Apex Glass & Sash, Inc. v. City of Seattle
Opinion
Plaintiff, Apex Glass & Sash, Inc., d/b/a Acme Glass & Sash, Inc., brought suit to recover payment for materials and labor furnished defendant Gunther-Shirley-Lane (Gunther) as prime contractor on the Boundary Dam in Pend Oreille County, Washington. Originally, Jack O. Rasmussen Company (Rasmussen), a subcontractor of defendant and also a codefendant, ordered the materials from plaintiff. Plaintiff in turn issued its purchase order for the materials to the Pittsburg Glass Company which shipped the materials directly to Rasmussen at the damsite and billed plaintiff. The materials arrived on or about August 25, 1967. Plaintiff billed Rasmussen on September 25, 1967. In the meantime, Rasmussen lost its subcontract under Gunther.
Subsequently Gunther contacted plaintiff concerning the possibility of the latter installing the materials previously furnished. Plaintiff agreed to do so on a time-and-material 1 basis. Upon completion of the installation, plaintiff billed Gunther for both the installation labor and the materials previously billed to Rasmussen, i.e., $819 (installation), plus $3,193.20 (materials).
Plaintiff’s action against the City of Seattle, for whom the dam was being constructed, and Gunther’s bonding company was dismissed on agreement of the parties. The court rendered judgment against Rasmussen in the amount of $3,193.20 based upon Rasmussen’s original contract with plaintiff, and against Gunther in the amount of $4,012.20 *796 based upon the subsequent time-and-material contract. Only Gunther appeals, contending if the materials were sold and title passed to Rasmussen, as evidenced by the trial court’s judgment against Rasmussen, that judgment should not have been rendered against Gunther for the same materials. We agree. RCW 62A.2-401 provides in part:
(2) Unless otherwise explicitly agreed title passes to the buyer at the time and place at which the seller completes his performance with reference to the physical delivery of the goods, . . . and in particular and despite any reservation of a security interest by the bill of lading
. . . if the contract requires delivery at destination, title passes on tender there.
Consequently, plaintiff must look to Rasmussen for its compensation for those materials, particularly since plaintiff did not comply with RCW 39.08.065 2 requiring a material-man supplying a subcontractor to serve notice upon the prime contractor of the delivery of materials. The judgment against Gunther for the cost of the materials cannot stand.
As for the subsequent contract with Gunther, the work performed thereunder by plaintiff is directly within the *797 purview of RCW 18.27.010. 3 Plaintiff did not comply with the registration requirement, RCW 18.27.080, 4 Murphy v. Campbell Inv. Co., 79 Wn.2d 417, 486 P.2d 1080 (1971), Stewart v. Hammond, 78 Wn.2d 216, 471 P.2d 90 (1970), nor is there any evidence of a substantial attempt made to so comply, Andrews Fixture Co. v. Olin, 2 Wn. App. 744, 472 P.2d 420 (1970); hence, plaintiff’s claim for installation charges is also void. Plaintiff does not come within the exemptions provided in RCW 18.27.090 (5) 5 by its definition, nor subsection (8) thereof by reason of its failure to comply with RCW 39.08.065, supra.
Inasmuch as the foregoing requires reversal of the judgment entered herein, we need not consider Gunther’s additional assignments of error.
Judgment is reversed and the case is dismissed.
Petition for rehearing denied December 29,1971.
Free access — add to your briefcase to read the full text and ask questions with AI
490 P.2d 885 (Apex Glass & Sash, Inc. v. City of Seattle) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.