ANR v. Wesco, Inc.

CourtVermont Superior Court
DecidedOctober 18, 2017
Docket61-6-16 Vtec
StatusPublished

This text of ANR v. Wesco, Inc. (ANR v. Wesco, Inc.) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ANR v. Wesco, Inc., (Vt. Ct. App. 2017).

Opinion

STATE OF VERMONT SUPERIOR COURT ENVIRONMENTAL DIVISION Environmental Division Unit Docket No. 61-6-16 Vtec

Agency of Natural Resources, Petitioner

v. DECISION ON THE MERITS Wesco, Inc., Respondent

This matter arises out of the alleged release in 2014 of diesel fuel (a hazardous material) into surface water, groundwater and land of the state, and Respondent Wesco, Inc.’s (Respondent) alleged failure to investigate, report or respond to the release and a failure to train staff for release response, all at or on property at 56 Pearl Street, Essex Junction, Vermont. In a May 3, 2016 Administrative Order (AO),1 the Vermont Agency of Natural Resources (ANR) alleges violations of the Vermont Waste Management law, 10 V.S.A. § 6616, and Vermont’s Underground Storage Tank Rules (UST Rules). The AO sets out factual allegations describing Respondents’ prohibited release and failure to investigate, report or respond to the release and failure to train staff. The AO does not seek further remediation; however, ANR seeks administrative penalties of $34,000 for the violations. ANR also directs that Respondent stop using Bio-Solve in response to petroleum releases. On July 1, 2016, Respondent requested a hearing on the AO with this Court. The Court conducted merits hearing at the Vermont Superior Court, Costello courthouse in Burlington, Vermont on May 26, 2017. Appearing at the trial were Randy J. Miller, II, Esq. and John Zaikowski, Esq. representing the Agency of Natural Resources and Tristram J. Coffin, Esq. representing Respondents.

1 The AO was filed with the Court on June 24, 2016.

1 Findings of Fact Based upon the evidence presented at trial, the Court renders the following Findings of Fact and Conclusions of Law. 1. Respondent owns a Champlain Farms fuel station and convenience store at 56 Pearl Street, Essex Junction, Vermont. 2. On July 4, 2014, a customer spilled approximately 1 gallon of diesel when fueling a vehicle. 3. The same day, the Vermont Department of Public Safety received a citizen complaint about the spill. Steven Simoes, an Environmental Analyst with ANR’s Hazardous Waste Program and a member of the State Spill Team, responded to the complaint. 4. Mr. Simoes discovered that because the release was under two gallons of diesel, the store manager understood it to be nonreportable. The incident was therefore not reported to ANR. 5. A store employee had treated the spill with a cleaning agent called Bio-Solve. Approximately one gallon of Bio-Solve was mixed with ten gallons of water. 6. Bio-Solve is a surfactant and dispersant. While petroleum products such as diesel do not normally mix with water, a surfactant acts to reduce the surface tension of water, allowing petroleum molecules to mix with water. A dispersant allows those petroleum molecules to then spread out in the water. 7. Bio-Solve is not intended for capture or remediation of petroleum releases. Rather, it is a cleaning agent which is intended to remove stains at the completion of remediation. 8. ANR had previously told Respondent a number of times not to apply Bio-Solve directly to a spill, but instead, to contain and absorb spills using an absorbent material such as Speedi-Dry. The Speedi-Dry should then be cleaned up and managed as a hazardous waste. ANR told Respondent that Bio-Solve should only be used as a final clean up measure. At the time of the release, Respondent’s own internal protocol called for applying Speedi-Dry to contain a spill, and then using Bio-Solve afterwards if necessary. 9. The Bio-Solve mixture was poured onto the pavement where the diesel spill occurred, presumably washing the diesel and Bio-Solve mixture into a catch basin connected to an oil /water separator located in the parking lot of the facility.

