ANTHONY D. BLEVINS v. PECGA, LLC D/B/A PALMER ENGINEERING COMPANY

CourtCourt of Appeals of Georgia
DecidedJune 23, 2023
DocketA23A0061
StatusPublished

This text of ANTHONY D. BLEVINS v. PECGA, LLC D/B/A PALMER ENGINEERING COMPANY (ANTHONY D. BLEVINS v. PECGA, LLC D/B/A PALMER ENGINEERING COMPANY) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ANTHONY D. BLEVINS v. PECGA, LLC D/B/A PALMER ENGINEERING COMPANY, (Ga. Ct. App. 2023).

Opinion

FOURTH DIVISION RICKMAN, C. J., DILLARD, P. J., and PIPKIN, J.

NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed. https://www.gaappeals.us/rules

June 23, 2023

In the Court of Appeals of Georgia A23A0061. BLEVINS et al. v. PECGA, LLC d/b/a PALMER ENGINEERING COMPANY.

PIPKIN, Judge.

Appellants Anthony D. Blevins and Cathy L. Procaskey appeal the entry of

summary judgment in favor of Appellee PEGGA, LLC d/b/a Palmer Engineering

Company on their claim of professional negligence. For the reasons set forth below,

we reverse.

The standard applicable to summary judgment is familiar and well-settled:

“Summary judgment is warranted when any material fact is undisputed, as shown by

the pleadings and record evidence, and this fact entitles the moving party to judgment

as a matter of law.” Strength v. Lovett, 311 Ga. App. 35, 39 (2) (714 SE2d 723)

(2011). On appeal from the grant of summary judgment, we apply a de novo standard of review, construing the evidence in a light most favorable to the non-movant. See

Latson v. Boaz, 278 Ga. 113, 113 (589 SE2d 485) (2004).

Here, Appellants hired an architectural firm to design a residence to sit on a

parcel of land in Cartersville, Georgia. The architectural firm turned to a general

contractor, Housing Trends, to construct the residence; Housing Trends, in turn,

retained Appellee to provide professional engineering services for the design and

construction of the house. Of note, the plans provided by Appellee lacked any notes

pertaining to the elevation of the house relative to the detached garage.

Housing Trends started construction on the home and poured the footings and

foundation walls in March 2016, but was eventually fired from the project; two other

general contractors followed. Around the time that Housing Trends was fired,

Appellant Blevins learned “about a challenge with the construction in that wood was

going to be below grade when construction was completed.” One of the subsequent

builders attempted to address the issue, but the house was ultimately constructed with

wood below grade “because of [Appellee’s] structural design.” An inspection showed

that the house did not comply with the relevant building codes and that Appellants

would not have been able to obtain a certification of occupancy.

2 After construction, Appellants brought this professional negligence action

against Appellee, claiming that its structural drawings “failed to properly address the

elevation of the floor framing with respect to the final adjacent exterior grade, which

resulted in the [residence] being built with significant grading, floor framing, and

foundation issues.” In short, Appellants “sue[d] because the final grade of their

property was above the bottom of the wood floor framing,” which required extensive

structural remediation to correct In support of their action, Appellants retained expert

witness Tony Ganooni, who was critical of the lack of detail in the structural

drawings and testified that it was the placement of the detached garage relative to the

location of the house that “caused the major issue with the walls being lower than

grade.”

Appellee moved for summary judgment, asserting that in order to recover “for

engineering malpractice [a plaintiff] must plead and prove that the [engineer’s] plans

and specifications were followed” but that “the undisputed evidence show[ed] that

[Appellee’s] plans were not followed by the builder.” (Emphasis supplied.) In support

of its motion, Appellee pointed to its structural drawing depicting “the finished grade

and the floor joists” in the relevant area, which, Appellee said, “clearly require the

floor framing . . . to be constructed above and not touching the finished exterior

3 grade[.]” In response, Appellants argued that genuine issues of material fact

precluded summary judgment, highlighting the fact that Appellee’s own engineer

testified that Housing Trends – the original contractor on the project – had, in fact,

constructed the residence according to plan. Appellants argued in the alternative that,

even if the builder had not strictly adhered to structural designs, Appellee could still

be liable if it was reasonably foreseeable that a builder could misinterpret the

structural drawings; Appellants asserted that testimony from their numerous experts

created a fact question on this issue. The trial court ultimately sided with Appellee,

granting summary judgment because Appellants had failed to “come forward and

point to evidence showing that the . . . construction of [the] house was entirely

consistent with [Appellee’s] plans.” Appellants challenge this ruling on appeal.

1. We begin by noting that the record transmitted to this Court was not limited

to that which was before the trial court at the time that summary judgment was

decided. Rather, after the trial court ruled, Appellants filed a “Notice of Filing of

Evidence in Support of their Notice of Appeal” and enlarged the record to include

multiple additional depositions and discovery documents; the additional filings

4 expanded the record three-fold.1 As Appellee correctly notes in its brief, Appellants

attempt to use this expanded record to support their appeal; indeed, nearly all of

Appellants’ brief – including their statement of material facts and argument sections

– rely in no small part on these thousands of additional pages. However, “[t]his is a

court for correction of errors of law, and our decision must be made upon the record

sent up by the trial court. Appellate courts will review only evidence presented to the

trial court before its ruling on the motion. Additional evidence will not be admitted

on appeal.” (Citations and punctuation omitted.) Cornwell v. Kirwan, 270 Ga. App.

147, 151 (2) (606 SE2d 1) (2004).

While Appellants purportedly present a “Restated Statement of Material Facts”

in their reply brief that is limited “to evidence considered by the trial court at the time

of the trial court’s ruling on summary judgment,” this does not correct the argument

sections of Appellants’ principle brief, which also rely heavily on the expanded

record. Despite understanding that they had relied on materials that were not before

the trial court at the time that summary judgment was decided, Appellants have not

filed an amended brief before this Court. In short, Appellants’ brief does not

1 The record before this Court totals over three-thousand pages; the record before the trial court, however, was less than one-thousand pages.

5 adequately demonstrate where evidence supporting their claim to reversal was

presented to the trial court, and we will not cull the record on their behalf. Luong v.

Tran, 280 Ga. App. 15, 18 (2) (633 SE2d 797) (2006) (“[I]t is axiomatic that

[Appellant] bears the burden of showing error affirmatively by the record.”). For this

reason alone, we need not consider Appellants’ arguments on appeal. See Stewart v.

Johnson, 358 Ga. App. 813, 814 (856 SE2d 401) (2021) (recognizing that this Court

need not consider enumerations that are not supported by proper references to the

record). Nevertheless, we exercise our discretion and consider the merits of

Appellants’ arguments. Id.

2. Appellants argue that the trial court erred in granting summary judgment to

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bodin v. Gill
117 S.E.2d 325 (Supreme Court of Georgia, 1960)
Latson v. Boaz
598 S.E.2d 485 (Supreme Court of Georgia, 2004)
Luong v. Tran
633 S.E.2d 797 (Court of Appeals of Georgia, 2006)
Covil v. Robert & Co. Associates
144 S.E.2d 450 (Court of Appeals of Georgia, 1965)
Cornwell v. Kirwan
606 S.E.2d 1 (Court of Appeals of Georgia, 2004)
Strength v. Lovett
714 S.E.2d 723 (Court of Appeals of Georgia, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
ANTHONY D. BLEVINS v. PECGA, LLC D/B/A PALMER ENGINEERING COMPANY, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anthony-d-blevins-v-pecga-llc-dba-palmer-engineering-company-gactapp-2023.