Appeal of Barnard Silver Lake Assoc. Inc.

CourtVermont Superior Court
DecidedJune 7, 2001
Docket229-10-00 Vec
StatusPublished

This text of Appeal of Barnard Silver Lake Assoc. Inc. (Appeal of Barnard Silver Lake Assoc. Inc.) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Appeal of Barnard Silver Lake Assoc. Inc., (Vt. Ct. App. 2001).

Opinion

STATE OF VERMONT

ENVIRONMENTAL COURT

In re: Appeal of Barnard Silver } Lake Association, Inc. } } Docket No. 229-10-00 Vtec } }

Decision and Order on Cross-Motions for Summary Judgment

Appellant Barnard Silver Lake Association, Inc. appealed from a decision of the Zoning Board of Appeals (ZBA) of the Town of Barnard denying Appellant a zoning permit for rock clearing, grading, and seeding, and referring the matter for enforcement. Appellant is represented by Peter M. Nowlan, Esq.; the Town is represented by Joseph S. McLean, Esq.; Thurston Twigg-Smith, Jr., Executive Vice-President of the Persis Corporation, an adjoining landowner, has appeared and represents himself; and James F. Clarke, Jr., an adjoining landowner, has appeared and represents himself.

Appellant and the Town have moved for summary judgment on four of the five questions in the Statement of Questions: #1: whether its October, 1988 permit remained valid in August, 2000; #2: whether Appellant= s grading and seeding in August 2000 satisfied the zoning regulations; #3: whether the ZBA= s issuance of a fine is void for lack of a cease and desist order and lack of notice and opportunity to be heard; and #5: whether the Town has authority to regulate clearing and grading where it does not change the contours of the land or drainage patterns.

The following facts are undisputed unless otherwise noted.

Appellant owns an approximately 2.67 acre lot with frontage on Route 12 and Stage Road in the Lakeshore Overlay zoning district of the Town of Barnard. As of July 7, 1997, the date Appellant acquired the lot, it was not developed and had grown up in weeds and brush. The following year, after commencing work to clear the lot, Appellant filed a zoning permit application on August 25, 1998, for A brush-hogging, grading and re-seeding.@ The Zoning Administrator denied the permit A temporarily pending ZBA approval,@ and referred it to the ZBA, as all development in the Lakeshore Overlay district requires conditional use approval, ' 3.4.2 of the Zoning Regulations1, and all uses other than single and two-family dwellings require site plan approval. ' 5.1.5.

Appellant applied to the Planning Commission on October 5, 1998 for site plan approval. The site plan shows a buffer strip that is ten feet in width by scale, but bears a designation of 10" (inches). The buffer strip appears on the plan only adjacent to the Barnard General Store property and adjacent to Stage Road and Route 12, and not along the Persis Corporation, Universalist Parsonage, or Brown/Finlayson properties. The site plan contains text describing the scope of work as A site clearing.@ The work described on the plan is to remove all rocks and brush from the property, to fill the holes with compacted soil from the site, to compact the top 6 inches, to smooth the grade to a uniform surface, and to dispose of all removed rocks off site. The plan specifically instructs: A do not strip topsoil unnecessarily or within driplines of trees,@ and A remove no trees [of] 4" or greater diameter.@ The plan shows a single access onto Route 12.

The Planning Commission approved Appellant= s site plan at the October 5, 1998 hearing and issued its decision orally, as reflected in its minutes. The Planning Commission does not appear to have reduced its site plan approval to writing, other than by approving the minutes. The Planning Commission imposed the following conditions in the text of its minutes: A the fertilizer needed is 250 to not more than 300 pounds per square acre of 15-8-12, conservation mix seeding, if by June the seeding with a cover crop of oats or heavily mulched with hay and compacted, maintain 10 foot buffer, hay bale and filter-fabric fence [in] place until seeding takes, no burning but chipping on site and no heavy equipment activity between 7 PM and 7 AM.@ Although the 10 foot buffer shown on the site plan did not extend around all the property lines, the parties discussed and Appellant= s representative Mr. Aikens agreed at the hearing that the 10 foot buffer was to extend around all the property lines. Although the Planning Commission discussed requiring mulching and seeding by September 1, 1999, no such condition was imposed in the approval motion voted on by the Planning Commission. The 1998 Planning Commission decision was not appealed, and became final.

As soon as the Planning Commission had acted, the ZBA acted to grant conditional use approval at its hearing on October 8, 1998 and issued its decision orally, as reflected in its minutes. The ZBA does not appear to have reduced its conditional use approval to writing, other than by approving the minutes. The ZBA imposed the following conditions in the text of its minutes: A with the site plan approved by the Planning Commission and with the Planning Commission= s conditions, with the two further conditions that Appellant seek and follow professional guidance on the type and amount of fertilizer needed and that the present access be left as is (that there be no improvement in that access as indicated on the plat approved by the Planning Commission).@ The 1998 ZBA conditional use approval was not appealed, and became final.

The zoning permit application form states that it becomes valid when signed on both sides by the Zoning Administrator and A approved above,@ by the Zoning Administrator= s checking of a box to indicate that the permit had been granted. Although the zoning permit would have been eligible for approval after the conditional use and site plan approvals had been issued, in fact the Zoning Administrator did not issue a zoning permit in 1998. Appellant did not request its issuance nor appeal the fact that it had not been issued, as Appellant did not believe it had to take any additional action to request its issuance.

' 5.0.2 of the Zoning Regulations provides that zoning permits are valid for two years from their date of issuance, except that they expire after one year if no > construction= is begun under the permit, and except that a landowner may request a one-year extension if requested before the expiration of the initial two years. However, as no zoning permit was ever issued in 1998, the duration provisions for zoning permits do not apply. Whether the time is measured to the summer of 1999 or the summer of 2000, Appellant had no zoning permit authorizing it to do the work allowed by the 1998 conditional use approval or site plan approval. We note that there are no duration provisions applicable to the site plan approval or conditional use approval. Those approvals remained in effect and did not expire, even if Appellant had been obligated to acquire a new zoning permit as of the summer of 1999 or 2000. Levy v. Town of St. Albans, 152 Vt. 139, 143-44 (1989). Of course, any new zoning permit would be determined under any changes to the regulations in effect at such later time.

On August 8, 2000, Appellant filed with the Zoning Administrator a new application for a zoning permit for A rock clearing, grading & seeding.@ The Zoning Administrator granted the permit on August 11, 2000, with the limitation that the permit was A approved in accordance with ZBA hearing of 10/8/982 - no other development approved via this permit.@ Before the expiration of the time for appeal, Appellant performed more work on the lot. Mr. Twigg-Smith appealed this permit to the ZBA.

The ZBA acted on the appeal at its September 14, 2000 hearing, and issued its decision orally, as reflected in its minutes. The ZBA does not appear to have reduced this decision to writing, other than by approving the minutes. The ZBA denied the August 8, 2000 permit application on the basis that the 1998 permit and approvals had expired and that therefore the new permit application required a new site plan approval and conditional use approval before it could be issued.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Levy v. Town of St. Albans Zoning Board of Adjustment
564 A.2d 1361 (Supreme Court of Vermont, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
Appeal of Barnard Silver Lake Assoc. Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/appeal-of-barnard-silver-lake-assoc-inc-vtsuperct-2001.