Anthony M. Meyerstein, Inc. v. United States

153 F. Supp. 433, 139 Ct. Cl. 305, 1957 U.S. Ct. Cl. LEXIS 100
CourtUnited States Court of Claims
DecidedJuly 12, 1957
DocketNo. 49647
StatusPublished

This text of 153 F. Supp. 433 (Anthony M. Meyerstein, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anthony M. Meyerstein, Inc. v. United States, 153 F. Supp. 433, 139 Ct. Cl. 305, 1957 U.S. Ct. Cl. LEXIS 100 (cc 1957).

Opinion

Whitaker, Judge,

delivered the opinion of the court:

Plaintiff sues for costs allegedly incurred by it as a result of an alleged breach of a contract between it and defendant, under which plaintiff undertook to manufacture for defendant twelve floating cranes, as well as to supply maintenance tools, spare parts, final drawings, and instruction book therefor.

The chief controversy is over whether defendant was obligated to accept delivery of the parts for the cranes as they were manufactured, and before one crane had been assembled and had satisfactorily passed the test provided for. Defendant refused to do so. Plaintiff says defendant was required to do so, and that its breach of this obligation required plaintiff to store the parts at a cost of $190,521.49. This is the main item of its claim. The other items will be stated later.

There is no specific provision of the contract that deals with the subject of the controversy. To resolve the dispute [307]*307it is necessary to consider those contract provisions which are at all pertinent, the purpose for which the cranes were purchased and the place of delivery, and the construction placed upon the contract by the parties to it.

As appears from the correspondence and negotiations between the parties, the cranes were contracted for by the United States for the purpose of shipping them to France for use by the French Government under the Lend-Lease Act. The parts for the cranes were to be manufactured by plaintiff and delivered to defendant for shipment to France, and there assembled by the French Government. This fact should be borne in mind in construing section 1-01 of the General Clauses of the contract, and its other provisions. Section 1-01 reads:

Scope of the Contract. The Contract shall include design and construction of 12 floating revolving cranes of 6 metric ton capacity, as well as the supply of maintenance tools, of spare parts and of final drawings.
One crane out of 12 cranes of 6 metric ton capacity shall be erected, complete with barges, and tested in accordance with procedure described in Section 3-07. After satisfactory completion of the tests the cranes and barges shall be again disassembled and prepared for shipping.

A crane is composed of many parts. These were to be so designed and manufactured by plaintiff as to produce a crane that would satisfactorily do the work desired. Any defective, inadequate, or unsuitable part might prevent the crane from operating satisfactorily. It seems unreasonable to suppose, therefore, that defendant was obligated to accept any part for shipment to France until it knew that the sum of all the parts would produce the thing it wanted, which was a complete crane which would do satisfactorily certain specified work. Having been assured of this, defendant was then ready to accept delivery of the parts for shipment to France, but not before then. It would have been foolish to have shipped parts to France until it had been determined that they were the right parts to make up a crane that would operate satisfactorily.

Take for instance the luffing mechanism and the engine to operate it: plaintiff’s design for them was an mmsual [308]*308design which had not been proven by actual operation to be acceptable. It would have been worse than foolish for the defendant to have shipped them to France until after they had been assembled with other parts into a complete crane and the whole had operated satisfactorily.

There was no provision in the contract requiring defendant to accept the parts before it was ready to ship them to France. Article 10 of the contract, dealing with “delivery and payment when shipping instructions are delayed,” is of no help, because in subparagraph (d) it is provided:

The foregoing paragraphs (a), (b) and (c) shall apply to partial deliveries of completed articles during the term of the contract only if such partial deliveries are required or permitted by the terms of the contract as to delivery.

This provision was a part of the standard “Procurement Division Contract Terms No. 6,” which defendant had said, in accepting plaintiff’s proposal, would be incorporated in the formal contract. It has no application to the present controversy.

There is no other provision of the contract that has any bearing on the controversy.

The construction of the contrapt by the parties, however, clearly shows that both of them understood that defendant was not obligated to accept delivery until after the test of the completed crane had been, or should have been, made.

The contract was executed by plaintiff on September 11, 1945. On October 20,1945, plaintiff wrote defendant a letter, in which it said:

In connection with the above noted contract, we have requested shipping instructions which seemingly are not available at this time. Consequently, it is imperative that we make arrangements to store completed equipment. Inasmuch as our eontraot does not 'provide for this storage, we would appreciate receiving an amendment to the contract authorizing us to provide for such storage facilities at a price to be negotiated and mutually satisfactory. [Italic ours.]

On November 29,1945 plaintiff’s president wrote the company’s agent in Washington, District of Columbia, instruct[309]*309ing him to secure an addendum to the contract containing the following provisions:

1. Contract time extended to May 14,1946 as agreed.
2. Partial shipments can be made as completed.
3. In order to allow partial shipments, it shall be provided that the last crane will be the one to be erected and tested in this country.
4. Warehousing of any parts that are held for shipment shall be for the account of Treasury Procurement.
5. The Contractor agrees that subject to the certification of his erection supervisor, any defects or misfits found in his work after it has been delivered in France will be rectified by him without charge to the Purchaser.

No such addendum was ever made, although afterwards, and on at least four different occasions, the contract was amended in other respects.

Again, on April 16, 1946, plaintiff wrote defendant, in which it said:

We have been unable to procure shipping instructions from the French Supply Council in connection with the various parts of the above noted contract.
* * * ‡ ❖
We are now in a position where our plants and yards are becoming overloaded with the various parts of the cranes and pontoons. We therefore kindly request that you contact the French Supply Council and forward to us firm shipping instructions so that delivery may be started.

In reply to this letter, defendant said:

It is impossible to issue shipping instructions at this time inasmuch as the contract stipulated that one machine would be successfully operated in a test run. * * *

Then, on April 27 plaintiff wrote defendant, in which it said:

_ Reference 2.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
153 F. Supp. 433, 139 Ct. Cl. 305, 1957 U.S. Ct. Cl. LEXIS 100, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anthony-m-meyerstein-inc-v-united-states-cc-1957.