Appeal of Donna M. Heald & a.

CourtSupreme Court of New Hampshire
DecidedMay 22, 2020
Docket2019-0277
StatusUnpublished

This text of Appeal of Donna M. Heald & a. (Appeal of Donna M. Heald & a.) is published on Counsel Stack Legal Research, covering Supreme Court of New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Appeal of Donna M. Heald & a., (N.H. 2020).

Opinion

THE STATE OF NEW HAMPSHIRE

SUPREME COURT

In Case No. 2019-0277, Appeal of Donna M. Heald & a., the court on May 22, 2020, issued the following order:

Having considered the briefs and oral arguments of the parties, the court concludes that a formal written opinion is unnecessary in this case. The intervenors, Donna M. Heald, Regis Miller, Matthew and Amanda Fitch, Larry Gans, Ann Darragh, Tom and Yael DeCapo (collectively, the Durham Residents), and the Durham Historic Association (Historic Association), appeal a decision of the New Hampshire Site Evaluation Committee (SEC) granting the application filed by the petitioner, Public Service Company of New Hampshire d/b/a Eversource Energy (Eversource), for a “Certificate of Site and Facility” (Certificate) for the siting, construction, and operation of a new high voltage electric transmission line between existing substations in Madbury and Portsmouth (the Project). We affirm.

I. Facts

The following facts were either found by the SEC or are drawn from the contents of documents submitted as part of the appellate record. In April 2016, Eversource applied to the SEC for a Certificate to install and operate a 12.9-mile transmission line, comprising aboveground, underground, and underwater segments, traversing portions of Madbury, Durham, Newington, and Portsmouth. The Project was selected by the Independent System Operator of New England (ISO-NE) to address identified transmission capacity needs for the continued reliability of the electric transmission system in the seacoast region. ISO-NE chose the Project, in 2012, as the preferred solution for increasing transmission system thermal capacity, increasing transformer thermal capacity, and improving system voltage performance, because “it is much less costly than the other alternative and addresses the needs in the area.” (Quotation omitted.)

The overhead portion of the Project will be located entirely within existing distribution and transmission rights-of-way. The underground portion will be located in locally-maintained roads, on property in Durham now owned by Eversource, and on other property in Durham and Newington where Eversource has contracted to acquire new easements.

Pursuant to RSA 162-H:9 (2014), the attorney general appointed a Counsel for the Public, and, in late April 2016, a Subcommittee was appointed to consider the application (Subcommittee). See RSA 162-H:4-a (Supp. 2019). After the Subcommittee accepted the application, finding that it contained sufficient information for the purposes of RSA chapter 162-H, public information sessions and, later, public hearings, were held in Durham and Newington. The Subcommittee granted motions to intervene filed by the intervenors and others.

Beginning in late August 2018, the Subcommittee held adjudicative hearings, receiving testimony and exhibits from many witnesses. The Subcommittee heard evidence through November 15, 2018, and deliberated over six days in November and December 2018. Its narrative decision, totaling more than 300 pages, was issued on January 31, 2019.

A. Orderly Development of the Region

Relevant to this appeal, before granting the Certificate, the Subcommittee deliberated about whether the “site and facility will not unduly interfere with the orderly development of the region with due consideration having been given to the views of municipal and regional planning commissions and municipal governing bodies.” RSA 162-H:16, IV(b) (Supp. 2019). In its deliberations, the Subcommittee observed that Newington and Durham had each entered into a Memorandum of Understanding with Eversource “addressing, minimizing, and mitigating” the Project’s “construction impacts.” The Subcommittee conditioned the Certificate upon Eversource’s compliance with those Memoranda of Understanding.

In addition, the Subcommittee observed that, as to the Durham Residents and other intervenors, “the Applicant conducted a comprehensive outreach campaign where it contacted almost every intervenor who raised his/her concerns about the Project’s impact and offered [a] variety of avoidance and mitigation measures that can be implemented to address their concerns.”

Eversource asserted that the Project will not have “an unreasonable adverse effect” on real estate values in the region. Eversource’s expert, Dr. James Chalmers, opined that, as to residential properties, given the “small number of properties” located within 100 feet of the rights-of-way, “there will be no discernable effects in local or regional real estate markets” as a result of the Project. Based upon Chalmers’ testimony and report, the Subcommittee found that the Project will be partially or clearly visible from at least 29 properties, and that “[i]t is reasonable to conclude, depending on the extent of increase in visibility of the Project, that the Project will have some effect on values of some of these properties.”

However, the Subcommittee identified “shortcomings” in the testimony and report. Specifically, the Subcommittee faulted Chalmers for “limit[ing] the area of impact” from the Project to properties located within 100 feet of the

2 rights-of-way and for opining that the value of real estate “will be impacted only if the Project was not previously visible and will become visible from the property or was partially visible and will become clearly visible.” By so doing, the Subcommittee determined, Chalmers “failed to account . . . for significant change in visibility that will not result in clear visibility” and underestimated the number of properties likely to be impacted by the Project.

In light of those shortcomings, the Subcommittee found “it . . . reasonable to conclude that the Project will have some effect on values of additional properties, whether from visibility change or other Project impacts.” Therefore, the Subcommittee conditioned the Certificate upon the creation of a voluntary dispute resolution process, described in more detail below, through which affected property owners could “address and mitigate such impacts.” Under this process, which will be “available to all property owners who can verify the impact on the value of their property” and may be initiated up to two years after the Project’s construction is completed, affected property owners will be able to mitigate impacts or receive financial reimbursement for them. Accordingly, considering Chalmers’ “conclusion that only a limited number of properties [would] be impacted” and that property owners may mitigate those impacts through the voluntary dispute resolution process, the Subcommittee found “that the impacts of the Project on the value of real estate will not unduly interfere with the orderly development of the region.” See id.

B. Public Interest

Also relevant to this appeal, before granting the Certificate, the Subcommittee deliberated about whether granting the Certificate would serve the public interest. See RSA 162-H:16, IV(e) (Supp. 2019). In its deliberations on this subject, the Subcommittee considered the “numerous comments from the Intervenors and members of the public indicating that the Project will have an adverse effect on aesthetics, historic sites, water quality, natural environment, value of real estate, tourism, land use, and public health and safety.” See N.H. Admin. R., Site 301.16(a)-(j) (identifying the factors that must be considered “[i]n determining whether a proposed energy facility will serve the public interest”).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Burrows v. City of Keene
432 A.2d 15 (Supreme Court of New Hampshire, 1981)
Vogel v. Vogel
627 A.2d 595 (Supreme Court of New Hampshire, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Appeal of Donna M. Heald & a., Counsel Stack Legal Research, https://law.counselstack.com/opinion/appeal-of-donna-m-heald-a-nh-2020.