2 10. From the evidence presented at trial, it is not entirely clear whether the Bio-Solve / water mixture was applied to liquid diesel that remained on the ground, or whether some or all of the diesel had already run down the storm drain at the time the Bio-Solve / water mixture was applied. 11. Respondent retained ENPRO Services, Inc. to investigate and remediate the oil / water separator. Through this work, ENPRO discovered on July 11, 2014 that the oil / water separator was installed without a baffle. Without the baffle, petroleum discharged to the separator would not be contained within the separator and would flow through the system into the Essex municipal stormwater system. 12. The Essex municipal stormwater system discharges to the Sunderland Brook. 13. Respondent repaired the deficiency by installing the necessary baffle. 14. Respondent retained environmental consultant KAS to respond to the release. KAS determined that there was no evidence that petroleum impacted subsurface soil. 15. No evidence was provided that petroleum impacted groundwater. Because the spill ran into the storm drain, either with or without the help of the Bio-Solve; the oil / water separator on the drain was not functioning; and the storm drain leads to Sunderland Brook, some or all of the spill must have entered the brook. 16. As required by a subsequently issued Notice of Alleged Violation (NOAV), Respondent engaged in a substantial retraining program of its employees on spill remediation. 17. Respondent ceased use of Bio-Solve as a cleaning agent. 18. ANR issued an administrative order (AO) dated May 3, 2016, alleging four violations related to the release. 19. ANR’s cost of enforcement included approximately $765.56 attributable to Steven Simoes, Environmental Analyst, Hazardous Waste Program; $638.22 of Chief Environmental Enforcement Officer, Department of Environmental Conservation, Sean McVeigh’s time; and $370 of Environmental Analyst, UST Program, Thomas Edward Unkles’ time. 20. Respondent has three prior violations of 10 V.S.A § 8003 or related rules, permits, orders or assurances of discontinuance in the prior seven years.

3 Determining Violations and Penalty Assessment When a respondent requests a hearing on an AO, we have the authority to determine whether the alleged violation occurred. 10 V.S.A. § 8012(b)(1). ANR carries the burden of proving the alleged violations by a preponderance of the evidence. Id. § 8013(a). If ANR meets this burden, we are required to “determine anew the amount of a penalty” that should be assessed against the respondent challenging the ANR order. Id. § 8012(b)(4). We therefore review the evidence before the Court and determine an appropriate penalty assessment, pursuant to the eight subsections of 10 V.S.A. § 8010(b)(1)–(8). ANR, and this Court in this proceeding, must consider seven factors when assessing a penalty: (1) the degree of actual or potential impact on public health, safety, welfare, and the environment resulting from the violation; (2) the presence of mitigating circumstances, including unreasonable delay by the Secretary in seeking enforcement; (3) whether the respondent knew or had reason to know the violation existed; (4) the respondent’s record of compliance; (5) [Repealed.] (6) the deterrent effect of the penalty; (7) the State’s actual costs of enforcement; and (8) the length of time the violation has existed.

10 V.S.A. § 8010(b)(1)–(8). The maximum penalty for each violation is $42,500, plus $17,000 for each day a penalty continues. Id. § 8010(c)(1). Generally, ANR treats multiple violations of the same permit, or related violations generally, as one violation when calculating penalties. We take the same approach in this case, and analyze the four violations as a single violation. The State may also “recapture economic benefit” that the violator may have derived from the violation, up to the total maximum penalty allowed of $170,000. Id. § 8010(c)(2). In an effort to standardize penalties and ensure a fair process, ANR enforcement officers use a form that is based on the seven factors.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 6602
Vermont § 6602(17)
§ 6616
Vermont § 6616
§ 8003
Vermont § 8003(a)
§ 8010
Vermont § 8010(b)(1)
§ 8012
Vermont § 8012(b)(1)
§ 8013
Vermont § 8013(d)

Cite This Page — Counsel Stack

Bluebook (online)
ANR v. Wesco, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/anr-v-wesco-inc-vtsuperct-2017.