Anham, Fzco v. United States

123 Fed. Cl. 386, 2015 U.S. Claims LEXIS 1188, 2015 WL 5439726
CourtUnited States Court of Federal Claims
DecidedSeptember 15, 2015
Docket13-414C
StatusPublished
Cited by3 cases

This text of 123 Fed. Cl. 386 (Anham, Fzco v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anham, Fzco v. United States, 123 Fed. Cl. 386, 2015 U.S. Claims LEXIS 1188, 2015 WL 5439726 (uscfc 2015).

Opinion

Motion for an Enlargement of Time; RCFC 56(d); RCFC 6(b); Partial Summary Judgment; Affidavit or Declaration Required to Request Discovery Prior to Responding to a Motion for Summary Judgment.

ORDER

WILLIAMS, Judge.

On August 20, 2015, Defendant filed a motion for a 150-day enlargement of time until February 18, 2016, to respond to Plaintiffs motion for partial summary judgment. Plaintiff opposed the request.

This case involves Defendant’s alleged breach of a settlement agreement following Plaintiffs bid protest challenging its exclusion from a procurement for services in Afghanistan. “The agreement provided that the Government should notify Anham within 60 days whether the Government would award a contract to Anham.” Def.’s Mot. at 3. “However, the Government did not notify *388 Anham that the Government would not award Anham a contract.” Id. As grounds for its lengthy enlargement, Defendant argued that it requires discovery before it can respond to Plaintiffs motion for partial summary judgment, and that the discovery period, will end on January 29. Defendant further claimed that there are genuine issues of material fact regarding liability, and suggested that it might raise defenses of waiver, prior material breach, and forfeiture. Specifically, Defendant may claim waiver because “Anham wanted the Government to continue consideration of its proposals,” and may argue that Plaintiff committed a prior material breach by failing to “disclose the subcontractors that Anham planned to use for performance.” Def.’s Mot. at 4. Defendant expanded this argument in its Reply, asserting that more discovery is needed “because Anham considered using a different web of subcontractors for any new contract awarded, and it appears that Anham’s plans changed substantially” between 2011 and 2012. Def.’s Reply at 3. Defendant suggested that there are questions about Anham’s “corporate liabilities” because there are subcontractor entities that “had actually incurred the costs that Anham now claims as damages.” Id. at 2-3. Defendant noted that “Anham has made surprising statements [about corporate liabilities] that we do not believe are accurate. We have not yet made a decision concerning whether to file counterclaims based upon such statements because we want to hear Anham’s explanations for these statements.” Id. at 3. Defendant also argued that proceeding with Plaintiffs motion for partial summary judgment would impede discovery by delaying and disrupting the deposition schedule. Id. at 4.

In its opposition, Plaintiff countered that its motion for partial summary judgment on liability was ripe and that Defendant “fail[ed] to point to a single material fact related to liability that it is still seeking to develop through discovery.” Pl.’s Resp. at 1, 3. Plaintiff further argued that the parties have completed substantial discovery all “focused on damages” including Anham’s responses to nine requests for production of documents totaling 80,198 pages, seven sets of interrogatories, and one set of requests for admission. Id. at 3-4. Finally, Plaintiff contended that Defendant’s “casually identifie[d] legal theories” that it might assert as defenses were no basis for delay, because Defendant was not claiming an inability to respond to material facts supporting Anham’s motion for summary judgment. Id. at 4.

Discussion

Defendant has requested a five-month extension of time to respond to a motion for partial summary judgment. In seeking such a lengthy extension of time, after the Court 1 granted Plaintiff leave to file a motion for partial summary judgment, Defendant has not invoked the proper procedural vehicle. Under the Rules of the Court of Federal Claims, a Rule 56(d) motion is the appropriate vehicle to request the Court to defer consideration of a motion for summary judgment pending further discovery, not a generalized Rule 6 motion for enlargement of time. Rule 56(d)-is specifically directed to the situation at hand — a scenario where a party requires discovery in order to respond to a motion for a summary judgment. In contrast, Rule 6 governs general extensions of any court-ordered deadline. These Rules require markedly different showings to secure a requested extension. Under Rule 6(b), a party must merely establish “good cause” to secure an extension of time — a modest showing that might be met by any legitimate reason for delay. In contrast, Rule 56(d), which governs whether to press forward with a summary judgment motion or permit discovery, sets forth a more onerous standard with particularized requirements. Rule 56(d) provides:

When Facts Are Unavailable to the Nonmovant.

If a nonmovant shows by affidavit or declaration that, for specified reasons, it cannot present facts essential to justify its opposition, the court may:
*389 (1) defer considering the motion or deny it;
(2) allow time to obtain affidavits or declarations or to take discovery; or
(3) issue any other appropriate order.

To obtain Rule 56(d) relief, a party must satisfy the following five-pronged test:

(1) Specify the particular factual discovery being sought;
(2) explain how the results of the discovery are reasonably expected to engender a genuine issue of material fact;
(3) provide an adequate factual predicate for the belief that there are discoverable facts sufficient to raise a genuine and material issue;
(4) recite the efforts previously made to obtain those facts; and
(5) show good grounds for the failure to have discovered the essential facts sooner.

Jade Trading, LLC v. United States, 60 Fed.Cl. 558, 565 (2004) (quoting Theisen Vending Co. v. United States, 58 Fed.Cl. 194, 198 (2003)). The Court will then determine whether the “parties would be better served by pursuing discovery and deferring any dis-positive motions until further development of the record.” Id. at 566.

Defendant is required to articulate with “some precision” the evidence Defendant hopes to obtain, “how this evidence would likely disclose issues of material fact, and why it is unable to access such evidence without further discovery.” Clear Creek Cmty. Servs. Dist. v. United States, 100 Fed.Cl. 78, 82 (2011) (quoting Padilla v. United States, 58 Fed.Cl. 585, 593 (2003)); Keebler Co. v. Murray Bakery Prods., 866 F.2d 1386, 1398 (Fed.Cir.1989). Defendant has failed to meet these requirements here.

This matter, which involves the breach of a single term of a settlement agreement, is progressing at a sluggish pace. Plaintiff filed its original Complaint over two years ago in June, 2013. Discovery has been extended six times. Plaintiffs motion for partial summary judgment on its face appears to present a pure question of law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Beres v. United States
Federal Claims, 2019
Doe v. United States
Federal Claims, 2017

Cite This Page — Counsel Stack

Bluebook (online)
123 Fed. Cl. 386, 2015 U.S. Claims LEXIS 1188, 2015 WL 5439726, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anham-fzco-v-united-states-uscfc-2015.