APAC-Atlantic, Inc. v. Owners Insurance Company

CourtDistrict Court, W.D. North Carolina
DecidedSeptember 23, 2024
Docket1:23-cv-00167
StatusUnknown

This text of APAC-Atlantic, Inc. v. Owners Insurance Company (APAC-Atlantic, Inc. v. Owners Insurance Company) is published on Counsel Stack Legal Research, covering District Court, W.D. North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
APAC-Atlantic, Inc. v. Owners Insurance Company, (W.D.N.C. 2024).

Opinion

UNITED STATES DISTRICT COURT WESTERN DISTRICT OF NORTH CAROLINA ASHEVILLE DIVISION 1:23-cv-167-MOC-WCM

APAC-ATLANTIC, INC., ) ) Plaintiff, pro se, ) ) vs. ) ORDER ) OWNER’S INSURANCE COMPANY, ) ) ) Defendant. ) __________________________________________)

THIS MATTER comes before the Court on the parties’ cross Motions for Summary Judgment. (Doc. Nos. 11, 15). I. PROCEDURAL BACKGROUND Plaintiff, APAC-Atlantic (“APAC”) hired Emery Sealco (“Emery”) to install stationary advance warning signage at a road repaving project. APAC was added to Emery’s an insurance policy though Owner’s Insurance Company’s (“Owner’s”) as an additional insured but only with respect to “liability arising out of [Emery’s] work for [APAC].” After installation of the stationary advance warning signs and while APAC was repaving the road, two separate motorcycle accidents happened, resulting in personal injuries to the passengers. A lawsuit was filed against APAC (“the underlying lawsuit”). APAC tendered the defense to Owner’s, which defended the underlying lawsuit under a reservation of rights. However, after extensive discovery and during the pendency of the underlying litigation, Owner’s informed APAC that no indemnity coverage would be provided under the policies because the accidents did not arise out of the work performed by Emery on the project; therefore, APAC was not an additional insured under the Commercial General Liability (“CGL”) policy. Following a mediation in the underlying lawsuit, APAC settled the matter and has now filed this action seeking reimbursement from Owner’s of the settlement amount of the underlying lawsuit plus interest. II. FACTUAL BACKGROUND

1. The Prime Contract On July 2, 2018, Plaintiff, APAC-Atlantic, was awarded a state funded contract from the North Carolina Department of Transportation for the milling, resurfacing and shoulder restoration of various roadways in Haywood and Jackson Counties, North Carolina (“the project”). See (Defendant’s Responses to Plaintiff’s Requests for Admissions (“Def. Resp. to RFA”), Contract attached as Ex. 1 ¶ 1 (Exs. A & B)). The original contract called for payment to APAC totaling $13,052,189.87. (Id.). The contract details all requirements to provide work zone traffic control in sections TC-1 – TC-6. (Id.).TC-1 provides that APAC was to install “Work Zone Advance Warning Signs in

accordance with the detail drawing provided in these plans prior to beginning any other work.” (Id.). That “Work Zone Advance/General Warning Signing” responsibility is identified as Line Item #13 on the Contract Item Sheets for C204188. (Id.) APAC’s bid amount for that item was $66,375.00. (Id.). Line Item #13 involved stationary signage that was to be installed prior to commencement of the pavement work. (Id.). The Contract with NCDOT also contained Line Item #14, designated as Temporary Traffic Control, for which APAC was paid a lump sum of $630,000.00. (Id.). As will be discussed in more detail below, Line Item #14 encompassed the portable signage, including those signs described on TC-2, TC-4 and TC-5 of the contract, that is at the heart of this dispute. Line Item #14 at all times remained APAC’s contractual responsibility. 2. The Subcontract On or about July 24, 2018, APAC entered into a subcontract (“the subcontract”) with Emery. Pursuant to that agreement, Emery subcontracted to install the stationary work zone

advance/general warning signing before the paving work commenced, pursuant to Line Item 13 of the contract between APAC and NCDOT. See (Def. Resp. to RFA ¶ 2, Contract p. 6 of 8, attached as Ex. 2 thereto, and Defendant’s Responses to Plaintiff’s First Set of Interrogatories (“Def Disc. Resp”), ¶ 3 (Exs. C &D)). Emery was paid $44,250.00 to perform Line Item #13. (Id.). The Temporary Traffic Control requirements under Line Item #14 were never subcontracted or delegated to Emery. 3. The Stationary Uneven Pavement Signs Before construction/paving began on the section of U.S. 17 where the accidents forming the basis of this dispute occurred, Emery installed stationary uneven pavement signs at the

