Apex Control Systems, Inc. v. Alaska Mechanical, Inc.

776 P.2d 310, 1989 Alas. LEXIS 54, 1989 WL 68191
CourtAlaska Supreme Court
DecidedJune 2, 1989
DocketS-2636, S-2658
StatusPublished
Cited by10 cases

This text of 776 P.2d 310 (Apex Control Systems, Inc. v. Alaska Mechanical, Inc.) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Apex Control Systems, Inc. v. Alaska Mechanical, Inc., 776 P.2d 310, 1989 Alas. LEXIS 54, 1989 WL 68191 (Ala. 1989).

Opinion

*311 OPINION

COMPTON, Justice.

Alaska Mechanical, Inc. (“AMI”) is a mechanical contractor engaged in the business of furnishing and installing plumbing, heating and air conditioning systems. Apex Control Systems, Inc. (“Apex”), a mechanical controls contractor, designs, furnishes and installs the devices which regulate heating and air conditioning systems. It is customary for mechanical contractors to subcontract the controls work to controls contractors.

This case arises from two unrelated subcontracts between AMI and Apex: the Adak contract and the Pump Station No. 3 contract.

During the performance of the Adak contract, the parties disagreed as to whether Apex was required under the contract to furnish and install certain controls. Later, following performance of the Pump Station No. 3 contract, a dispute arose as to whether Apex was entitled to additional compensation under that contract for certain contract “extras.”

The disputes were tried together. In written findings of fact and conclusions of law, Judge James A. Hanson held for AMI in the Adak contract dispute and for Apex in the Pump Station No. 3 contract dispute. He designated AMI as the prevailing party and awarded it attorney’s fees and costs.

Apex appeals the judgment on the Adak contract dispute, including the designation of AMI as the prevailing party in the overall litigation. AMI appeals the judgment on the Pump Station No. 3 dispute.

The specific facts pertaining to each contract dispute are set out separately in this opinion.

I. THE ADAK CONTRACT

a. Facts and Proceedings.

In April 1981, the Department of the Navy issued a bid invitation for a project at the Adak Naval Station. The project involved replacement of the plumbing for the chilled water cooling system and replacement of the plumbing for the heating system. In the months following the bid invitation, AMI prepared a bid for the mechanical work on the project. AMI obtained bids from a number of controls contractors for the controls work that would be required under the contract. The bids for the controls work all fell between $105,000 and $119,000.

Apex’s bid of $108,000 specifically excluded “humidifyer [sic] packages and refrigeration controls,” but included “control air for refrigeration controls.” None of the other bids contained similar exclusions.

AMI was awarded the mechanical subcontract and it awarded the controls sub-subcontract to Apex. The fixed-price contract between Apex and AMI includes the following description of the work to be performed by Apex:

ARTICLE II — WORK TO BE PERFORMED
The Subcontractor [Apex] agrees to furnish all materials, labor, tools, equipment, supervision, supplies, transportation, and other things, unless otherwise provided herein, necessary or required to perform, and to perform fully and completely, at the price or prices set forth herein, and all that portion of the work required to be done by the Prime Contractor under the General Contract, as described as follows:
All heating, ventilating and air-conditioning controls as necessary for a complete and operable system as shown and described in contract drawings and specifications as issued under IFB-N62474-80-B-9657 including amendments # 0001 through # 0004 and inparticular [sic] Section 15904.

Immediately below the description of the work to be performed, a handwritten paragraph provides:

Chiller and refrigeration controls are excluded from this subcontract, however control air will be provided.

The work required of AMI and its subcontractors by the general contract included furnishing and installing chilled water system sequencing controls. A chilled water system provides chilled water to the coils of an air conditioning system. The *312 water is chilled by devices known as “chillers”. In this contract, the specifications called for four chillers. The specifications also called for a control mechanism to turn the chillers on and off in sequence with changes in the water temperature. For example, the controls were to activate chiller number 3 when the water temperature rose above 52°, and to turn it off when the temperature dipped below 48°; the controls were to activate chiller number 2 at 54°, and turn it off at 50°.

During the performance of the contract, a disagreement arose between AMI and Apex as to whether Apex was required under its subcontract to provide the sequencing controls. AMI instructed Apex to proceed with the work on the understanding that financial responsibility for the work would be determined at a later date. Sequencing controls were provided by Apex with the help of another subcontractor. Defects in the system designed by Apex could not be corrected, and ultimately new sequencing controls were designed and installed by third parties.

The trial court concluded that AMI was entitled to back charge Apex for the costs incurred to design and install the chilled water system controls. It held that Apex was not entitled to payment for design services and materials furnished with reference to the chilled water system controls.

b. The trial court did not err in finding that the handwritten clause excluding “chiller controls” was not intended by the parties to exclude chilled water system controls.

In its written findings of fact, the trial court stated:

There exists a distinction between “chiller controls” and “chilled water system controls” which is recognized within the construction industry. The contract between AMI and Apex for the Adak Project required Apex to design, furnish and install the “chilled water system controls.” That requirement was not excluded by the oral and/or written bid submitted by Apex to AMI or by agreement of the parties.

Apex contends that the contract did not require it to provide the chilled water system controls and that the trial court erred in finding such a requirement in the contract.

Because the task of interpreting the contract required the trial court to weigh extrinsic evidence, the trial court’s conclusion should be accorded the deference this court accords to findings of fact. Alyeska Pipeline Serv. Co. v. O’Kelley, 645 P.2d 767, 771 n. 2 (Alaska 1982). This court will not set aside the trial court’s findings of fact unless those findings are clearly erroneous, that is, unless this court is left with a definite and firm conviction on the whole record that a mistake has been made. Martens v. Metzgar, 591 P.2d 541 (Alaska 1979).

There seems to be little question that but for the handwritten exclusion, the subcontract would have required Apex to provide the chilled water system controls. The subcontract requires Apex to perform work described as “All heating, ventilating and air-conditioning controls.” 1

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nicdao v. Chase Home Finance
839 F. Supp. 2d 1051 (D. Alaska, 2012)
State v. Jacob
214 P.3d 353 (Alaska Supreme Court, 2009)
Andrus v. Lena
975 P.2d 54 (Alaska Supreme Court, 1999)
Barber v. Barber
915 P.2d 1204 (Alaska Supreme Court, 1996)
Kalenka v. Taylor
896 P.2d 222 (Alaska Supreme Court, 1995)
Shepherd v. State, Department of Fish & Game
897 P.2d 33 (Alaska Supreme Court, 1995)
Pavone v. Pavone
860 P.2d 1228 (Alaska Supreme Court, 1993)
Hillman v. Nationwide Mutual Fire Insurance Co.
855 P.2d 1321 (Alaska Supreme Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
776 P.2d 310, 1989 Alas. LEXIS 54, 1989 WL 68191, Counsel Stack Legal Research, https://law.counselstack.com/opinion/apex-control-systems-inc-v-alaska-mechanical-inc-alaska-1989.