Appeal of Ghia

CourtVermont Superior Court
DecidedNovember 29, 2003
Docket31-2-03 Vtec
StatusPublished

This text of Appeal of Ghia (Appeal of Ghia) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Appeal of Ghia, (Vt. Ct. App. 2003).

Opinion

STATE OF VERMONT

ENVIRONMENTAL COURT

Appeal of James Ghia } } Docket No. 31-2-03 } Vtec } }

Decision and Order

Appellant James Ghia appeals from a decision of the Development Review Board (DRB) of the Town of Ludlow, affirming the Administrative Officer=s1 decision that Appellant= s 1985 zoning permit had lapsed. The appeal to this Court is an on-the-record appeal pursuant to 24 V.S.A. ' 4471(a) and V.R.C.P. 76(e)(3), as the Town of Ludlow has adopted and implemented the procedures necessary for such appeals. Appellant is represented by Martin Nitka, Esq.; the Town2 of Ludlow is represented by J. Christopher Callahan, Esq.

The documentary record was received by the court, as was a copy of the audio tape of the DRB hearing. No transcripts were ordered by any party of any portion of the hearing. The parties were given the opportunity to submit written memoranda of law. Upon consideration of the record and the parties= memoranda, the court determines that the following facts are supported by substantial evidence in the record as a whole, and concludes as follows.

In an on-the-record appeal, the factual findings of the administrative body are given great weight, although they are not conclusive. The court must determine if substantial evidence exists in the record as a whole from which the factual findings of the DRB might reasonably be inferred. See In re Petition of Town of Sherburne, 154 Vt. 596, 604-05 (1990); Appeal of Lussier and Noe, Docket No. 116-5-02 Vtec (Vt. Envtl. Ct., Sept. 16, 2002). If there is conflicting evidence in the record, the DRB is the body charged with weighing this evidence and the court will not disturb its factual findings if supported by substantial evidence in the record as a whole. See Appeal of Doyle, Docket No. 100-5-02 Vtec (Vt. Envtl. Ct., Jan. 21, 2003).

The 1979 Ludlow zoning regulations (applicable to Appellant= s 1985 permit) provided in ' 225 that no land or building development could commence without a zoning permit issued by the Administrative Officer. The issuance of the zoning permit by the Administrative Officer was the final step in the municipal zoning approval process. Depending on the particular project, other approvals were necessary prerequisites to the Administrative Officer=s issuance of the zoning permit. For all uses other than one- and two-family dwellings, the then-Planning Commission first had to grant site plan approval before the zoning permit could be issued by the Zoning Administrator. ' 275, and see, e.g., Wesco, Inc. v. City of Montpelier, et al., 169 Vt. 520 (1999). For conditional uses (' 250) or for extensions of non-conforming uses (' 255), the then-Zoning Board of Adjustment (ZBA) first had to grant conditional use approval3 before the zoning permit could be issued by the Zoning Administrator. For permitted uses that did not also require prior site plan approval, under ' 245 the Administrative Officer could proceed directly to issuing the zoning permit. The procedure described in Section 250 was followed in 1985 for this application: a public hearing was held by the then-ZBA, which granted conditional use approval, on the basis of which a zoning permit was issued by the Administrative Officer under ' 225.

In 1985, Appellant applied to the then-ZBA for approval of his plans to build 24 condominium units in six buildings of four residential units each, A to be built in 3 phases of 2 buildings (8 units) per year,@ on property located off West Hill Road4 on Okemo Mountain in the Town of Ludlow. The project was to be connected to the municipal sewer system but to have an on-site water supply from a drilled well or wells. The ZBA held a public hearing on February 27, 1985, at which it voted to approve the project with certain conditions. It issued a written Notice of Decision on April 19, 1985, which required Appellant to then apply to the Administrative Officer for a zoning permit. Appellant thereafter applied for and received a zoning permit from the Administrative Officer. The zoning permit carries a date on its face of February 27, 1985, referring to the date of approval of the project; however, as the Notice of Decision did not issue until April 19, 1985, we will give Appellant the benefit of that lapse of two months and treat the date of the conditional use approval and the zoning permit as no earlier than April 19, 1985.

