Antero Resources Corporation v. Tejas Tubular Products, Inc.

CourtDistrict Court, S.D. Ohio
DecidedJuly 6, 2022
Docket2:19-cv-00804
StatusUnknown

This text of Antero Resources Corporation v. Tejas Tubular Products, Inc. (Antero Resources Corporation v. Tejas Tubular Products, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Antero Resources Corporation v. Tejas Tubular Products, Inc., (S.D. Ohio 2022).

Opinion

UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF OHIO EASTERN DIVISION

ANTERO RESOURCES CORPORATION,

: Plaintiff,

Case No. 2:19-cv-804

v. Judge Sarah D. Morrison

Magistrate Judge Kimberly A.

Jolson

TEJAS TUBULAR PRODUCTS, : INC., et al.,

Defendants.

OPINION AND ORDER This matter is before the Court on the motions for summary judgment filed by Defendants Ken Miller Supply, Inc. and Ken Miller Supply of W. Va., Inc. (together, “KMS”), and by Tejas Tubular Products. (ECF Nos. 94, 101.) The motions are ripe for ruling.1 I. BACKGROUND This case deals with the fallout from a failed horizontal “fracking” oil well. Plaintiff Antero Resources Corporation’s Wehr 3H well lost pressure after steel production casing ruptured during a pressure test. Production casing is used to maintain hydraulic pressure inside this type of well. Antero believes the casing failure occurred because of a manufacturing defect resulting in casing that was

1Tejas has requested oral argument. (ECF No. 101.) Because the Court does not believe oral argument would be helpful, that request is DENIED. noncompliant with the required American Petroleum Industry (“API”) 5CT specifications. KMS, a distributor of oilfield supplies including tubing and casing products,

supplied the casing to Antero for use in the Wehr 3H well. Tejas manufactured the casing. KMS and Tejas deny any liability to Antero. A. The Contracts There are five separate contracts at issue. Four of the contracts are between Antero and KMS, and one is between KMS and Tejas. Work Order. To complete the Wehr 3H well, Antero issued a Request for Quote (“RFQ”) seeking a supply of, among other products, casing that met API 5CT

specifications. (ECF No. 79-1, RFQ, PageID 1299–1310; ECF No. 80-4, Waltz Dep., PageID 2120–21, 2281–82.) Antero’s RFQ required a manufacturer’s warranty on all products supplied. (RFQ, PageID 1304–07.) KMS responded to the RFQ and represented that it could fulfill Antero’s requirements. (RFQ, PageID 1310.) Tejas would manufacture and KMS would supply the casing to Antero. (ECF No. 79-1, PageID 1288–91, 1306–07.) Antero and

KMS then executed a Work Order that incorporated the RFQ’s product specifications and warranty requirements – including a representation by KMS that the casing was warranted by the manufacturer, Tejas. (See, RFQ, PageID 1299– 1307; ECF No. 100-3, Work Order, PageID 12212–17; ECF No. 79-1, Dye Dep., PageID 1101–04.) Relevant here, KMS agreed to supply: 5.5 [inch] P-110-pipe to be certified to meet API specification 5CT with supplementary requirement SR16 and that no pipe is to have yield strengths exceeding 140,000 pounds. There has to be a process where [KMS] regularly inspect[s] the casing (a third party not associated with the tubular provider is preferred) and randomly test[s] casing properties to validate they are conforming to API specification 5ct w[ith] sr16.

(RFQ, PageID 1307; Work Order, PageID 12216.) Master Services Agreement. Antero and KMS then entered into a Master Services Agreement (“MSA”). (ECF No. 1-1, MSA.) The previously executed Work Order was incorporated into the MSA. (Id., PageID 15.) Sales Order Confirmation. KMS then contacted Tejas and placed an order for the required casing. (ECF No. 81-1, Sales Order Confirmation, PageID 2883.) KMS told Tejas that the casing was for resale to Antero, so Tejas knew that Antero was the end user. (ECF No. 78-1, Khandavelli Dep., PageID 468–49; ECF No. 79-1, Dye Dep., PageID 1122; ECF No. 81-1, PageID 2890.) According to the Sales Order Confirmation, Tejas agreed to “[p]rocess [the casing] per API 5CT Latest Edition Specifications.” (Sales Order Confirmation, PageID 2883.) Tejas was to perform various inspections and tests on the casing to ensure conformance with Antero’s specifications. (ECF No. 81-1, PageID 2888–2901; See generally, ECF No. 101, Tejas Mot., PageID 13353–54 (citing inspection and test results).) Sales Order. KMS and Antero subsequently executed their own Sales Order memorializing Antero’s purchase of the casing. The Sales Order included pricing and limited remedy and warranty disclaimer provisions. (ECF No. 80-4, Sales Order, PageID 2291–92.) Partial Settlement Agreement. After the production casing ruptured, KMS and Antero entered into a partial settlement agreement in which KMS paid Antero $1,200,000, subject to a refund if Antero is later satisfied that KMS, Tejas, and any

