Anr Pipeline Company v. Federal Energy Regulatory Commission

863 F.2d 959, 274 U.S. App. D.C. 270, 1988 U.S. App. LEXIS 16761
CourtCourt of Appeals for the D.C. Circuit
DecidedDecember 13, 1988
Docket87-1340, 88-1030
StatusPublished
Cited by3 cases

This text of 863 F.2d 959 (Anr Pipeline Company v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anr Pipeline Company v. Federal Energy Regulatory Commission, 863 F.2d 959, 274 U.S. App. D.C. 270, 1988 U.S. App. LEXIS 16761 (D.C. Cir. 1988).

Opinion

Opinion for the Court filed by Circuit Judge RUTH BADER GINSBURG.

RUTH BADER GINSBURG, Circuit Judge:

In a December 1986 opinion and order, designated Opinion No. 258, the Federal *960 Energy Regulatory Commission (FERC or Commission) determined that petitioner ANR Pipeline Company (ANR) should no longer retain its minimum bill (billing for volumes not in fact taken by the customer) for sales of natural gas. ANR Pipeline Co., 37 F.E.R.C. 1161,263 (1986), reh’g denied, 38 F.E.R.C. 1161,221 (1987). ANR, which also used the minimum bill quantity in calculating its rates, replaced that no-longer-valid figure with one reflecting actual sales volumes. In other words, it eliminated the minimum bill altogether. The instant case concerns the revised tariff sheets ANR submitted in asserted compliance with Opinion No. 258. In those sheets, ANR made two adjustments relevant here: (1) it eliminated all tariff language under which it had billed certain customers for minimum quantities of natural gas; and (2) it made a corresponding adjustment to remove the reflection of those minimum quantities in the calculation of its rates.

FERC rejected the rate adjustment as in conflict with Opinion No. 258 and with the filed rate doctrine. ANR Pipeline Co., 39 F.E.R.C. ¶ 61,232, reh’g denied, 40 F.E.R. C. 1161,067 (1987). ANR seeks our review of that rejection. Because the Commission has not satisfied us of the rationality of its orders rejecting ANR’s rate adjustment, we grant ANR’s petition, vacate the orders under review, and remand the case to the Commission for further proceedings.

I.

ANR owns and operates an interstate natural gas pipeline system that sells natural gas for resale to local distribution companies primarily in Michigan and Wisconsin. Its largest customer, accounting for about 45 percent of ANR’s sales, is Michigan Consolidated Gas Company (MichCon). Pursuant to the Natural Gas Act (NGA), 15 U.S.C. § 717c (1982), and the Department of Energy Organization Act, 42 U.S.C. § 7172(a)(1)(C) (1982), all of ANR’s sales are subject to FERC’s authority, and the Commission is charged with assuring that ANR’s rates are “just and reasonable.”

ANR sells gas under rate schedules that contain both demand and commodity components. The demand charge is payable each month regardless of the volume of gas actually purchased; the commodity charge is levied on each one thousand cubic feet of gas actually purchased. Prior to Opinion No. 258, ANR’s commodity component encompassed, in addition to all of ANR’s variable costs, 50 percent of the pipeline’s fixed costs; the other 50 percent of fixed costs was assigned to the demand component of ANR’s rates. 1

While ANR’s full requirements customers — those purchasing their entire gas supply from ANR — paid the commodity charge only on gas actually received, the pipeline’s two partial requirements customers, Mich-Con and Michigan Gas Utilities Company (MGU), were subject to a “minimum bill” regime. They were obligated to pay ANR, in each contract year, an amount equal to the fixed-cost portion of the commodity rate 2 times the greater of (1) the volume actually purchased by the customer, or (2) a “minimum bill quantity” (MBQ) specified by contract. In fact, MGU’s purchases did not fall below its MBQ, but MichCon’s did, and by a considerable amount. 3

MichCon therefore was paying, because of the minimum bill regime, a share of fixed costs on large volumes it did not take. This fact was reflected by ANR in the calculation of its then-current filed rates. Rates are determined by dividing the pipeline’s cost of service by the estimated quan *961 tity of gas its customers are projected to buy. In calculating the fixed-cost commodity charge unit rate, ANR used MichCon’s MBQ as that customer’s estimated quantity. This yielded rates lower than those that would have obtained had ANR used MichCon’s projected and actual gas purchases, for dividing the cost of service by higher volumes produces lower rates.

In Opinion No. 258, FERC addressed (1) the design for ANR’s sales rates, and (2) ANR’s minimum bill. The Commission directed ANR to use a “modified fixed variable” design for its rates; this design assigned to the demand component all fixed costs except return on equity and related income taxes, and fixed production and gathering costs. Complementing the new rate design, which assured ANR recovery of a greater portion — but not all — of its fixed costs, the Commission ordered elimination of ANR’s fixed-cost minimum bill. See 37 F.E.R.C. at 61,749-51, 61,753, 61,-755. FERC ordered ANR to “file ... revised tariff sheets to reflect the determinations made in [Opinion No. 258].” Id. at 61,757. 4

In its compliance filing ANR eliminated the fixed-cost minimum bill from its commodity charge, and it made a related change. In calculating the fixed-cost component of its new commodity rate, ANR replaced MichCon’s MBQ, which ANR had used in its then-current rate filing, with the actual sales volumes ANR was projecting for that customer. 5 This replacement of a high MBQ with low projected volumes substantially boosted the per unit commodity rate. 6

FERC rejected the compliance filing, principally on the ground that use of the lower projected volumes would result in an increase in sales rates not authorized by Opinion No. 258. ANR Pipeline Co., 39 F.E.R.C. It 61,232 (1987). “The upshot of the Commission’s order was that ANR was required, for the moment, to continue relying on the volumes that had been applicable to calculating the minimum bill in calculating the fixed-cost component of its commodity rate.” Brief for Respondent at 9.

The Commission stated its position more completely when ANR unsuccessfully petitioned for rehearing:

In Opinion No. 258, the Commission ... did not authorize ANR to alter the billing determinants used to calculate the commodity rate, but stated that ANR’s demand rate, as set forth in the modified fixed-variable rate design, assures ANR recovery of all fixed costs it should appropriately recover.... To allow ANR, at this time, to lower its fixed commodity quantity below that [currently on file] would be in direct conflict with Opinion No. 258. It would also conflict with the filed rate doctrine, which provides that no natural gas company may lawfully charge or collect a rate in excess of the rate properly on file and in effect. However, ANR may file for a rate increase to reflect the reduced volumes under section 4 of the Natural Gas Act.

ANR Pipeline Co., 40 F.E.R.C. ¶ 61,067, at 61,204-05 (1987) (footnotes omitted).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
863 F.2d 959, 274 U.S. App. D.C. 270, 1988 U.S. App. LEXIS 16761, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anr-pipeline-company-v-federal-energy-regulatory-commission-cadc-1988.