Apex Engineers & Consultants, Inc. v. Williams Brothers Construction Company, Inc.

CourtCourt of Appeals of Texas
DecidedDecember 23, 2004
Docket01-04-00760-CV
StatusPublished

This text of Apex Engineers & Consultants, Inc. v. Williams Brothers Construction Company, Inc. (Apex Engineers & Consultants, Inc. v. Williams Brothers Construction Company, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Apex Engineers & Consultants, Inc. v. Williams Brothers Construction Company, Inc., (Tex. Ct. App. 2004).

Opinion

Opinion issued December 23, 2004






In The

Court of Appeals

For The

First District of Texas





NO. 01-04-00760-CV





APEX ENGINEERS AND CONSULTANTS, INC., Appellant


V.


WILLIAMS BROTHERS CONSTRUCTION COMPANY, Appellee





On Appeal from County Civil Court at Law No. 4

Harris County, Texas

Trial Court Cause No. 800206





MEMORANDUM OPINION


          In this breach of contract case, appellant, Apex Engineers and Consultants, Inc., (“Apex”) challenges the summary judgment signed by the trial court in favor of appellee, Williams Brothers Construction Company, Inc. (“Williams Brothers”). In a single issue, with three supporting sub-issues, Apex contends that the trial court erred in granting the summary judgment.

          We affirm.

Factual and Procedural History

          Williams Brothers acted as general contractor on a highway project in Hidalgo County under a contract with the Texas Department of Transportation (“TxDOT”). Williams Brothers subcontracted with Apex to supply and install polyethylene liner for a portion of the project at a unit price of a $1.88 per square foot. The subcontract provided that Apex would provide an estimated 15,570 square feet of liner at an estimated cost of $29,271.60 ($1.88 x 15,570). A few days after the subcontract was signed, the parties signed a “subcontract modification,” which served only to increase the estimated quantity and approximate cost of the liner. The estimated amount of liner that Apex was to supply under the modification was increased to 21,100 square feet, which in turn changed the approximate total cost to $39,668 (21,100 x $1.88).           Apex ultimately supplied and installed 18,600 square feet of liner for the highway project. Contending that it owed Apex only the amount of the liner actually installed, Williams Brothers’s position was that the amount due Apex was $34,969 (18,600 x $1.88). Williams Brothers paid Apex $33,219.60 but initially withheld a five percent retainage fee of $1,748.40. The withholding was based on a provision in TxDOT’s standard specifications document, which provides for the withholding of five percent of the amount owed to a contractor until the highway project’s satisfactory completion. Both Williams Brothers’s general contract with TxDOT and the Apex subcontract were subject to the TxDOT standard specifications.

          Apex sued Williams Brothers for breach of the subcontract, alleging that it was owed $6,448.80. This amount represents the difference between the $33,219.60 paid by William Brothers and the estimated total of $39,668 found in the subcontract modification that was, in turn, based on the estimated liner quantity of 21,100 square feet. Apex also prayed for attorney’s fees and costs.

          Williams Brothers moved for summary judgment, asserting that, under the subcontract, it owed Apex only for the amount of liner actually installed multiplied by the fixed per unit (i.e., square foot) price of $1.88. In support of its summary judgment, Williams Brothers offered the subcontract and the subcontract modification. Williams Brothers also submitted summary judgment evidence supporting its contention that it was allowed to withhold the five percent retainage fee, (i.e., $1,748.40), until completion of the project. Williams Brothers also submitted the affidavit of its vice president, evidencing that Williams Brothers had offered to pay Apex the retainage fee when Apex filed suit in exchange for the suit’s dismissal, but that Apex declined to accept the offer. It is undisputed that TxDOT paid Williams Brothers $1,748.40 in December 1993 and that Williams Brothers paid Apex the retainage at the motion for summary judgment hearing in April 1994. Thus, Williams Brothers contends that it has paid Apex all that is owed under the subcontract.

