Appeal of Marc and Susan Wood

CourtVermont Superior Court
DecidedMay 19, 2004
Docket121-7-03 Vtec
StatusPublished

This text of Appeal of Marc and Susan Wood (Appeal of Marc and Susan Wood) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Appeal of Marc and Susan Wood, (Vt. Ct. App. 2004).

Opinion

STATE OF VERMONT

ENVIRONMENTAL COURT

Appeal of Marc and Susan } Wood } } Docket No. 121-7-03 Vtec } }

Decision and Order on Cross-Motions for Summary Judgment

Appellants Marc and Susan Wood appealed from a June 16, 2003 decision of the Zoning Board of Adjustment (ZBA) of the Town of Hartford, upholding the Zoning Administrative Officer= s decision not to accept Appellants= application to amend Zoning Permit #99-11801 and its associated site plans for the so-called Phase II of their development. Appellants represent themselves; the Town is represented by William F. Ellis, Esq.

The parties have moved for summary judgment on issues relating to the expiration date of the permit sought to be amended, and what regulations apply to the amendment application. The following facts are undisputed unless otherwise noted.

Appellants propose the development of a diner, private club, gas station, and convenience store on their property in the Town of Hartford. The property is located between Maple Street (Route 14) at a higher elevation and Ferry Boat Crossing (formerly Alber Drive) at a substantially lower elevation. Because of the difference in elevation, Appellants proposed to create a concrete slab retaining wall and to place fill to increase the area of land at the higher elevation and to stabilize the slope or bank. Appellants obtained zoning permits for the project (see footnote 1).

Section 1-4.3 of the Zoning Regulations requires the work authorized by a zoning permit to be started within six months and to be completed within two years of the permit= s issuance date. Failure to meet these time deadlines requires that the applicant apply for a new permit for any remaining work, and that the new permit is to be decided under the regulations in effect at the time of the new permit application. Section 1-4.3 further allows the Planning Commission to issue a one-time six-month extension to either or both time periods (the start date and the completion date).

The permit for Phase III, #99-1215, does not appear to be at issue in the present appeal. Its effective date appears to have been September 2, 1999, so that absent any extensions it would have expired on September 2, 2001. Appellants appealed in Docket No. 37-2-00 Vtec from the Planning Commission= s site plan approval for Phase III, and in Docket No. 102-5-00 Vtec from the ZBA= s decision to uphold the Zoning Administrator= s denial of a building permit for Phase III. These two appeals were dismissed as moot in the fall of 2001.

The effective date for Permit #99-1180, for Phase II, was October 16, 1999. Absent any extensions, it would have expired on October 16, 2001. Among other requirements, Permit #99- 1180 required Appellants= engineer to certify that the concrete slab retaining wall was constructed in accordance with the approved plans.

On June 11, 20012, the ZBA granted Appellants a six-month extension of the completion date for one of the zoning permits. If this extension were applicable to Phase II (Permit #99-1180), its completion date would have expired on April 16, 2002, absent any issues regarding its being stayed due to the pendency of litigation.

In early 2000, Appellants began the construction of the retaining wall or at least the stockpiling of concrete slabs on the lower elevation portion of the property, as the slab segments became available from ongoing highway bridge improvement projects. The Zoning Administrative Officer issued a Notice of Violation on February 4, 2000, alleging that the slabs were not being placed in the location authorized by the zoning permit and that the placement of the slabs was not in conformance with the approved Phase II plans.

Appellants appealed the Notice of Violation (Docket No. 91-5-00 Vtec) and the Town brought an enforcement action (Docket No. 72-3-00 Vtec). These two Environmental Court cases were consolidated for trial with a related Windsor Superior Court case3, in which the Town alleged that Appellants created a public nuisance by clearing the slope and stacking the slabs on the property (Docket No. 219-5-00 WnCv).

During the very early pendency of that litigation, before the consolidation, on April 28, 2000, Judge Wright heard a motion for preliminary injunction, and took a site visit with the parties. At the site visit, Judge Wright issued an oral order governing the work on the site over the weekend of April 29-30, 2000, allowing Appellants to re-stack the concrete slabs at the westerly end of the site, and allowing only such work on the embankment as necessary to render it more stable during those two days. On May 1, 2000, the Environmental Court issued a written order in Docket Nos. 72-3-00 Vtec and 91-5-00 Vtec, denying the Town= s request for a preliminary injunction, without prejudice, and stating the Court= s expectations that the merits of the litigation would establish the safety and stability of the stacked slabs and the scope and conditions of the site plan approval of the project. Together with the transfer and consolidation order, Judge Cheever in Windsor Superior Court issued an order in Docket No. 219-5-00 Wrcv, orally on the record on June 14, 2000, and in writing on June 16, 2000, requiring Appellants to stabilize the pile of slabs and otherwise to stop construction until that litigation was completed or until further order of the Court.

Those consolidated cases were concluded by a decision issued on September 21, 2001, concluding that the retaining wall on the Town property did not meet the design specifications as approved in the permit for Phase II. However, the decision allowed Appellants to apply to the ZBA for approval of their proposal for Phase II, as an amendment to the previously-approved plans for Phase II. Appellants appealed that decision to the Vermont Supreme Court, which affirmed it on May 29, 2002. Town of Hartford v. Marc and Susan Wood, Docket No. 2001-473 (Vt. Supreme Ct., May 29, 2002) (three-justice panel).

Between the date of that decision and the application at issue in the present appeal (filed on April 15, 2003), Appellants assert that they made four earlier attempts to apply for approval of an amended site plan pursuant to the September 21, 2002 Order. Whether these applications or attempts to apply were rejected as incomplete or for some other reason, Appellants did not appeal the Zoning Administrator= s action on those attempts, and therefore those earlier efforts to apply are not before the Court in the present appeal. 24 V.S.A. ' 4472(a).

Appellants= April 15, 2003, application sought to amend the Phase II permit (Permit #99-11804). In addition to the changes in the design of the retaining wall, this application proposed changes to the locations of parking, a curb cut and gas pumps, and changes to the existing diner building. It also proposed that a building that had been proposed to be removed under the original Phase II permit would be retained and changed in use to a retail store.

On May 1, 2003, the Zoning Administrator declined to accept Defendants= application to amend, returning the application as incomplete, and stating that the permit for Phase II had expired. She also stated that the current application A would not be considered an amendment@ due to the extent of the proposed changes from the original application.

In their arguments, both parties conflate the issue of whether the expiration time of the old permits had been stayed due to the pendency of the appeal litigation (under Preseault v. Wheel, 132 Vt. 247 (1974)) with the issue of what regulations would apply to any amendment or new permit request.

The time for expiration of a valid permit is properly suspended for a period during which delay in construction is caused by litigation. A permittee does not acquire additional time for construction if the permit expired prior to the litigation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Preseault v. Wheel
315 A.2d 244 (Supreme Court of Vermont, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
Appeal of Marc and Susan Wood, Counsel Stack Legal Research, https://law.counselstack.com/opinion/appeal-of-marc-and-susan-wood-vtsuperct-2004.