Apache Deepwater, LLC v. Double Eagle Dev., LLC

557 S.W.3d 650
CourtCourt of Appeals of Texas
DecidedAugust 23, 2017
DocketNo. 08-16-00038-CV
StatusPublished
Cited by3 cases

This text of 557 S.W.3d 650 (Apache Deepwater, LLC v. Double Eagle Dev., LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Apache Deepwater, LLC v. Double Eagle Dev., LLC, 557 S.W.3d 650 (Tex. Ct. App. 2017).

Opinion

ANN CRAWFORD McCLURE, Chief Justice

In the world of oil and gas, it is no great secret that mineral owners generally prefer to have their minerals gathered and sold. The lease bonus paid at the outset of a mineral lease is nice, but a stream of royalty payments is better. On the other hand, mineral lessees must measure the cost to gather and bring the minerals to market against the expected return. They must prioritize where best to invest the substantial costs of hiring a drilling rig. At the intersection of these sometimes competing interests are three clauses in a typical oil and gas lease: (1) the habendum clause that sets a termination date for the lease unless the lessee is producing minerals from the leasehold; (2) the continuous development clause which similarly requires production or at least drilling activity; and (3) the retained acreage clause that defines what portion of the entire leasehold is protected from termination when the lessee develops some, but not all the land encompassed by the lease.1

Today we are asked to construe a lease containing variants of these clauses. The dispute arises out of a 640-acre leasehold that contains four equal proration units of 160 acres.2 At the end of the lease's primary term, at least one well was producing on each of those four proration units. All *652agree that the primary term of the lease was extended. With the passage of time, however, the wells on three of the 160 acre units stopped producing, and no new wells were developed on those units. In that context, does the one operating well on only one of 160 acre units extend the lease in favor of the lessee for the entire 640 acres, or only for the one proration unit that has an operating well? We conclude the entire leasehold is extended and we reverse the trial court's judgment to the contrary.

FACTUAL AND PROCEDURAL BACKGROUND

On July 11, 1975, the predecessors of Apache Deepwater, LLC (Apache) leased from Gladys Clark the mineral rights to Section 43, Block Y, Abstract 360 of the M. K.&T. RR Co. survey in Reagan County. The lease provided for a primary term of three years. During that primary term, Apache's predecessors drilled and brought into production four wells.3 Consistent with the regulatory scheme at the time, Apache's predecessor divided the 640 acre section into four 160 acre proration units; each of those units had one of the operating wells within its boundaries. At the end of the primary term of the lease in July 1978, all four wells were producing.

Under the habendum clause to the lease, the primary term of the lease was extended "as long thereafter as oil, gas or other hydrocarbons or other minerals or leased substances, or either or any of them, are produced from the leased premises...." In the ensuing years, the wells on three of the four proration units ceased to produce. The wells in the southeast, northeast, and northwest proration units stopped producing in 1999, 2004, and 2008 respectively.4 The Gladys Clark No. A-3 well located in the southwest proration unit operated until July 31, 2010. Before it stopped producing, however, well No. A-5TM was completed in that same proration unit and according to our record is still operating.

Apache or its predecessors did not develop any new wells in the southeast, northeast, and northwest proration units of Section 43. In 2012, the property owner executed mineral leases in favor of Double Eagle Development LLC (Double Eagle) or its predecessors for the portion of Section 43 comprising those three proration units, and those leases have been extended through at least 2018. We refer to these three 160 acre proration units as the Disputed Tracts. This litigation arose after Double Eagle demanded that Apache release its interest to the Disputed Tracts. Apache, however, contended that it still owned the rights to the Disputed Tracts by virtue of its continued production from the well in the southwest proration unit of Section of 43. Double Eagle filed suit seeking a declaration of its rights in the Disputed Tracts. Apache answered and both sides filed competing motions for summary judgment. Both sides agree to the factual history as to when the respective wells were brought into and taken out of production. Both sides agree that the decision here turns on the construction of the original lease that Apache's predecessors signed with the property owner in 1975, *653and neither side believes the lease to be ambiguous.

The parties focus on several provisions in the lease. First, the lease uses the defined term "leased premises" to include all 640 acres of Section 43. The lease then incorporates the term "leased premises" in several other provisions, including the habendum clause which reads:

TO HAVE AND TO HOLD the leased premises for a term of three (3) years from the date hereof, hereinafter called 'primary term,' and as long thereafter as oil, gas or other hydrocarbons or other minerals or leased substances, or either or any of them, are produced from the leased premises or from lands with which the leased premises are pooled or unitized.

The lease itself appears to be a pre-printed form, but it contains several typewritten special provisions that the parties added. One of those includes the three-year term which was typed in after the original term on the pre-printed from was struck out. The stated purpose of the lease includes "drilling, producing and operating wells or mines" on the leased premises. Consistent with that goal, the lease contains a delay rental clause, such that if the lessee had not begun drilling operations within the first year of the lease, additional delay rental payments were due. The lease also contained a "drilling operations" clause which in part provides:

If, at the expiration of the primary term, oil, gas or other minerals are not being produced from the leased premises ... but Lessee is then engaged in operations for drilling or reworking of any well, this lease shall remain in force so long as such drilling or reworking operations are prosecuted, or reworking operations on any well or additional drilling operations are conducted on the leased premises, ... with no cessation of more than sixty (60) consecutive days, and if any such operations result in production then as long thereafter as such production continues.

One of the typewritten inserted provisions reflects an intent to develop the minerals on the property:

11(a) This lease contemplates the reasonable development of the above designated minerals, including the drilling, or mining, or production as the facts may justify. Lessee shall adequately protect the mineral under the above described lands, or acreage pooled therewith, from drainage from the adjacent lands or leases.

The "retained acreage clause" which is central to this case, was also typewritten. The parties agree that its terms are unique at least in the sense that no reported case directly interprets its text:

17.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
557 S.W.3d 650, Counsel Stack Legal Research, https://law.counselstack.com/opinion/apache-deepwater-llc-v-double-eagle-dev-llc-texapp-2017.