direction of and with the approval of NCDOT and APAC. (Def. Resp. to RFA ¶13). The NCDOT log books indicate that Emery installed 15 “Uneven Lanes” signs on U.S. 74 eastbound on August 3, 2023, 15 “Uneven Pavement” signs on U.S. 74 westbound on August 11, 2018, and one “Uneven Pavement” sign on U.S. 74 eastbound on August 11, 2018. See (NCDOT Logbooks (Ex. E)). Placement of those stationary uneven pavement signs was not part of Emery’s initial scope of work but was part of a subsequent verbal agreement between Emery and APAC. (Id. ¶ 15). The DOT inspectors were present when those signs were installed, and the DOT and APAC instructed Emery where to place them. See (Chad Emery Deposition, P. 45 (Ex. F)). Following placement of those stationary signs, Emery was never asked to remain on the project site to monitor pavement activities and was never asked to return to the project to install any additional signage, including portable signs. (Plaintiff’s Responses to Defendant’s Requests for Admissions (“Pl. Resp. to RFA”) ¶¶ 17 & 25 (Exhibit G)). Paving had not begun, and no uneven pavement existed, when Emery installed the stationary uneven pavement signs. (Id. ¶ 5). The paving work did not begin until August 19, 2018. See (timeline (Ex. H)).

4. The Underlying Lawsuit On September 7, 2018, while the paving project was underway on U.S. Highway 17 headed west before the exit for Maggie Valley, Don and Melinda Craft were involved in a motorcycle crash when Craft’s motorcycle lost control as the motorcycle came down off the pavement separating the two westbound lanes. (Def. Resp. to RFA ¶ 10). As a result of the crash, Don Craft ultimately died after several weeks in the hospital and Melinda Craft sustained several serious injuries. (Id.). Two days later, on September 9, 2018, in the same location, Tim and Donna Lozaw were involved in an accident when Mr. Lozaw lost control of his motorcycle on the pavement edge separating the two westbound lanes resulting in injuries to Donna Lozaw. (Id.

¶ 11). Melinda Craft, the Estate of Don Craft, and Donna Lozaw filed a lawsuit on November 14, 2019 in Georgia State Court, which was removed to the United States District Court of the Northern District of Georgia. (Id. ¶ 12). In the underlying lawsuit, Plaintiffs alleged that APAC was negligent in, among other ways, failing to place uneven pavement signs prior to the area where the lanes were uneven so that motorists had advance warning. (Def. Resp. to RFA, Underlying Complaint attached as Exhibit 7 thereto, ¶ 30(f) (Exhibit I)). APAC notified Emery and Owner’s of the underlying lawsuit and demanded that Owner’s defend and indemnify APAC. (Id. ¶ 20). Through correspondence dated January 30, 2020, Owner’s acknowledged receipt of the underlying suit and agreed to payment of APAC’s defense costs pursuant to a reservation of rights. (Id. ¶ 22). W. Curtis Anderson of Downey & Cleveland represented APAC and Owner’s paid the legal fees to defend APAC in the underlying lawsuit. (Id. ¶¶ 24–25). During discovery the investigating officer, Trooper Holcombe, testified that there were no uneven pavement signs along the roadway in the westbound direction in advance of the

stationary uneven pavement signs installed by Emery. See (Trooper Holcombe Deposition, pgs. 36-40 & 49-54 (Exhibit J)). This fact is not in dispute, as APAC admits that they failed to place portable uneven pavement signs in advance of the uneven pavement.. (Pl. Resp. to RFA ¶ 18). Moreover, APAC admits that it did not fulfill its temporary traffic control obligations as set forth in the NCDOT contract and that such acts and/or omissions were a proximate cause of the collisions referenced in the underlying lawsuit. (Id. ¶ 16).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Klaxon Co. v. Stentor Electric Manufacturing Co.
313 U.S. 487 (Supreme Court, 1941)
United States v. Diebold, Inc.
369 U.S. 654 (Supreme Court, 1962)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Anthony Dash v. Floyd Mayweather, Jr.
731 F.3d 303 (Fourth Circuit, 2013)
Fortune Insurance v. Owens
526 S.E.2d 463 (Supreme Court of North Carolina, 2000)
Waste Management of Carolinas, Inc. v. Peerless Insurance
340 S.E.2d 374 (Supreme Court of North Carolina, 1986)
Gilbert v. North Carolina Farm Bureau Mutual Insurance
574 S.E.2d 115 (Court of Appeals of North Carolina, 2002)
State Capital Insurance v. Nationwide Mutual Insurance
350 S.E.2d 66 (Supreme Court of North Carolina, 1986)
Bowles v. Bowles
75 S.E.2d 413 (Supreme Court of North Carolina, 1953)
Pulte Home Corp. v. American Southern Insurance
647 S.E.2d 614 (Court of Appeals of North Carolina, 2007)
Grant v. Emmco Insurance
243 S.E.2d 894 (Supreme Court of North Carolina, 1978)
Davis v. Ltv Steel Co.
716 N.E.2d 766 (Ohio Court of Appeals, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
APAC-Atlantic, Inc. v. Owners Insurance Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/apac-atlantic-inc-v-owners-insurance-company-ncwd-2024.