Anna Ready Mix, Inc. v. N.E. Pierson Construction Co.

747 F. Supp. 1299, 13 U.C.C. Rep. Serv. 2d (West) 757, 1990 U.S. Dist. LEXIS 13975, 1990 WL 155768
CourtDistrict Court, S.D. Illinois
DecidedOctober 16, 1990
DocketCiv. 88-4066
StatusPublished
Cited by33 cases

This text of 747 F. Supp. 1299 (Anna Ready Mix, Inc. v. N.E. Pierson Construction Co.) is published on Counsel Stack Legal Research, covering District Court, S.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anna Ready Mix, Inc. v. N.E. Pierson Construction Co., 747 F. Supp. 1299, 13 U.C.C. Rep. Serv. 2d (West) 757, 1990 U.S. Dist. LEXIS 13975, 1990 WL 155768 (S.D. Ill. 1990).

Opinion

MEMORANDUM AND ORDER

FOREMAN, Chief Judge:

On July 23, 1983, Pierson Construction Company, Inc. (Pierson) and Anna Ready Mix, Inc. (ARM) entered into an agreement for the purchase of concrete. Pursuant to the agreement, ARM was to provide concrete for use by Pierson in constructing grain silos at two sites in Mound City, Illinois. The agreement specified that the concrete, unless otherwise agreed, would have a strength of 3,000 pounds per square inch (p.s.i.) twenty-eight days after being poured and that the concrete was to contain at least 5*/2 sacks of cement per cubic yard of concrete. Because of cold weather at the time of construction, this requirement was increased to 6 sacks of cement per cubic yard of concrete.

On December 8, 1983, because of a scale malfunction at ARM, the regular scale was removed for repairs and replaced with a temporary electronic scale. On the afternoon of January 6, 1984, ARM determined that the electronic scale was providing inaccurate readouts. Due to the inaccuracy of the scales, the concrete delivered by ARM did not meet the required strength specification. As a result, Pierson was obliged to make various repairs to the silos.

The parties then began this wrangling litigation. ARM sued Pierson for breach of contract; Pierson counterclaimed for breach of warranty. ARM attempted to bring in a variety of third-party defendants; these claims were dismissed. Related litigation was being conducted in state courts.

Currently before the Court are two motions for summary judgment. Pierson has moved this Court for summary judgment in its favor on the issue of liability for breach of warranty. ARM has moved for summary judgment in its favor on the issue of consequential damages. Magistrate Philip Frazier has issued his recommendations. (Documents 182 and 183). The parties have filed numerous objections, responses to objections, and other related pleadings directed towards the Magistrate’s reports. This Court must review the Magistrate’s reports and make a de novo determination. 28 U.S.C. § 636(b)(1).

I.

A Court may grant summary judgment only if the party seeking summary judgment demonstrates that no genuine issue of fact exists for trial and that the movant is entitled to judgment as a matter of law. Fed.R.Civ.P. 56(e); Wilson v. Chicago, Milwaukee, St. Paul & Pacific R.R. Co., 841 *1301 F.2d 1347, 1354 (7th Cir.1988), petition for cert. dismissed 487 U.S. 1244, 109 S.Ct. 1, 101 L.Ed.2d 953 (1988). If that showing is made and the motion’s opponent would bear the burden at trial on the matter that forms the basis of the motion, the opponent must come forth with evidence to show what facts are in actual dispute. Celotex Corp. v.. Catrett, 477 U.S. 317, 324, 106 S.Ct. 2548, 2553, 91 L.Ed.2d 265 (1986); Donald v. Polk County, 836 F.2d 376, 379 (7th Cir.1988). Where the moving party fails to meet its strict burden of proof, summary judgment cannot be entered even if the opposing party fails to respond to the motion. Yorger v. Pittsburgh Corning Corp., 733 F.2d 1215, 1222 (7th Cir.1984).