third parties are not liable for the casing failure. (ECF No. 1-2, Settlement Agreement, PageID 32.) Antero was required to provide information to KMS as requested and Antero agreed that it would not plug the well for a period of time. (Id.) B. The Casing Failure After installing the Tejas casing into its Wehr 3H well, Antero ran a pressure test in preparation for operation. A 4-foot split occurred somewhere along a joint or

the body of the casing. (ECF No. 91-1, Hansen Dep., PageID 8576; ECF No. 89-1, Malloy Dep., PageID 6150, 6172.) The casing, which Antero argues was supposed to withstand a 14,530-psi burst, failed at roughly 10,837 psi – 75 percent of its burst rating. (ECF No. 88-1, Mason Dep., PageID 5843–44.) The parties dispute whether API 5CT standards required the casing to withstand 14,530-psi; Tejas contends that it only had to test the casing up to 10,000 psi of pressure. (See, ECF No. 91-1,

Hansen Dep., PageID 8616.) The parties’ experts disagree on the cause of the casing failure. Antero’s primary expert, John Hadjioannou, believes that a manufacturing defect caused the casing failure. (ECF No. 90-1, Hadjioannou Dep., PageID 6708.) He opines that the culprit is a “cold weld,” a defect that is “nearly indetectable, if not impossible to detect.” (Id., PageID 6689.) Tejas’s experts, on the other hand, believe that “fatigue” of the casing due to improper movement during installation caused the failure. (ECF No. 91-1, Hansen Dep., PageID 8577–78; Malloy Dep., PageID 6251–52.) They argue that the casing

could have been damaged while being transported, stored, or prepared for installation. (Hansen Dep., PageID 8480–81, 8618–19.) For its part, KMS argues that some error on Antero’s part caused the failure. (See, ECF No. 94, PageID 9273.) The one consensus among the experts is that it is difficult to determine the cause of the failure with certainty without retrieving the casing. (See e.g., Hansen Dep., PageID 8577; ECF No. 99-1, Luo Dep., PageID 10506–08; ECF No. 94, KMS

Mot., PageID 9295 n.7.) Antero attempted and failed to retrieve the casing from the well. (ECF No. 80-4, PageID 2190.) But even without the casing, the cause of the failure can be investigated. Tejas expert Kenneth Malloy testified that in roughly 75 percent of his investigations the casing is not retrieved from the well, but he can still determine the likely cause of failure in each case – retrieving the defective casing is “just an added bonus.” (Malloy Dep., PageID 6127–28, 6150.)

After the conclusion of the investigations, Antero determined that the Wehr 3H well was irreparable and did not take any further remedial action. (ECF No. 87- 4, PageID 5597.) Roughly four years have passed since the initial casing failure, and Antero has received an order from the Ohio Department of Natural Resources requiring it to plug and abandon the well. (ECF No. 112-1, ODNR Order.) C. Procedural Background Antero brought this suit against KMS and Tejas in March 2019. (ECF No. 1, Compl.) It brings claims against KMS for: Breach of Express Warranty (Count I);

Breach of Implied Warranty in Contract (Count III); Negligence under the Ohio Products Liability Act (OPLA) (Count VII); and Supplier Nonconformance with Representations under the OPLA (Count VIII).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Adickes v. S. H. Kress & Co.
398 U.S. 144 (Supreme Court, 1970)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Daubert v. Merrell Dow Pharmaceuticals, Inc.
509 U.S. 579 (Supreme Court, 1993)
Hdm Flugservice Gmbh v. Parker Hannifin Corporation
332 F.3d 1025 (Sixth Circuit, 2003)
Evanston Insurance Co. v. ATOFINA Petrochemicals, Inc.
256 S.W.3d 660 (Texas Supreme Court, 2008)
Fresh Coat, Inc. v. K-2, Inc.
318 S.W.3d 893 (Texas Supreme Court, 2010)
Savedoff v. Access Group, Inc.
524 F.3d 754 (Sixth Circuit, 2008)
Meritor Automotive, Inc. v. Ruan Leasing Co.
44 S.W.3d 86 (Texas Supreme Court, 2001)
Manon v. Tejas Toyota, Inc.
162 S.W.3d 743 (Court of Appeals of Texas, 2005)
FLS Miljo, Inc. v. Munters Corp.
682 F. Supp. 2d 681 (N.D. Texas, 2010)
ROCK HILL MECHANICAL, INC. v. Liebert Corp.
707 F. Supp. 2d 998 (E.D. Missouri, 2010)
Goodyear Tire & Rubber Co. v. Lockheed Martin Corp.
622 F. App'x 494 (Sixth Circuit, 2015)
CoMa Insurance Agency, Inc. v. Safeco Insurance Company
526 F. App'x 465 (Sixth Circuit, 2013)
O'Neill v. Showa Denko K.K.
655 N.E.2d 767 (Ohio Court of Appeals, 1995)
Bobb Forest Products, Inc. v. Morbark Industries, Inc.
783 N.E.2d 560 (Ohio Court of Appeals, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
Antero Resources Corporation v. Tejas Tubular Products, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/antero-resources-corporation-v-tejas-tubular-products-inc-ohsd-2022.