Another Attic, Ltd v. Plains Builders, Inc., Wendy White, as Independent of the Estate of G. Tim White, Formerly D/B/A White Associates Architecture, and Chavez Concrete Company

Court of Appeals of Texas·Decided December 6, 2010·No. 07-08-00312-CV·Published

Opinion

NO. 07-08-0312-CV

IN THE COURT OF APPEALS

FOR THE SEVENTH DISTRICT OF TEXAS AT AMARILLO

PANEL C

DECEMBER 6, 2010

ANOTHER ATTIC, LTD., APPELLANT V.

PLAINS BUILDERS, INC., WENDY WHITE, AS INDEPENDENT EXECUTRIX OF THE ESTATE OF G. TIM WHITE, FORMERLY D/B/A WHITE ASSOCIATES ARCHITECTURE, AND CHAVEZ CONCRETE COMPANY, APPELLEES

FROM THE 64TH DISTRICT COURT OF HALE COUNTY;

NO. A33892-0502, HONORABLE ROBERT KINKAID, JUDGE

Before QUINN, C.J., and HANCOCK and PIRTLE, JJ.

MEMORANDUM OPINION

Appellant, Another Attic, Ltd. ("Another Attic"), a limited liability partnership, appeals from a judgment rendered in favor of Appellees, Plains Builders, Inc. ("Plains Builders"), Wendy White, as Independent Executrix of the Estate of G. Tim White, formerly d/b/a White Associates Architecture ("White"), and Chavez Concrete Company ("Chavez"), in a contract dispute lawsuit arising out of a written contract. By eight

issues, Another Attic questions the liability determination (Issues 1 through 4), the legal sufficiency of the damages (Issue 5), the trial court's finding that the contract was unambiguous (Issue 6), its failure to submit certain instructions and questions (Issue 7), and its award of attorney's fees (Issue 8). We modify the judgment and affirm as modified.

Factual Background

In 2004, Plains Builders and Another Attic executed a written contract for the construction of a mini-storage facility in Plainview, Texas. Plains Builders subcontracted the architect-related work to White and concrete work to Chavez. Construction began in May of that year; however, towards the end of construction, disputes arose about the work being performed by Plains Builders. By a letter dated October 8, 2004, Another Attic directed Plains Builders to cease work, which it did. Plains Builders contended that, at the time it was ordered off the project, Another Attic owed it $57,938 under the terms of the contract. According to Plains Builders this sum was calculated by deducting from the full contract price, the sum of the amounts already paid plus the value of work that was not performed by Plains Builders due to Another Attic's termination of the contract.1 Another Attic refused to pay this sum and on February 4, 2005, Plains Builders filed suit for breach of contract for failure to pay, declaratory judgment as to substantial completion, and enforcement of its statutory mechanic's and materialmen's lien. Asserting lack of substantial completion, Another

1 Plains Builders contends that it allowed credit to Another Attic for items of work that had not yet been completed at the time it was ordered off the job. Specifically, Plains Builders offered evidence that it allowed credit for its "cost plus all markup" relating to installation of the gate operating system, landscaping, and sprinklers.

Attic filed multiple counterclaims against Plains Builders, as well as a third-party claim against two of the subcontractors, the architect, White, and the concrete provider, Chavez. Another Attic contended the work performed was so defective the alleged deficiencies could not be remedied without having the entire facility torn down and rebuilt. Another Attic also contended that certain provisions of the contract were ambiguous.

On April 5, 2008, the trial court submitted the dispute to a jury based upon thirteen questions. The first two questions dealt with the issue of contract liability, as it pertained to the dispute between Another Attic and Plains Builders. As submitted to the jury, questions one and two, together with the jury's verdict, provided as follows:

QUESTION NO. 1 Did ANOTHER ATTIC fail to comply with the construction contract?

You are instructed that a "failure to comply" is an unjustified failure or refusal of one of the parties to the contract to perform all or part of what is promised in the contract. Failure to comply by Another Attic would be excused by a previous failure by Plains Builders to comply with a material obligation of the same agreement. A failure to comply must be material.

A "failure to comply" becomes material when it deprives the injured party of any substantial benefit which the injured party could reasonably have anticipated. The less the non-breaching party is deprived of expected benefit, the less material the breach.

Answer "Yes" or "No"

Answer: Yes QUESTION NO. 2 Did PLAINS BUILDERS fail to comply with the construction contract?

You are instructed that a "failure to comply" is an unjustified failure or refusal of one of the parties to the contract to perform all or part of what is promised in the contract. Failure to comply by Plains Builders would be

excused by a previous failure by Another Attic to comply with a material obligation of the same agreement. A "failure to comply" must be material.