When the parties do not dispute the factual basis of a motion for summary judgment, the court’s only inquiry is whether judgment should issue as a matter of law. The burden of proof on this matter rests with the moving party. Summary judgment is inappropriate, however, if the parties disagree about inferences reasonably to be drawn from undisputed facts. Bowyer v. United States Dept. of Air Force, 804 F.2d 428, 430 (7th Cir.1986), cert. denied, — U.S. -, 110 S.Ct. 846, 107 L.Ed.2d 840 (1990).

When the parties dispute the facts, the parties must produce proper documentary evidence to support their contentions. The parties cannot rest on mere allegations in the pleadings, Boruski v. United States, 803 F.2d 1421, 1428 (7th Cir.1986), or upon conclusory allegations in affidavits. First Commodity Traders v. Heinold Commodities, 766 F.2d 1007, 1011 (7th Cir.1985). The Court must view the evidence and any permissible inferences from the materials before it in favor of the non-moving party, Matsushita Elecs. Co., Ltd. v. Zenith Radio Corp., 475 U.S. 574, 588-89, 106 S.Ct. 1348, 1356-57, 89 L.Ed.2d 538 (1986), as long as the inferences are reasonable. Davis v. City of Chicago, 841 F.2d 186, 189 (7th Cir.1988). The non-moving party must show that the disputed fact is material; that is, it must be outcome-determinative under the applicable law. Wainwright Bank & Trust Co. v. Railroadmens Fed. Sav. & Loan Ass’n, 806 F.2d 146, 149 (7th Cir.1986).

II.

Pierson has filed a motion for summary judgment in its favor on Counts I, II, III and IV of its counterclaim against ARM. Pierson argues, in essence, that there is no genuine dispute that the concrete supplied by ARM contained less than 6 bags of cement per cubic yard. Since the contract called for concrete containing 5¥2 sacks of cement per cubic yard, later increased to 6 sacks per cubic yard, ARM breached its contract.

Magistrate Frazier recommends that Pierson’s motion be denied. In his recommendation, Magistrate Frazier notes several disputed questions of fact, any of which would preclude summary judgment. For example, there is a question of whether concrete mixed with as few as 3 bags of cement per cubic yard could reach the desired strength of 3,000 p.s.i. Another disputed question of fact is the effect of cold weather at the construction site. Cold weather, apparently, can cause concrete to weaken. The parties dispute whether the weakened condition of the concrete was due to cold weather and whose responsibility it was to protect the concrete from the cold. There is also a dispute whether Pier-son knowingly accepted the concrete knowing that it contained less than 6 sacks of cement per cubic yard.

In its objection to the Magistrate’s report, Pierson emphasizes that Magistrate Frazier wrote that “[tjechnically, ARM probably did breach the contract when less than 5V2 sacks per cubic yard concrete was delivered to the job site.” Magistrate’s Report and Recommendation at 2 (April 6, 1990) (Document 183).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
N.D. Indiana, 2026
Lewis v. Chance
M.D. Pennsylvania, 2025
Rossetti v. Shapiro
M.D. Pennsylvania, 2025
Tejada v. Delbalso
M.D. Pennsylvania, 2024
O'Connor v. Snyder
M.D. Pennsylvania, 2023
Johnson v. Mirarchi
M.D. Pennsylvania, 2023
Raye v. Vannoy
E.D. Louisiana, 2022
Hunt v. City of Wilkes Barre
M.D. Pennsylvania, 2021
Al-Maqablh v. Temple
E.D. Kentucky, 2020
United States v. Simeon
115 F. Supp. 3d 981 (N.D. Iowa, 2015)
Murphy v. Lockhart
826 F. Supp. 2d 1016 (E.D. Michigan, 2011)
Harrington v. Wilber
384 F. Supp. 2d 1321 (S.D. Iowa, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
747 F. Supp. 1299, 13 U.C.C. Rep. Serv. 2d (West) 757, 1990 U.S. Dist. LEXIS 13975, 1990 WL 155768, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anna-ready-mix-inc-v-ne-pierson-construction-co-ilsd-1990.