APCO CONSTR., INC. v. HELIX ELEC. OF NEV., LLC

2022 NV 31, 509 P.3d 49
CourtNevada Supreme Court
DecidedMay 5, 2022
Docket80177
StatusPublished
Cited by2 cases

This text of 2022 NV 31 (APCO CONSTR., INC. v. HELIX ELEC. OF NEV., LLC) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
APCO CONSTR., INC. v. HELIX ELEC. OF NEV., LLC, 2022 NV 31, 509 P.3d 49 (Neb. 2022).

Opinion

138 Nev., Advance Opinion 51 IN THE SUPREME COURT OF THE STATE OF NEVADA

APCO CONSTRUCTION, INC., A No. 80177 NEVADA CORPORATION; AND SAFECO INSURANCE COMPANY OF AMERICA, Appellants, FIVE) vs. HELIX ELECTRIC OF NEVADA, LLC, MAY 0 5 2022 A NEVADA LIMITED LIABILITY COMPANY, Respondent.

Appeal from a district court judgment after a bench trial in a contract action. Eighth Judicial District Court, Clark County; Elizabeth Gonzalez, Judge. Affirmed.

Fennemore Craig, P.C., and Christopher H. Byrd, Las Vegas; Fennemore Craig, P.C., and John Randall Jefferies, Phoenix, Arizona, for Appellants.

Peel Brimley LLP and Cary B. Domina and Ronald J. Cox, Henderson, for Respondent.

BEFORE THE SUPREME COURT, SILVER, CADISH, and PICKERING, JJ.

SUPREME COURT OF NEVADA

101 1947A 416124. 1,1 N31k OPINION By the Court, SILVER, J.: The covenant of good faith and fair dealing "prohibits arbitrary or unfair acts by one party that work to the disadvantage of the other." State, Dep't of Transp. v. Eighth Judicial Dist. Court, 133 Nev. 549, 555, 402 P.3d 677, 683 (2017) (internal quotation marks omitted). In this appeal, we consider whether the district court properly applied the covenant of good faith and fair dealing when it awarded delay damages to a subcontractor. We also, for the first time, interpret NRS 338.490 and determine whether the subcontractor waived its right to receive delay damages by signing a waiver and release to receive its retention. We conclude that the district court properly determined the covenant of good faith and fair dealing applies here, the contractor breached the covenant, and the subcontractor did not waive its delay claims under NRS 338.490. FACTS AND PROCEDURAL HISTORY The City of North Las Vegas (CNLV) contracted with appellant APCO Construction, Inc.,' for a construction project. Subcontractor and respondent, Helix Electric, Inc., contracted with APCO for the project's electrical work. The project was originally scheduled to be completed on January 9, 2013, but the project was not substantially completed until October 25, 2013. After the original project completion date passed, Helix notified APCO that it reserved the right to receive payment for the additional costs incurred due to the delay. In response, APCO indicated that Helix must timely pursue reimbursement for those costs and provide all related

'We refer to appellants APCO and Safeco Insurance Company of America collectively as APCO. SUPREME COURT OF NEVADA

(0) 1947A 405 2 documentation to APCO, so that APCO could then submit Helix's claim to CNLV. Helix thereafter sent APCO a list of delay costs totaling $72,960. Helix later submitted a revised claim for $102,000 based on the calculation of $640 per day for 32 weeks. APCO created a change order request for Helix's $102,000 delay claim and submitted it to CNLV. APCO also told Helix it was in the process of preparing a time impact analysis, which would "open the door for Helif to present its case. CNLV rejected the change order request because CNLV did not have a contract with Helix. APCO informed Helix it needed backup documentation to reverse CNLV's rejection but did not tell Helix that CNLV rejected the claim on the basis that CNLV did not have a contract with Helix. In fact, at trial, the CNLV construction manager testified that providing backup information would not have changed CNLV's decision "because [the information] still would be coming from a contractor that does not have a contract with the city." Moreover, CNLV expected APCO to include its subcontractors claims in its own claim for general conditions, rather than submit the subcontractors' claims separately. On October 2, 2013, APCO settled its own $1,090,066 delay claim with CNLV for $560,724. As part of the settlement, APCO agreed to forgo any claim, present or future, that may occur on the project. The record shows APCO did not notify Helix that it had settled with CNLV or that CNLV had paid APCO's delay claim. On October 18, 2013, Helix also billed APCO for its retention payment of $105,677 and included a conditional waiver and release upon final payment that indicated a disputed-claim amount of "zero." On November 5, 2013, APCO submitted a revised change order to CNLV seeking a total of $111,847 for Helix's delay claim, which CNLV again

3 rejected. On November 13, 2013, Helix submitted another claim to APCO in the amount of $26,304, accounting for the extended overhead costs for the months of September and October. APCO submitted Ilethes claim to CNLV, which CNLV rejected on grounds that CNLV did not have a contract with Helix and, moreover, CNLV had already settled with APCO. In October 2014, APCO sent a copy of a check in the amount of Helbes retention and an updated unconditional waiver for Helix to sign upon final payment. The waiver—which Helix did not sign—included the retention amount, and Helix added the delay amount to the payment line next to the retention amount. Helix did not list the delay claim as a disputed claim on the waiver, but Helix's president emailed APCO's contract manager expressing concern about Helix's delay claim. Helix's senior vice president also wrote to APCO, explaining that Helix reserved its rights to its delay claim. Helix's president also emailed a promissory note to APCO's contract manager laying out a payment plan for Hethes delay costs. Ultimately, Helix claimed APCO owed $134,724.68 for Helix's delay costs. APCO did not pay Helix's delay costs, and Helix filed the underlying complaint. The district court ruled in favor of Helix after a three-day bench trial, finding that APCO breached the covenant of good faith and fair dealing by not including Helix's delay damages claim as part of APCO's own claim to CNLV and thereafter settling its own claim with CNLV without notifying Helix. Notably, the district court found that CNLV rejected Helix's claims because APCO did not include Helix's claim under its own claim and that APCO waived and released Helix's claim by settling with CNLV. The court further found that under NRS 338.490, the waiver Helix signed applied to retention only and not to Helix's claim for delay

(0) 1947A 406, 4 damages. The district court awarded Helix $43,992.39 in delay damages and $1,960.85 in interest along with attorney fees. APCO appeals. DISCUSSION The primary issue before us on appeal is whether the district court erroneously found Helix was entitled to damages. In addressing this question, we consider, first, whether Helix properly received delay damages pursuant to the covenant of good faith and fair dealing and the subcontract and, second, whether the conditional release and waiver Helix signed precludes it from receiving delay damages from APCO. We give deference to the district court's factual findings and will uphold them so long as they are not clearly erroneous and are supported by substantial evidence. Weddell v. H20, Inc., 128 Nev. 94, 101, 271 P.3d 743, 748 (2012). "Substantial evidence is evidence that a reasonable mind might accept as adequate to support a conclusion." Id. (quoting Whitemaine v. Aniskovich, 124 Nev. 302, 308, 183 P.3d 137, 141 (2008)). We review issues of statutory and contractual interpretation de novo. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2022 NV 31, 509 P.3d 49, Counsel Stack Legal Research, https://law.counselstack.com/opinion/apco-constr-inc-v-helix-elec-of-nev-llc-nev-2022.