Condition 1 of the ZBA= s 1985 conditional use approval required construction to begin A within 120 days of granting of Conditional Use Permit, or permit automatically becomes void.@ Condition 12 required the project to be A in absolute conformance@ with the Town of Ludlow Zoning Regulations. Section 225 of the Zoning Regulations in effect in 1985 required that A [a]ny zoning permit issued shall become void if the work described therein is not commenced within a period of 120 days from the date of issuance and diligently prosecuted thereafter.@

In addition, Condition 14 of the ZBA= s 1985 conditional use approval prohibited any additions, changes, modifications, or improvements to the project without prior notification to the Zoning Administrator and A prior written mutual agreement@ between the applicant and the board. Condition 15 required the developer to notify the Zoning Administrator upon completion and prior to occupancy. No construction completion date was imposed in the ZBA decision.

Appellant did not appeal the 1985 conditional use approval or any of the conditions imposed in it, and did not request extension of any of the construction commencement dates found in the conditional use approval decision or in ' 225 of the Zoning Regulations.

Appellant also applied in 1985 for Act 250 approval of the project; but received an Act 250 permit on July 16, 1985 for only the first 12 units, based on the amount of water available from the on-site well. The Act 250 permit required Appellant to apply for an Act 250 permit amendment in the future to construct the remaining 12 units, if an additional water supply could be found. The Act 250 permit required the initial 12 units to be completed by October 15, 1986, but this completion date was later extended upon Appellant= s attorney= s request. Thus, as of July 16, 1985, Appellant knew that construction of the second group of 12 units would require further engineering work and a future application for a state water supply and wastewater disposal permit and a future application for an Act 250 permit amendment.

A period of 120 days from the April 19, 1985 zoning permit would have expired on or about August 17, 1985. A period of 120 days from the July 16, 1985 Act 250 permit issuance date would have expired on or about November 13, 1985.

Construction did not begin on the initial 12 units until some time in 1987, as stated by Appellant= s attorney on the audio-taped record of the DRB hearing in the present appeal and as found by the DRB supported by substantial evidence in the record as a whole. Construction of the initial 12 units, in three buildings of four units each, was completed by some time in 1989.

Appellant sold the initial 12 units over the nine years from 1989 through 1998, but did nothing towards construction of the remaining 12 units during that period. At some time not earlier than 1998, Appellant decided to start the process of obtaining the additional water supply and applying for the state water and waste water permit and Act 250 permit amendment for the remaining 12 units. He hired hydrologists and engineers to find additional water; they had to hydrofracture as well as to drill for water, and also extended the sewer lines to the location of the new buildings. Between the engineering and the state water supply and wastewater permitting process the process was lengthy and expensive and cost Appellant approximately $40,000.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Kostenblatt
640 A.2d 39 (Supreme Court of Vermont, 1994)
Benning v. State
641 A.2d 757 (Supreme Court of Vermont, 1994)
Preseault v. Wheel
315 A.2d 244 (Supreme Court of Vermont, 1974)
Petition of Town of Sherburne
581 A.2d 274 (Supreme Court of Vermont, 1990)
Wesco, Inc. v. City of Montpelier
739 A.2d 1241 (Supreme Court of Vermont, 1999)
Brody v. Barasch
582 A.2d 132 (Supreme Court of Vermont, 1990)
Rogers v. Watson
594 A.2d 409 (Supreme Court of Vermont, 1991)
Appeal of Farrell & Desautels, Inc.
383 A.2d 619 (Supreme Court of Vermont, 1978)
Levy v. Town of St. Albans Zoning Board of Adjustment
564 A.2d 1361 (Supreme Court of Vermont, 1989)
Richards v. Nowicki
772 A.2d 510 (Supreme Court of Vermont, 2001)
In re S.M.
2003 VT 41 (Supreme Court of Vermont, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
Appeal of Ghia, Counsel Stack Legal Research, https://law.counselstack.com/opinion/appeal-of-ghia-vtsuperct-2003.