A.P. Croll & Son, Inc. v. Clark's General Contractors, Inc.

Superior Court of Delaware·Decided April 30, 2015·No. 13C–07–022·Published

Opinion

IN THE SUPERIOR COURT OF THE STATE OF DELAWARE IN AND FOR SUSSEX COUNTY

A.P. Croll & Son, Inc., : C.A. No.: S13C–07–022 RFS Plaintiff :

:

v. :

:

Clark’s General Contractors, Inc., :

Defendant :

MEMORANDUM OPINION

Final Decision and Order

Date Submitted: January 6, 2015

Date Decided: April 30, 2015

Dean A. Campbell, Esquire, Law Office of Dean A. Campbell, LLC, Georgetown Professional Park, North Building, 20175 Office Circle, P.O. Box 568, Georgetown, DE, 19947, Attorney for Plaintiff

Jeffrey J. Clark, Esquire, Schmittinger & Rodriguez, P.A., 414 S. State Street, P.O. Box 497, Dover, DE, 19901, Attorney for Defendant

STOKES, J.

Presently before the Court is a breach of contract action brought by subcontractor, A.P. Croll & Son, Inc., (“Croll”), against general contractor, Clark’s General Contractors, Inc. (“Clark”). Croll seeks to recover losses sustained resulting from work related to site preparation and a paving subcontract related to the construction project for Royal Farms in Georgetown, Delaware. Croll alleges Clark failed to pay Croll for performance of its obligation in accordance with a written construction contract for the completion of highway reconstruction work. Croll seeks payment of $24,188.54, plus interest and reasonable attorney’s fees. Clark maintains Croll did not perform as contractually obligated and is not entitled to recover losses.

Following the bench trial and upon review of the parties’ post-trial briefs, the Court finds Croll is entitled to recover losses sustained in the amount of $5,489.57, plus costs and present and past interest.1 This amount accounts for a deduction for back fill and top soil, affords set-offs for work performed on Gordy Street, the additional stone materials, and the difference between the interest paid and simple interest for payments made by Clark to a subcontractor on behalf of Croll.

1 Interest is to be calculated at the simple legal interest rate. See e.g., O'Riley v. Rogers, 2013 WL 4773076, at *1 (Del. Super. Sept. 4, 2013) (applying the legal interest rate); see also, David L. Finger & Louis J. Finger, Delaware Trial Handbook, § 28.10 (1994).

FACTS AND PROCEDURAL POSTURE In April 2012 Croll entered into a contract, prepared by Clark, in which Croll was to perform work related to highway reconstruction in and around Royal Farms located in Georgetown, Delaware. 2 The Royal Farms project required substantial highway reconstruction work at the intersection of US Route 113 (“113”) and Route 404 (“404”).3 Along 113, 404, and Gordy Street is where most of the work related to the present dispute took place. 4

Emory Hill was hired to oversee the project and Clark was hired as a general contractor to construct the new store. 5 Clark subcontracted with Croll to complete roadwork, including site work within the right-of-way as defined by Delaware Department of Transportation (“Del Dot”), for the agreed upon amount of $298,353.31. 6

As work progressed, incremental payments were made by Clark to Croll. 7 A dispute arose after four applications were paid, totaling $192,880.73, leaving an alleged balance of $105,472.58 owed to Croll.8 In July 2013, Croll filed a Complaint alleging Clark had breached their contract by failing to pay Croll for

2 Pl’s Ex. E. 3 Id. 4 Id. 5 Id. 6 Id. 7 Pretrial Stipulation and Order at ¶ 3–4. 8 Id.; Compl. at ¶ 7.

work performed. 9 Before trial, most of the disputes raised in the Complaint were resolved.

At this juncture, the parties’ contentions center on a handful of transactions.

First, Emory Hill paid Croll directly for work related to the back fill and top-soil on 404 and 113 and subtracted the amount due, $8,884.50, to Clark. 10 Second, Clark paid $11,870 to an alternative contractor, Stanley’s Asphalt, to pave Gordy Street and $520.08 for additional stone material to complete work allegedly within Croll’s responsibility under the contract. 11 Lastly, Croll disputes the payment Clark paid to Shea Concrete, LTD (“Shea”), a party subcontracted by Croll.12 Croll contends Shea was not entitled to interest in the first instance, and in the alternative argues to reduce the amount of interest paid from $2,914.96, calculated at a rate of twenty-four percent, to $339.35 in order to reflect interest calculated at the legal interest rate.13

Croll maintains Clark has breached the contract by failing to pay for work performed. 14 Defendant Clark asserts Croll failed to perform the work as

9 See generally, Compl. (asserting a total sum due to Croll). 10 Pl.’s Post Trial Closing Reply Mem. at 1–2; Def.’s Closing Mem. at 2–3.