          Apex filed a response to Williams Brothers’s motion for summary judgment and a cross-motion for summary judgment. Apex contends that Williams Brothers owes it, not for the amount of liner actually installed, but for the amount that Williams Brothers “purchased”; that is, the estimated amount of 21,100 square feet listed in the subcontract modification. Apex asserts that such interpretation is required under the plain language of the subcontract. Apex did not contest that the subcontract was subject to the TxDOT general specifications, which allowed Williams Brothers to withhold the retainage.

          In support of its response and cross-motion, Apex offered the affidavit of its president, Charles Schibi. Williams Brothers filed an objection to Schibi’s affidavit, which was sustained by the trial court.

          The trial court granted Williams Brothers’s motion for summary judgment and denied Apex’s cross-motion. The court signed a final summary judgment, providing that Apex take nothing against Williams Brothers and dismissing Apex’s claims with prejudice. Apex appeals the judgment, challenging the trial court’s ruling on the respective motions for summary judgment.

Standard and Scope of Review

          A party moving for traditional summary judgment carries the burden of establishing that no material fact issue exists and that it is entitled to judgment as a matter of law. Tex. R. Civ. P. 166a(c); M.D. Anderson Hosp. & Tumor Inst. v. Willrich, 28 S.W.3d 22, 23 (Tex. 2000). When cross-motions for summary judgment are filed, a reviewing court examines all of the summary judgment evidence presented by both sides, determines all questions presented, and if reversing, renders such judgment as the trial court should have rendered. FM Props. Operating Co. v. City of Austin, 22 S.W.3d 868, 872 (Tex. 2000); Bradley v. State ex rel. White, 990 S.W.2d 245, 247 (Tex. 1999). Each summary-judgment movant must carry its own burden and neither can prevail due to the other’s failure to meet its burden. Guynes v. Galveston County, 861 S.W.2d 861, 862 (Tex. 1993); W.H.V., Inc. v. Assocs. Hous. Fin., LLC, 43 S.W.3d 83, 87 (Tex. App.—Dallas 2001, pet. denied).

Interpretation

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
FM Properties Operating Co. v. City of Austin
22 S.W.3d 868 (Texas Supreme Court, 2000)
W.H v. Inc. v. Associates Housing Finance, LLC
43 S.W.3d 83 (Court of Appeals of Texas, 2001)
Standard Constructors, Inc. v. Chevron Chemical Co.
101 S.W.3d 619 (Court of Appeals of Texas, 2003)
Ash v. Hack Branch Distributing Co., Inc.
54 S.W.3d 401 (Court of Appeals of Texas, 2001)
Bates v. Texas State Technical College
983 S.W.2d 821 (Court of Appeals of Texas, 1999)
Guynes v. Galveston County
861 S.W.2d 861 (Texas Supreme Court, 1993)
M.D. Anderson Hospital & Tumor Institute v. Willrich
28 S.W.3d 22 (Texas Supreme Court, 2000)
Columbia Gas Transmission Corp. v. New Ulm Gas, Ltd.
940 S.W.2d 587 (Texas Supreme Court, 1996)
Universal C. I. T. Credit Corp. v. Daniel
243 S.W.2d 154 (Texas Supreme Court, 1951)
Bradley v. State Ex Rel. White
990 S.W.2d 245 (Texas Supreme Court, 1999)
Inglish v. Prudential Insurance Co. of America
928 S.W.2d 702 (Court of Appeals of Texas, 1996)
Forbau Ex Rel. Miller v. Aetna Life Insurance Co.
876 S.W.2d 132 (Texas Supreme Court, 1994)
MCI Telecommunications Corp. v. Texas Utilities Electric Co.
995 S.W.2d 647 (Texas Supreme Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
Apex Engineers & Consultants, Inc. v. Williams Brothers Construction Company, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/apex-engineers-consultants-inc-v-williams-brothers-texapp-2004.