ANR Production Co. v. Westburne Drilling, Inc.

581 F. Supp. 542, 80 Oil & Gas Rep. 14, 1984 U.S. Dist. LEXIS 19016
CourtDistrict Court, D. Colorado
DecidedFebruary 29, 1984
DocketCiv. A. 82-A-2194
StatusPublished
Cited by13 cases

This text of 581 F. Supp. 542 (ANR Production Co. v. Westburne Drilling, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ANR Production Co. v. Westburne Drilling, Inc., 581 F. Supp. 542, 80 Oil & Gas Rep. 14, 1984 U.S. Dist. LEXIS 19016 (D. Colo. 1984).

Opinion

MEMORANDUM OPINION AND ORDER

ARRAJ, District Judge.

This diversity action arises from a contract between plaintiff ANR Production Company and defendant Westburne Drilling, Inc., to drill four oil and gas wells in North Dakota. Serious drill pipe problems interfered with the drilling of these wells and their related sidetracks. ANR seeks damages based upon defendant’s alleged breach of contract, breach of warranty, negligence, and wanton and willful negligence. Plaintiff also seeks a judgment declaring invalid the contract’s exculpatory provisions. Westburne denies all liability to ANR and counterclaims for unpaid materials, replacement costs of damaged pipe and interest, attorneys’ fees, litigation costs and expenses.

Defendant now moves for partial summary judgment and asks this Court to dismiss as a matter of law, all but one claim in ANR’s complaint. Both parties tendered exhaustive briefs on the motion and oral argument was heard on February 17, 1984. I am now prepared to rule.

FACTUAL BACKGROUND

ANR, an oil and gas development company, is a Delaware corporation with its principal place of business in Texas. Defendant is a drilling contractor, incorporated under the laws of the State of Montana, with its principal place of business in Colorado. On October 23, 1980, ANR and Westburne entered into a written agreement for the drilling of oil and gas wells in Dunn County, North Dakota. The standardized language in the contract was taken from an International Association of Drilling Contractors (IADC) Daywork Drilling Contract form. In general, Westburne agreed to provide the drilling rig, the drill pipe and the personnel to conduct drilling activities at a set cost per day. Defendant was to perform its work in accordance with ANR’s orders and directions, and with due diligence and care.

Four wells and three sidetracks were drilled under the contract: Askew 1-14, Askew 1-14A, Hansen 1-11 and Hansen 1-11A. Only one well, Askew 1-14, was completed to total depth. Although it was a dry hole, Westburne is not responsible for its failure to produce. Another well, Hansen 1-11 A, was completed in a secondary objective about 3000 feet shallower than planned. Most importantly, the drilling of three of these wells — all but Askew 1-14A — was impeded by repeated drill pipe failures. ANR alleges that the drill pipe was fatigued before the contract was signed and holds Westburne accountable for the washouts, drilling interruptions and *545 costly fishing expeditions. 1 Plaintiff seeks damages based upon defendant’s purported breach of contract, breach of warranty and negligence.

Westburne denies all liability and moves for partial summary judgment. Defendant contends that four of ANR’s five claims for relief must be dismissed as a matter of law. First, Westburne argues that the exculpatory provisions in the contract are enforceable and compel summary judgment on ANR’s declaratory relief claim (Fifth claim for relief). Defendant also urges that the exculpatory provisions bar plaintiff from asserting its negligence claim (Third claim for relief). ANR’s Fourth claim for relief, based upon wanton and willful negligence, should be dismissed because any negligence on the part of the driller is solely attributable to plaintiff under the loaned servant doctrine. Finally, Westburne maintains that ANR’s damages must be limited as a matter of law. Defendant insists that its contractual duty was fulfilled with the first satisfactory drill pipe inspection, and any alleged non-conforming pipe thereafter was not Westburne’s responsibility. Additionally, Westburne asks this Court to deny ANR any recovery of “consequential damages”, including the cost of drilling a replacement well, rig rental, fishing costs, additional wages, and materials purchased due to delay.

I

Under Rule 56, Fed.R.Civ.P., summary judgment may be entered when there is no genuine issue of material fact outstanding. Adickes v. S.H. Kress & Company, 398 U.S. 144, 157-59, 90 S.Ct. 1598, 1608-09, 26 L.Ed.2d 142 (1970); Luckett v. Bethlehem Steel Corp., 618 F.2d 1373, 1383 (10th Cir.1980). Because it is a drastic remedy, the movant must establish entitlement to summary judgment beyond a reasonable doubt. Norton v. Liddel, 620 F.2d 1375, 1381 (10th Cir.1980). In addition, all pleadings, affidavits, and depositions must be construed liberally in favor of the party against whom the motion is made. Mustang Fuel Corp. v. Youngstown Sheet & Tube Co., 516 F.2d 33, 36 (10th Cir.1975). Thus, where different inferences can be drawn from conflicting affidavits or documents, the law is clear the summary judgment should not be granted. United States v. Diebold, Inc., 369 U.S. 654, 655, 82 S.Ct. 993, 994, 8 L.Ed.2d 176 (1962); Romero v. Union Pacific Railroad, 615 F.2d 1303, 1309 (10th Cir.1980).

In accordance with these principles, I grant defendant’s motion for partial summary judgment on ANR’s Third and Fifth claims for relief. I deny the motion with respect to claims One, Two and Four.

II

Before addressing defendant’s first argument for partial summary judgment, a preliminary choice-of-law question requires resolution. I must determine whether Colorado, Texas or North Dakota law governs the interpretation of the contract. The issue arises because the underlying agreement was negotiated and signed, in part, in Texas and Colorado, and was to be performed in North Dakota.

“In a diversity case a federal court must apply the conflict-of-law rules of the state in which the court sits.” Becker v. Marketing and Research Consultants, Inc., 526 F.Supp. 166, 169 (D.Colo.1981); see Klaxon Co. v. Stentor Electric Manufacturing Co., Inc., 313 U.S. 487, 496-497, 61 S.Ct. 1020, 1021-22, 85 L.Ed. 1477 (1941). Colorado has adopted the “most significant relationship” test for conflict-of-law questions in contract actions. Wood Bros. Homes, Inc. v. Walker Adjustment Bureau, 601 P.2d 1369, 1372-73 (Colo.1979). Under the Restatement {Second) approach, the objective “is to locate the state having the ‘most significant relationship’ to the particular issue.” Id. at 1372. This is *546 determined according to the factors set forth in Section 188:

a. The place of contracting;
b. The place of negotiation of the contract;
c. The place of performance;
d.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
581 F. Supp. 542, 80 Oil & Gas Rep. 14, 1984 U.S. Dist. LEXIS 19016, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anr-production-co-v-westburne-drilling-inc-cod-1984.