Angles v. West, Unpublished Decision (1-21-2003)

CourtOhio Court of Appeals
DecidedJanuary 21, 2003
DocketCase No. 02CA16.
StatusUnpublished

This text of Angles v. West, Unpublished Decision (1-21-2003) (Angles v. West, Unpublished Decision (1-21-2003)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Angles v. West, Unpublished Decision (1-21-2003), (Ohio Ct. App. 2003).

Opinion

DECISION AND JUDGMENT ENTRY
{¶ 1} Appellants challenge the judgment of the Circleville Municipal Court awarding Joe Angles $11,110.00 on his breach of contract claim.1 Appellants contend that the trial court's award of the full contract price is against the manifest weight of the evidence because the concrete they poured has value. Because there is no competent, credible evidence to support the court's finding that the concrete has no value, we conclude that the trial court's award is against the manifest weight of the evidence.

{¶ 2} Joe Angles hired Virgil and Wendell West of V W, Inc. to lay the concrete for two driveways, a porch, and steps at Angles' newly built home. The parties entered into an oral agreement in which appellants agreed to do the work for $11,110.00. Four months after appellants completed the work, Angles noticed that cracks had developed in the concrete. Specifically, the concrete pours done by the appellants had developed severe midline cracking. Angles filed suit against appellants alleging that they breached the contract by failing to perform in a workmanlike manner.

{¶ 3} At trial, Angles presented the deposition of Donald Pierce, a construction consultant for Columbus Testing Laboratory Engineers. Mr. Pierce testified that the cracking occurred because the concrete slabs had an insufficient number of saw joints and because the saw joints that were present were not deep enough. According to Mr. Pierce, saw joints control where the cracking occurs. With saw joints, the cracking will be minimized and occur in the joint rather than randomly. Relying on standards published by the American Concrete Institute, Mr. Pierce testified that the largest section of concrete poured should be no more than 10 feet, and that any area larger than that needs a saw joint. Many of appellants' concrete sections were 15 to 20 feet wide. Mr. Pierce testified that the unsightly cracks could have been avoided if appellants had used "proper joint methods".

{¶ 4} After a one-day bench trial, the court found that appellants had not performed in a workmanlike manner and, thus, had breached the contract. The court recognized that the general measure of damages for defects in construction contracts is the "cost to repair," i.e., the cost of curing the defects. However, the court felt that the possibility of repair had not been adequately addressed, so it set the matter for a further hearing.

{¶ 5} At the second hearing, the court heard testimony from Joe DeFelice of A.L.D. Concrete and Grading. Mr. DeFelice testified that repairing the concrete so that it didn't look like a patch job would cost almost as much as replacing it. At the first hearing, the court heard testimony that replacing the concrete work would cost approximately $16,000 to $18,000. That price included the cost of removing the old concrete, which alone cost $3,000 to $3,500.

{¶ 6} Subsequently, the court determined that there was no possibility for successful repair. The court found that the defects in workmanship were substantial and that appellants' work had "no extrinsic (sic) value." The trial court then awarded Angles $11,110, the original contract price. Appellants raise the following assignments of error:ASSIGNMENT OR ERROR NO. 1 — The trial court erred in returning the entire purchase price to the Plaintiff as such judgment is against the manifest weight of the evidence, because there is no evidence that the concrete has no value. ASSIGNMENT OF ERROR NO. 2 — The trial court erred in returning the entire purchase price to the Plaintiff because such action is violative of the doctrine of substantial performance.ASSIGNMENT OF ERROR NO. 3 — The trial court erred in returning the entire purchase price to the Plaintiff because it creates an unjust enrichment situation, instead of correcting one.

{¶ 7} In their first assignment of error, appellants argue that the trial court's award of the full contract price is against the manifest weight of the evidence. They contend that the record does not support the court's finding that there is no value in the work done by appellants. Appellants contend that the concrete has value because it is capable of being used.

{¶ 8} A trial court's decision will not be found to be against the manifest weight of the evidence as long as there is some competent, credible evidence to support it. Security Pacific Natl. Bank v. Roulette(1986), 24 Ohio St.3d 17, 20, 492 N.E.2d 438. This standard of review is necessarily highly deferential because the trial court is in the best position to analyze the witnesses and determine their credibility. SeasonsCoal Co. v. Cleveland (1984), 10 Ohio St.3d 77, 80, 461 N.E.2d 1273. We are reminded that it is not the province of this court to reweigh the evidence. C.E. Morris v. Foley Construction Co. (1978), 54 Ohio St.2d 279,280, 376 N.E.2d 578. However, if there is no competent, credible evidence to support the trial court's judgment, we are required to reverse it.

{¶ 9} Generally, the proper measure of damages for breach of a construction contract is the cost of repair. Ohio Valley Bank v. Copley (1997), 121 Ohio App.3d 197, 210, 699 N.E.2d 540, citing 5 Corbin on Contracts (1964), Section 1089. See, also, Barton v. Ellis (1986),34 Ohio App.3d 251, 253, 518 N.E.2d 18. However, if repair would lead to unreasonable economic waste, damages are measured by the difference in market value between the structure as contracted for and the structure as received. Ohio Valley Bank, supra.

{¶ 10} In its entry, the trial court did not expressly indicate what measure of damages it used. However, it appears that the court applied the diminution or difference in value measure. In its judgment entry of May 8, 2002, the trial court found that there was "no extrinsic (sic) value in the work" done by appellants. Moreover, the court filed a separate entry containing its findings of fact and conclusions of law. In that entry, the court found that Angles "received no benefit or value from the initial contract." Thus, it appears the court determined that Angles contracted for concrete work (the driveway, porch, and steps) worth $11,110 but that the completed project had no value to him. Based on that, the court awarded Angles $11,110, the full contract price.

{¶ 11} We find that there is no evidence in the record to support the court's finding that the concrete has no value.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ohio Valley Bank v. Copley
699 N.E.2d 540 (Ohio Court of Appeals, 1997)
Barton v. Ellis
518 N.E.2d 18 (Ohio Court of Appeals, 1986)
C. E. Morris Co. v. Foley Construction Co.
376 N.E.2d 578 (Ohio Supreme Court, 1978)
Seasons Coal Co. v. City of Cleveland
461 N.E.2d 1273 (Ohio Supreme Court, 1984)
Security Pacific National Bank v. Roulette
492 N.E.2d 438 (Ohio Supreme Court, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
Angles v. West, Unpublished Decision (1-21-2003), Counsel Stack Legal Research, https://law.counselstack.com/opinion/angles-v-west-unpublished-decision-1-21-2003-ohioctapp-2003.