Anr Pipeline Company v. Federal Energy Regulatory Commission, Mobil Exploration & Producing North America, Inc. v. Federal Energy Regulatory Commission

894 F.2d 1396
CourtCourt of Appeals for the D.C. Circuit
DecidedFebruary 6, 1990
Docket88-1707
StatusPublished

This text of 894 F.2d 1396 (Anr Pipeline Company v. Federal Energy Regulatory Commission, Mobil Exploration & Producing North America, Inc. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anr Pipeline Company v. Federal Energy Regulatory Commission, Mobil Exploration & Producing North America, Inc. v. Federal Energy Regulatory Commission, 894 F.2d 1396 (D.C. Cir. 1990).

Opinion

894 F.2d 1396

282 U.S.App.D.C. 356

ANR PIPELINE COMPANY, Petitioner,
v.
FEDERAL ENERGY REGULATORY COMMISSION, Respondent.
MOBIL EXPLORATION & PRODUCING NORTH AMERICA, INC., et al., Petitioners,
v.
FEDERAL ENERGY REGULATORY COMMISSION, Respondent.

Nos. 88-1707, 88-1794.

United States Court of Appeals,
District of Columbia Circuit.

Argued Jan. 9, 1990.
Decided Feb. 6, 1990.

Timm L. Abendroth, F.E.R.C., with whom Catherine C. Cook, General Counsel, and Joseph S. Davies, Deputy Sol., F.E.R.C., were on the brief, Joanne Leveque and Samuel Soopper, F.E.R.C., for respondent.

Bernard A. Foster, III, with whom Daniel F. Collins was on the brief, for petitioner ANR Pipeline Co. in No. 88-1707.

Douglas F. John, with whom Jay G. Martin was on the brief, for petitioners Mobil Oil Exploration and Producing North America, Inc. et al. in No. 88-1794.

Before WALD, Chief Judge, RUTH B. GINSBURG, Circuit Judge, and ROBINSON, Senior Circuit Judge.

Opinion for the Court filed by Circuit Judge RUTH B. GINSBURG.

RUTH B. GINSBURG, Circuit Judge:

These consolidated cases arise from a contract dispute between petitioner gas-producer Mobil Exploration & Producing North America, Inc. (Mobil) and petitioner gas-purchaser ANR Pipeline Company (ANR). Mobil, alleging that the contracts governing its gas sales to ANR expired on October 24, 1980, sought a price increase effective retroactively as of that date. The Federal Energy Regulatory Commission (FERC or Commission) granted Mobil a rate increase effective February 24, 1986--thirty days after Mobil applied for the increase--rather than October 24, 1980, as Mobil had requested.

Both ANR and Mobil invite our review of the Commission's disposition: ANR contests the applicability of the higher rate and FERC's conclusion that Mobil could raise the rate unilaterally; Mobil challenges FERC's refusal to make the increase effective from the alleged contract expiration date. We grant ANR's petition for review because the Commission's determination that the higher rate applies did not reflect reasoned decisionmaking. We therefore remand, vacating the Commission's orders in the interim, without addressing ANR's other arguments and without considering Mobil's petition.

I.

To place the facts of these cases in context, we first briefly describe, in relevant part, the pricing scheme for natural gas established by the Natural Gas Act (NGA) and the Natural Gas Policy Act of 1978 (NGPA). The NGPA contains two sections here implicated governing the maximum lawful price for natural gas, sections 104 and 109. Section 104, setting the lower of the two ceiling prices, applies to gas that was "committed or dedicated to interstate commerce [as that term is defined by the NGPA] on November 8, 1978, and for which a just and reasonable rate under the Natural Gas Act was in effect on such date for the first sale of such natural gas." 15 U.S.C. Sec. 3314.1 The higher section 109 price, as germane here, can be obtained if the gas fits within the descriptions of either of two subsections: subsection 109(a)(2), which applies to gas committed or dedicated under the NGPA and not subject to an NGA rate on November 8, 1978, see 15 U.S.C. Sec. 3319(a)(2); or subsection 109(a)(3), which applies to gas not committed or dedicated under the NGPA and not subject to an existing contract on November 8, 1978. See 15 U.S.C. Sec. 3319(a)(3).

Complicating the scheme, the NGA and NGPA define "committed or dedicated" to interstate commerce differently. Under the NGPA provision in point, gas from the Outer Continental Shelf is, by definition, "committed or dedicated" to interstate commerce. See 15 U.S.C. Sec. 3301(18)(A)(i). However, the second inquiry under subsection 109(a)(2), i.e., was an NGA rate in force on the critical November 8, 1978 date, turns on whether the gas was, on that date, "committed or dedicated" under the NGA, as opposed to the NGPA; gas is "committed or dedicated" under the NGA if, and only if, deliveries of the gas have commenced. See Tenneco Explorations, Ltd. v. FERC, 649 F.2d 376, 378-81 (5th Cir.1981).

Turning to a synopsis of the case, in 1971, ANR's predecessor-in-interest (ANR) and Mobil (or its predecessors) entered into advance payment agreements that gave ANR the right to purchase all gas that Mobil produced from Block 306 on the Outer Continental Shelf. These agreements provided that the purchases would be effected through individual contracts from time to time. Mobil Exploration and Producing N. Am., Inc., 43 F.E.R.C. p 61,228 at 61,601 & n. 2 (1988). In 1972 and 1974, Mobil and ANR entered into four separate contracts, in which Mobil agreed to sell ANR specific quantities of gas. Shortly after the parties entered into each of these contracts, FERC issued certificates of public convenience and necessity to authorize the sales.

Since the enactment of the NGPA in 1978, ANR has paid Mobil the maximum price provided by section 104. So long as the 1972 and 1974 contracts were in force, this rate was indisputably correct, for the gas met both section 104 criteria: The gas was committed or dedicated under the NGPA because it was produced on the Outer Continental Shelf, and it was subject to an NGA rate because deliveries continued pursuant to agreements made before 1978.

On January 24, 1986, Mobil filed applications proposing certificate amendments to authorize collection of the higher section 109 price.2 Mobil argued that, on or about October 24, 1980, the previous contracts had expired because Mobil had provided ANR the full volumes of gas specified under the contracts. Mobil maintained that its continued deliveries since that date, its acceptance of the section 104 price, and its execution of amendments to the contracts in 1981 and 1983 all had been made under the mistaken belief that the contracts were still in force. Mobil conceded that its continued deliveries since October 1980 obligated it to continue to sell gas to ANR. Mobil claimed nonetheless that it was entitled to the higher price retroactive to October 24, 1980, because on that date, the 1972 and 1974 contracts having expired, deliveries of "new" gas began.

ANR intervened in opposition to Mobil's request and argued that the post-1980 deliveries were merely continued sales of Block 306 gas, all of which had been dedicated to ANR under the advance payment agreements, and the implementing contracts and certificates. ANR also challenged, specifically, the accuracy of Mobil's claim that the contracts expired on October 24, 1980. See 43 F.E.R.C. at 61,101 & n. 1.

FERC rejected ANR's arguments that, prior to November 1978, all reserves underlying Block 306 had already been committed and dedicated to ANR by virtue of the advance payment agreements and subsequent contracts. The post-1980 gas, the Commission held, constituted a new stream of delivery pursuant to no previous agreement, and not gas already dedicated to interstate commerce within the meaning of the NGA. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
894 F.2d 1396, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anr-pipeline-company-v-federal-energy-regulatory-commission-mobil-cadc-1990.