11 Pl.’s Post Trial Closing Reply Mem. at 4–5; Def.’s Closing Mem. at 3–4.

12 Pl.’s Post Trial Closing Reply Mem. at 4–5; Pretrial Stipulation and Order at ¶ 4 (alleging “Clark paid Shea Concrete $26,522.34 on behalf of Croll”). 13 Pl.’s Post Trial Closing Reply Mem. at 4–5. 14 See generally, Compl. (seeking damages for failure to pay for work performed); Pl.’s Post Trial Closing Reply Mem.

contractually obligated resulting in a breach of contract.15 As such, Clark asserts funds are not due to Croll, and in the alternative that set-offs are due to Clark.16

Following a bench trial held on November 19, 2014 the Court reserved decision pending receipt of post-trial briefs.

DISCUSSION

Both parties in this matter have abundant experience; both parties are particularly knowledgeable about their chosen profession. Moreover, some of the parties involved in this dispute have a history; some parties even have a prior course of dealings. In fact, Croll and Clark were known to each other.

Looking at the issue globally, both sides are not without fault in terms of how things fell apart. On Clark’s side of the ledger, an amount of $24,188.54 was owed.17 On the other hand, Croll, after making an initial payment failed to pay— even the principal amount—which escalated into the demand of interest by Shea at a rate of twenty-four percent. 18

Moreover, with Croll’s knowledge as a subcontractor in this large project Croll was aware the bills were paid by Clark in order to obtain a release for the

15 Def.’s Closing Mem. at 5. 16 Id. 17 Pl.’s Opening Post Trial Closing Mem. at 2. 18 Pl.’s Post Trial Closing Reply Mem. at 4–5.

Royal Farms project. Although, Croll was not paid in full for the work performed, it is not tenable in the trade to fail to pay subcontractors, such as Shea in this case, based on the failure to receive all funds due under Delaware law. 19 The evidence does not reflect a finding of intent to make Clark’s payment to Croll a condition precedent of Croll’s payment to Shea.20 As such, some of the present controversy regarding Shea could have been avoided had Croll paid Shea when their right to payment matured.

Turning to contract formation, the contract itself was finalized in April. 21 It is important to note Croll’s proposal was submitted one month before the contract was finalized.22 The proposal offered more details, including line items, compared to the scant contract developed in April by Clark.23 The bottom line of Croll’s work was $298,353.31; however, the proposal was not signed by Clark and the

19 See e.g.,Worthy Bros. Pipeline Corp. v. Acierno, 1996 WL 527347, at *2 (Del. Super. July 26, 1996) aff'd, 693 A.2d 1066 (Del. 1997) (resolving a dispute against a subcontractor raised by a paving company finding when a reasonable time expires the paving company’s right to payment matures notwithstanding receipt of payment from a general contractor in the absence of an unambiguous expression of the parties’ intent to make receipt of payment a condition precedent). 20 Pl’s Trial Ex. E; see e.g., Volair Contractors, Inc. v. Coastal Mechanical, Inc.,1986 WL 13982, (Del. Dec. 1, 1986) at *1 (requiring an unambiguous expression of intent to establish a condition precedent). 21 Pretrial Stipulation and Order at ¶ 1. 22 Pl’s Trial Ex. C. 23 Id.

scope of work in the resulting contract was different. 24 Accordingly, the Court finds the proposal is a mere offer and is not a contract. 25

Free access — add to your briefcase to read the full text and ask questions with AI

A.P. Croll & Son, Inc. v. Clark's General Contractors, Inc., (Del. Ct. App. 2015).

A.P. Croll & Son, Inc. v. Clark's General Contractors, Inc. (A.P. Croll & Son, Inc. v. Clark's General Contractors, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Scureman v. Judge
626 A.2d 5 (Court of Chancery of Delaware, 1992)
Friel v. Jones
206 A.2d 232 (Court of Chancery of Delaware, 1964)
Holland v. Hannan
456 A.2d 807 (District of Columbia Court of Appeals, 1983)
Zullo v. Smith
427 A.2d 409 (Supreme Court of Connecticut, 1980)
Acierno v. Worthy Bros. Pipeline Corp.
693 A.2d 1066 (Supreme Court of Delaware, 1997)
Estate of Osborn Ex Rel. Osborn v. Kemp
991 A.2d 1153 (Supreme Court of Delaware, 2010)
Rhone-Poulenc Basic Chemicals Co. v. American Motorists Insurance Co.
616 A.2d 1192 (Supreme Court of Delaware, 1992)
Burbridge v. Howard University
305 A.2d 245 (District of Columbia Court of Appeals, 1973)