APAC-Mississippi, Inc. v. Clardy (In Re Clardy)

190 B.R. 552, 1995 Bankr. LEXIS 1899, 1995 WL 782963
CourtUnited States Bankruptcy Court, N.D. Mississippi
DecidedJune 9, 1995
Docket19-10663
StatusPublished
Cited by2 cases

This text of 190 B.R. 552 (APAC-Mississippi, Inc. v. Clardy (In Re Clardy)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, N.D. Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
APAC-Mississippi, Inc. v. Clardy (In Re Clardy), 190 B.R. 552, 1995 Bankr. LEXIS 1899, 1995 WL 782963 (Miss. 1995).

Opinion

OPINION

DAVID W. HOUSTON, III, Bankruptcy Judge.

On consideration before the court is a complaint for declaratory judgment filed by the plaintiff, APAC-Mississippi, Inc., against the defendant, Bobby Clardy, d/b/a Clardy Construction; answer and a counterclaim for actual, extraeontractual, and punitive damages having been filed by the defendant; all issues having been appropriately joined; and the court having heard and considered same, hereby finds as follows, to-wit:

I.

This court has jurisdiction of the subject matter of and the parties to this adversary proceeding pursuant to 28 U.S.C. § 1334 and 28 U.S.C. § 157. This is a core proceeding as defined in 28 U.S.C. § 157(b)(2)(A), (B), (C), and (O).

II.

On February 1,1991, Clardy entered into a contract with APAC to perform certain paving work in a subdivision being developed by Clardy. After completing the work, APAC billed Clardy the sum of $9,635.25. When Clardy failed to pay the invoice, APAC filed *553 a materialmen’s and contractor’s lien. This was followed by the filing of a complaint to impress the lien in the Chancery Court of Lowndes County, Mississippi. Also named as party defendants to the lawsuit were E. Frank Goodman, trustee, and Eastover Bank for Savings which held a deed of trust encumbering the subdivision. This lawsuit is apparently still pending.

Subsequently, APAC obtained a contract to perform paving work at a Wal-Mart store in Amory, Mississippi. In connection with this contract, APAC contacted Clardy to determine if he would crack-seal the store’s parking lot. Representing APAC during the negotiations with Clardy were Michael Bogue and Stan McCown. According to the uncon-tradicted testimony, Bogue and McCown had authority to act for and on behalf of APAC. After several discussions, Clardy executed a subcontract on July 27, 1992. The subcontract provided that Clardy would perform the crack-seal work at the rate of $.49 per linear foot. It contained a specific typewritten provision to the effect that $.02 per linear foot was “to be applied toward prior debt retirement.” There was a general printed provision in the subcontract, paragraph 17, which was not excised, stating that APAC could setoff the entire payment due under the subcontract against any indebtedness that Clar-dy might owe to APAC. Clearly, the typewritten provision conflicted with the printed provision.

The testimony concerning the subcontract negotiations was reasonably consistent. Everyone was aware that Clardy owed a prior debt to APAC. The APAC representatives both indicated that Clardy expressed concern about getting paid for the subcontract work. McCown testified that he thought Clardy would be paid $.49 per linear foot less the $.02 per linear foot reduction. Bogue indicated that when he inserted the typewritten language that he did not intend to waive the printed provisions in the document. He added that he thought that if Clardy would make satisfactory arrangements to pay the prior debt that the $.02 per linear foot reduction would be the only amount withheld from the subcontract proceeds. Clardy candidly admitted that he knew that the general setoff provisions were in the subcontract when he signed the document.

After completing performance, Clardy submitted a statement to APAC on August 7, 1992, in basically the following form:

12,820 feet @ $.49 per foot $6,281.80
less $.02 per foot toward debt retirement 256.40
Total due $6,025.40

On October 19, 1992, a check from Wal-Mart was received by APAC. Clardy did not expect his payment until APAC had been paid by Wal-Mart. Shortly thereafter, Clar-dy requested payment, but it was refused.

Clardy then contacted his attorney, David Owen. Likewise, APAC contacted its attorney, Dewitt Hicks. These attorneys initiated several discussions in an attempt to resolve the dispute. Hicks stated that he made a settlement proposal calling for Clardy to make a $500.00 down payment on his debt to APAC, presumably from the subcontract proceeds, with the balance of the indebtedness to be paid at the rate of $500.00 per month. A down payment of some amount was apparently significant to APAC. Owen indicated that he proposed a counter offer consisting of the $.02 per linear foot reduction from the subcontract proceeds, plus the retirement of the balance of the indebtedness at the rate of $300.00 per month. Thereafter, Hicks had a promissory note prepared which was generally consistent with Owen’s counter offer. (It did not reflect the $.02 per linear foot reduction.) However, because APAC still insisted on a more substantial down payment, this promissory note was never tendered to Owen or Clardy. Thereafter, the settlement negotiations reached an impasse. Ironically, considering the terms of the offer and the counter offer, the parties were less than $250.00 apart as to the down payment amount.

On October 30,1992, only eleven days after receiving the check from Wal-Mart, APAC, on the advice of its attorney, filed suit in the Chancery Court of Lowndes County requesting a declaratory judgment as to its rights under the subcontract. Hicks testified that it was his intention after filing the lawsuit to request the court for an expedited hearing pursuant to Rule 57, Mississippi Rules of *554 Civil Procedure. This would have allowed the parties to have an early determination of their respective rights under the subcontract. Unfortunately, neither Clardy nor his attorney were agreeable to this procedure.

Clardy filed an answer and counterclaim alleging that APAC was hable for actual, extracontractual, and punitive damages because it had no arguable reason not to pay the net subcontract amount in the sum of $6,025.40.

Shortly thereafter, Clardy filed a voluntary petition for relief under Chapter 11 of the Bankruptcy Code, and removed the state court litigation to this court.

III.

At the conclusion of APAC’s proof, Clardy moved for a directed verdict on the issue of contractual damages. In a bench opinion, the court sustained the motion, offering the following conclusions and reasons:

1. Because the typewritten provision in the subcontract conflicted with the printed provision in paragraph 17, the subcontract was obviously ambiguous. Short of an agreement, there was no way to reconcile the conflicting terms.

2. Because the subcontract was prepared by APAC and because the typewritten provision was inserted by APAC’s representative, Michael Bogue, the subcontract had to be construed more strongly against APAC.

3. The specific typewritten provision should be given more weight than the general printed provisions as recognized by the standards of contract interpretation. See, Restatement, Second, Contracts § 203(d) (1981).

4.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Young v. Harris
N.D. Mississippi, 2024
In Re Wilson
413 B.R. 330 (E.D. Louisiana, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
190 B.R. 552, 1995 Bankr. LEXIS 1899, 1995 WL 782963, Counsel Stack Legal Research, https://law.counselstack.com/opinion/apac-mississippi-inc-v-clardy-in-re-clardy-msnb-1995.