the property boundary, as required by ''734.3d and 734.3e. Appellee-Applicant, and to maintain noise levels from the extraction process below 75 dBA at the property boundary, except the noise from trucks (and possibly the noise during any blasting). Appellee-Applicant does not expect to need to conduct any blasting. Appellee-Applicant proposes to notify the adjoining property owners at least two weeks prior to conducting any blasting or to using any portable crusher machinery in the pit. Appellee-Applicant proposes to use every effort to minimize noise, including to limit truck speed to 15 mph on the access road, to stockpile processed material in a noise-reducing berm, to plant additional trees near the entrance to the Town Highway, to maintain a large enough pit floor area to minimize the need for trucks to back up (as the federally-required backup beepers produce an annoying noise), and to use sonic or Asmart@-type backup alarms on all non-registered pit machinery. Appellee-Applicant proposes to allocate approximately half of the gravel extracted annually to the Town of Lincoln and other local users. The Town Plan at page 6 recognizes that soil deposits within the Town may be very localized, and that land uses should be compatible with the type of soil in a given area. Specifically with regard to gravel extraction, that section of the Town Plan states that Agravel and sand banks in many areas of town lend themselves to the extraction of those materials on a small scale, in keeping with the traffic limitations of our roads,@ and recognizes that Asuch local projects could ease the [Town=s] cost burden of road maintenance ans other projects by keeping hauling expenses low.@ The proposal therefore meets criterion '734.2p regarding the conformance of the proposal with the Town plan. To receive a conditional use permit, Appellee-Applicant must satisfy the five general conditional use criteria in '734.1, applying the nine criteria specific to sand and gravel operations in '734.3. If necessary to protect the public safety or welfare, the Planning Commission, and hence this Court in this de novo proceeding, may impose conditions

3 related to the sixteen special criteria in '734.2. Certain of the criteria are inapplicable and will not be further discussed. The proposal will have no adverse effect on the utilization of renewable energy resources. '734.1e. The proposal will have no adverse effect on the capacity of existing or planned community facilities. '734.1a. All parking and loading is proposed to take place at the pit site well away from the road. 734.2b. Appellee-Applicant has not now proposed any signs; if one is proposed at the access road, it will have to meet the criteria of '550 and may require a minor amendment of this permit. '734.2g. Appellee-Applicant does not propose any structures or service areas ('734.2d); any outside displays ('734.2i); any outside storage of goods ('734.2j); or any on- site or municipal water supply or sewage disposal ('734.2k). Portable toilets will be provided for the use of employees and truck drivers on site.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
Appeal of Offray, Counsel Stack Legal Research, https://law.counselstack.com/opinion/appeal-of-offray-vtsuperct-2000.