APERM OF SC v. Roof

351 S.E.2d 171, 290 S.C. 442, 1986 S.C. App. LEXIS 469
CourtCourt of Appeals of South Carolina
DecidedNovember 17, 1986
Docket0819
StatusPublished
Cited by8 cases

This text of 351 S.E.2d 171 (APERM OF SC v. Roof) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
APERM OF SC v. Roof, 351 S.E.2d 171, 290 S.C. 442, 1986 S.C. App. LEXIS 469 (S.C. Ct. App. 1986).

Opinion

Cureton, Judge:

*444 Aperm of South Carolina, A Limited Partnership (Aperm), filed a breach of contract action against Alvin R. Roof to recover royalty payments due it under a license agreement. Roof defended, alleging that there was no contract with Aperm to pay royalties. The trial court found a contract and ordered Roof to pay Aperm accrued royalties. We affirm.

The sole issue presented in this appeal is whether a valid contract to pay royalties existed between Aperm and Roof after December 31, 1981, or whether the contract had been previously terminated by Aperm. We hold that a valid royalties contract existed. Roof’s second exception claims error by the trial judge in ordering him to pay Aperm royalties because the product “Aperm” was manufactured by a third party, Aperm Southeast, Inc. (Southeast). It is clear from his brief, however, that his real argument is that the license was assigned by him to Southeast, so that if Aperm has a contract it is with Southeast, not him.

Aperm, the owner of a roof coating composition and application method, entered into an option agreement with Roof on June 18, 1980 granting to Roof the exclusive license to research, develop, manufacture and sell the invention named “Aperm.” The license agreement specified that Roof had the option, after conducting preliminary tests to determine the marketability of the product, of terminating the agreement between June 18,1980 and August 1,1980. If Roof failed to give written notice of termination by August 1, 1980, the license agreement would become “fixed” and the parties would be governed by its terms. The contract provided for a start-up period of a year during which time minimum royalties of $2,400.00 per month were to be paid by Roof to Aperm.

By August 1,1981, Roof was required to present to Aperm a comprehensive manufacturing and marketing program in comformity with guidelines set forth in the agreement. The program was also required to include minimum royalty payments of $4,800.00 per month during the period August 1, 1981 to July 31, 1982, and increased monthly royalty payments thereafter. The marketing and manufacturing program was subject to Aperm’s approval, but disapproval had to be reasonably related to the guidelines set out. The contract stated specifically that if the program provided for the *445 minimum royalties, then objections to the program by Aperm would be subject to arbitration, but if the program failed to provide for minimum royalties, Aperm could cancel the contract.

The agreement also provided that the license was personal (emphasis added) to Roof and that assignment of the license was prohibited absent prior written consent by Aperm. In the event of an assignment, the assignee, would be required to assume all of Roofs obligations under the license agreement. Roof had the right to terminate the agreement on December 31,1980, and each year thereafter by giving written notice to Aperm by December 1 of the year in which termination was desired. Otherwise, the agreement would be automatically renewed each year provided Roof was not in default of any of the agreement’s terms and conditions.

In August 1980, counsel for Roof notified Aperm by letter that Roof had “exercised his rights” under the agreement and was proceeding “to Phase I, i.e., further testing and marketing of Aperm.”

By letter of August 7, 1981, Aperm notified Roof that he was seriously in default under the terms of the license agreement because he had failed to pay the required royalties and furnish it with a manufacturing and marketing program. The letter also advised Roof that the license would be terminated in thirty days if the defaults were not cured. As a result, the parties entered into an agreement on September 3, 1981 which confirmed the continuation of the license agreement and provided, inter alia, for payment of commissions and extension of the time for submission of the manufacturing and marketing program until December 31, 1981.

On January 28, 1982, Aperm forwarded another notice to terminate in consequence of Roof’s failure to pay royalties and for other violations of the license agreement. After this notice, both royalty payments and a marketing program were presented to Aperm, but were refused because both were deemed inadequate. After this notice was sent, much correspondence passed between Aperm, Roof, and Southeast, 1 but no consensus was ever reached regarding the *446 manufacturing and marketing program. In the meantime, Roof and/or Southeast continued to manufacture and sell the product. On August 11,1982, Aperm wrote to Southeast’s attorney advising him that the license would be terminated in thirty days.

The trial judge found that in August 1980, Roof exercised his right to transform the option contract into a “fixed” contract. He further found that “there was a continuing acknowledgement by [Roof] of the fixed contract with its minimum royalties of $4,800.00 per month, notwithstanding [Roof’s] repeated entreaties for a modification thereof.” The judge also found that the actual termination of the contract occurred on August 11,1982 effective September 11,1982. He additionally found Roof owed Aperm minimum royalties of $4,800.00 per month from January through September 11, 1982. He further found that Roof continued to sell the product through the middle of November 1982, and that Aperm was entitled to an accounting for royalties through that date. He entered judgment for Aperm in the amount of $50,400.00

In an action at law, the trial court’s findings of fact will not be disturbed on appeal if there is any evidence to support those findings. Southeastern PVC Pipe Mfg., Inc. v. Rothrock Construction Co., Inc., 280 S. C. 498, 313 S. E. (2d) 50 (Ct. App. 1984).

Roof argues in his brief that he contracted with South Carolina Aperm Associates, a General Partnership, not Aperm of South Carolina, A Limited Partnership. He argues that any assignment of contract rights by the General to the Limited Partnership was in violation of the license agreement and thus Aperm does not have standing to sue in this action. This issue was neither argued before the trial court nor is there an exception that addresses it on appeal. Where the record does not reflect that a point has been raised before the trial court, that point cannot be considered on appeal. Murphy v. Hagan, 275 S. C. 334, 271 S. E. (2d) 311 (1980). We therefore will not address this claim.

Roof next argues that after the license agreement start-up period ended on August 1, 1981, there was then no subsisting contract between him and Aperm *447 because the 1980 option agreement was simply an agreement to enter into a contract after the start-up period, and was therefore unenforceable, citing McLaurin v. Hamer, 165 S. C. 411, 164 S. E. (2d) (1932). We disagree. Neither party contends the license agreement is ambiguous. In the absence of fraud, the construction of a clear and unambiguous contract is a matter of law. Watts v. Monarch Builders Inc., 272 S. C. 517, 252 S. E. (2d) 889 (1979).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stevens & Wilkinson of South Carolina, Inc. v. City of Columbia
762 S.E.2d 696 (Supreme Court of South Carolina, 2014)
Knoxville Medical Investors, Ltd v. National Healthcorp L.P.
385 S.E.2d 110 (Court of Appeals of Georgia, 1989)
Patterson v. I. H. Services, Inc.
368 S.E.2d 215 (Court of Appeals of South Carolina, 1988)
Blanton Enterprises, Inc. v. Burger King Corp.
680 F. Supp. 753 (D. South Carolina, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
351 S.E.2d 171, 290 S.C. 442, 1986 S.C. App. LEXIS 469, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aperm-of-sc-v-roof-scctapp-1986.