A "failure to comply" becomes material when it deprives the injured party of any substantial benefit which the injured party could have [sic]

reasonably have anticipated. The less the non-breaching party is deprived of expected benefits, the less material the breach.

Answer "Yes" or "No"

Answer: No_

Another Attic did not object to the submission of these liability questions or the corresponding instructions in any respect material to this appeal. By these issues the jury was asked to determine whether Another Attic and/or Plains Builders materially breached the contract. Simply stated, the jury decided that Another Attic did (excusing Plains Builders from further performance) and that Plains Builders did not (thereby rejecting Another Attic's defective construction claims).

Having found that Another Attic had breached the contract in question (Question No. 1), and that Plains Builders had not (Question No. 2), the jury concluded that as a result thereof, Plains Builders had been damaged in the sum of $57,938 (Question No. 3). The jury also found that neither White, nor Chavez, had negligently damaged Another Attic (Question Nos. 10 and 12, respectively). Due to their conditional submission, the remaining jury questions were unanswered. Following cross-motions for judgment, on July 15, 2008, the trial court entered judgment that Plains Builders recover of and from Another Attic the sum of $57,938, plus attorney's fees, pre- judgment interest and costs of court, together with foreclosure of its mechanic's and

materialmen's lien. The judgment further provided that Another Attic take nothing as to White and Chavez and that it recover costs of court from Another Attic.

Substantial Performance Versus Excused Performance

A considerable portion of Another Attic's arguments is predicated on the premise that Plains Builders's theory of recovery was based upon the equitable doctrine of substantial performance. At trial and on appeal, Another Attic has pursued a theory that defects in the construction of the mini-storage facility were so material they could not be remedied without the entire facility being torn down and rebuilt. Another Attic posits that because substantial performance requires that any defects be remediable without doing material damage to the structure, there can be no substantial performance as a matter of law. Plains Builders counters this argument by contending that "this is not a substantial performance case," or, alternatively, that the defects that could not be remediated without doing material damage to the structure, if any, were immaterial. Plains Builders further contends that this is a suit for "breach of contract, quantum meruit and unjust enrichment."2

Free access — add to your briefcase to read the full text and ask questions with AI

Another Attic, Ltd v. Plains Builders, Inc., Wendy White, as Independent of the Estate of G. Tim White, Formerly D/B/A White Associates Architecture, and Chavez Concrete Company, (Tex. Ct. App. 2010).

Another Attic, Ltd v. Plains Builders, Inc., Wendy White, as Independent of the Estate of G. Tim White, Formerly D/B/A White Associates Architecture, and Chavez Concrete Company (Another Attic, Ltd v. Plains Builders, Inc., Wendy White, as Independent of the Estate of G. Tim White, Formerly D/B/A White Associates Architecture, and Chavez Concrete Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
All Seasons Window & Door Manufacturing, Inc. v. Red Dot Corp.
181 S.W.3d 490 (Court of Appeals of Texas, 2005)
Coker v. Coker
650 S.W.2d 391 (Texas Supreme Court, 1983)
RAJ Partners, Ltd. v. Darco Construction Corp.
217 S.W.3d 638 (Court of Appeals of Texas, 2006)
Multi-Moto Corp. v. ITT Commercial Finance Corp.
806 S.W.2d 560 (Court of Appeals of Texas, 1990)
Dill v. Helms
468 S.W.2d 608 (Court of Appeals of Texas, 1971)
Maritime Overseas Corp. v. Ellis
971 S.W.2d 402 (Texas Supreme Court, 1998)
Lee v. Perez
120 S.W.3d 463 (Court of Appeals of Texas, 2003)
Tiller v. McLure
121 S.W.3d 709 (Texas Supreme Court, 2003)
Dankowski v. Cremona
352 S.W.2d 334 (Court of Appeals of Texas, 1961)
Lazy M Ranch, Ltd. v. TXI OPERATIONS, LP
978 S.W.2d 678 (Court of Appeals of Texas, 1998)
Dobbins v. Redden
785 S.W.2d 377 (Texas Supreme Court, 1990)
White v. Baptist St. Anthony's Hospital
188 S.W.3d 373 (Court of Appeals of Texas, 2006)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
King Ranch, Inc. v. Chapman
118 S.W.3d 742 (Texas Supreme Court, 2003)
Gooch v. American Sling Co., Inc.
902 S.W.2d 181 (Court of Appeals of Texas, 1995)
Wal-Mart Stores, Inc. v. Berry
833 S.W.2d 587 (Court of Appeals of Texas, 1992)
Garza v. Alviar
395 S.W.2d 821 (Texas Supreme Court, 1965)
Clary Corp. v. Smith
949 S.W.2d 452 (Court of Appeals of Texas, 1997)
Simmons v. Simmons
280 S.W.2d 877 (Missouri Court of Appeals, 1955)