ANR B Wesco, Inc.

CourtVermont Superior Court
DecidedDecember 15, 2017
Docket60-6-16 Vtec
StatusPublished

This text of ANR B Wesco, Inc. (ANR B Wesco, Inc.) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ANR B Wesco, Inc., (Vt. Ct. App. 2017).

Opinion

STATE OF VERMONT SUPERIOR COURT ENVIRONMENTAL DIVISION Environmental Division Unit Docket No. 60-6-16 Vtec

Agency of Natural Resources, Petitioner

v. DECISION ON THE MERITS Wesco, Inc., Respondent

This matter arises out of Respondent Wesco, Inc.’s (Respondent) alleged release in 2011 of gasoline (a hazardous material) into surface water, groundwater and land of the state; Respondent’s alleged failure to install appropriate overfill protection, failure to install cathodic protection, failure to make documents, records and report available, and failure to report a suspected release all at or relating to property at 56 Pearl Street, Essex Junction, Vermont. In a May 3, 2016 Administrative Order (AO),1 the Vermont Agency of Natural Resources (ANR) alleges violations of the Vermont Waste Management law, 10 V.S.A. § 6616, and Vermont’s Underground Storage Tank Rules (VUST Rules). The AO sets out factual allegations describing Respondent’s prohibited release and associated failures. The AO does not seek further remediation; however, ANR seeks administrative penalties of $106,466.35 for the violations.2 On July 1, 2016, Respondent requested a hearing on the AO with this Court. The Court conducted a merits hearing at the Vermont Superior Court, Costello Courthouse in Burlington, Vermont on June 15 and 16, 2017. Appearing at the trial were Randy J. Miller, II, Esq. and John Zaikowski, Esq. representing the Agency of Natural Resources and Tristram J. Coffin, Esq. representing Respondent.

1 The AO was filed with the Court on June 24, 2016. 2 This includes $97,000 in penalties set out in the AO, in addition to $9,466.35 to cover the cost of enforcement.

1 Findings of Fact Based upon the evidence presented at trial, the Court renders the following Findings of Fact and Conclusions of Law. 1. Respondent owns the Champlain Farms fuel station and convenience store at 56 Pearl Street, Essex Junction, Vermont. 2. On May 24, 2011, the ANR Department of Public Safety’s Vermont Hazardous Materials Response Team was notified by the Essex Junction Fire Department that there was a concern of elevated gasoline vapors in the area of the Post Office Square Shopping Plaza off of Pearl Street in Essex Junction, Vermont. 3. Respondent’s technician had been dispatched to the site to investigate possible sources of inventory discrepancy. 4. Upon inspection, ANR discovered explosive levels of petroleum vapors within catch basins of a storm drain system on the Shopping Plaza property. 5. The Shopping Plaza occupants include retail and commercial businesses open to the public. There is also a post office at the Shopping Plaza. 6. The Fire Department evacuated the Shopping Plaza and closed the businesses due to the threat of explosion. 7. Agency personnel inspected the spill buckets for Respondent’s underground gasoline storage tanks. 8. By the end of the inspection, the owners of the Shopping Plaza had brought in a consultant and installed a ventilation system on the storm drain where the gasoline vapors had been detected. 9. On the morning of May 25, 2011, Thomas Unkles, an Agency representative, performed an inspection. Mr. Unkles was accompanied on the inspection by David McQuade, Wesco’s Director of Environmental Compliance. 10. In the afternoon, Respondent has its tanks and underground piping system inspected by a private contractor, Tanknology, Inc. 11. On May 26, 2011, Jerry Tanner, Wesco’s technician, performed a leak inspection.

2 12. Agency personnel returned to the site and alleged that a faulty O-ring was the likely source of the release. Mr. Tanner, however, testified that based on his inspection the O-ring could not have been the cause of the release. Ultimately, no conclusive or compelling evidence was presented to indicate the cause or duration of the release. 13. On May 27, 2011, Respondent’s representatives reported to the Agency the inventory records. 14. On June 1, 2011, Agency personnel returned to the facility and observed the installation of additional monitoring wells by Respondent’s consultant. 15. On June 3, 2011, Agency personnel requested copies of inventory reconciliation records for the facility’s gasoline tanks for the period of January 2011 until June 3, 2011 be brought to a meeting scheduled for June 6, 2011. 16. On June 6, 2011, Agency personnel met with Respondent’s representative and consultant to discuss remedial steps at the facility. 17. On June 8, 2011, the Agency issued Respondent a Notice of Alleged Violation (NOAV) with compliance directives to immediately pump, empty and cease operation of the gasoline tanks at the facility, and to remove the underground storage tanks from the ground and allow contractors access to remove free product and petroleum contaminated soils from beneath and around the tanks. 18. On June 9, 2011, Agency personnel reviewed the boring log and monitoring well construction diagrams prepared and submitted by Respondent’s consultant. The Agency also applied for an Emergency Order (EO) ordering Respondent to immediately empty underground storage tanks and cease operation of dispensing activities, and within five days to remove underground storage tanks, contaminated soils, and free product, and to properly dispose of these materials. 19. On June 16, 2011, the Environmental Division issued the EO requested by the Agency. 20. In cooperation with the ANR and the Fire Department, Respondent emptied and removed all underground storage tanks from the facility, removed contaminated soils from beneath and around the tanks, and disposed of those materials.

3 21. The Agency estimated that 2,600 gallons of product was released. But, this estimate was based entirely on inventory discrepancies, which may or may not be caused by a release. The Court therefore finds the estimate based on inventory records alone inconclusive. 22. In its “Site Investigation and Corrective Action Report,” Respondent’s environmental consultant noted that the amount of contaminant removed in the initial venting of the storm drain is unknown, but estimated that approximately 95.7 gallons of gasoline was removed in later venting. Ex. 28 at 12. The report also notes that contaminated liquids and solids were removed from the site in the initial response, but gives no estimate as to the amount of product removed at that time. Id. at 4. In addition, the report offers a high estimate of 1,592 gallons of gasoline removed from soils around the site. Id. at 18. 23. The site has been a gas station since the 1950’s and some of the contaminated soil samples contained MTBE, a compound that was used in gasoline for a period of time prior to 2007. This suggests that some of the contamination occurred in the past. Determining what contamination is attributable to the release in 2011 and what was historic contamination complicates whether a significant release occurred. 24. It is also unclear when the 2011 release began. 25. ANR issued an administrative order (AO) dated May 3, 2016, alleging five violations related to the release. 26. ANR’s cost of enforcement included approximately $9,466.35, attributable to the time spent by the Agency’s environmental analysts, enforcement officer, and waste management and prevention representative. 27. Respondent has three prior violations of 10 V.S.A § 8003 or related rules, permits, orders or assurances of discontinuance in the prior seven years.

Determining Violations and Penalty Assessment When a respondent requests a hearing on an AO, we have the authority to determine whether the alleged violation occurred. 10 V.S.A. § 8012(b)(1). ANR carries the burden of proving the alleged violations by a preponderance of the evidence. Id. § 8013(a). If ANR meets this burden, we are required to “determine anew the amount of a penalty” that should be assessed against the respondent challenging the ANR order. Id. § 8012(b)(4). We therefore

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 6616
Vermont § 6616
§ 8003
Vermont § 8003(a)
§ 8010
Vermont § 8010(b)
§ 8012
Vermont § 8012(b)(1)
§ 8013
Vermont § 8013(d)

Cite This Page — Counsel Stack

Bluebook (online)
ANR B Wesco, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/anr-b-wesco-inc-vtsuperct-2017.