Angell Enterprises, Inc. v. Abram & Hawkins Excavating Co.

643 N.E.2d 362, 1994 WL 680209
Indiana Court of Appeals·Decided January 31, 1995·No. 77A01-9405-CV-157·Published·Cited by 11 cases

Opinions

OPINION

BAKER, Judge.

This appeal of an arbitration award presents the opportunity to review the broad authority granted to an arbitrator by Indiana's Uniform Arbitration Act, IND. CODE §§ 34-4-2-1 to 22, and the means to effectively challenge an award.

Appellant-plaintiff Angell Enterprises, Inc. opposes the trial court's affirmance of an arbitration decision awarding appellee-defen-dants Abram & Hawkins Excavating Co., et al. (collectively Subcontractors) a total of $260,013. Angell's primary contention is that the arbitrator exceeded its authority by deciding claims not agreed to be arbitrated. Angell also cites a procedural error claiming the award is deficient in explaining its result. The Subcontractors' respond that the award was within the seope of the arbitrator's powers and sufficiently revealed the basis of its decision. Two of the Subcontractors, Abram & Hawkins Excavating Co. (Abram) and Proficient Building Systems (Proficient) have jointly filed their own appellees' brief presenting arguments in addition to those of the other Subcontractors.

FACTS

Angell entered a contract with Haver Companies, Inc. (General Contractor) to construct a supermarket in Sullivan County, Indiana, at an alleged contract price of $1,210,741.45. The General Contractor hired various subcontractors for the job. When the General Contractor failed to pay its subcontractors from the $1,051,924 of funds An-gell claims to have paid on the contract, Angell terminated its contract with the General Contractor and instituted this action to determine any amounts Angell owed to the subcontractors under IND.CODE § 82-8-3-9 (Owner's Liability Statute), and any set-off amounts. Thirteen of these subcontractors became interpleader defendants in this action [364]*364and are the Subcontractors in this appeal. The General Contractor declared bankruptcy and is not a party to the appeal.

Angell's complaint alleged that it bore additional costs of $71,248 to repair defective work and complete the supermarket. Angell claimed this amount as set-off to any amounts owed to the Subcontractors. Separate answers denying Angell's allegations were filed by six of the thirteen Subcontractors, and seven other Subcontractors filed a motion to compel arbitration in lieu of filing an answer. The motion to compel arbitration was based upon the Owner's Liability Statute, which makes an owner directly liable to a subcontractor for unpaid services on a project, but limits the owner's liability to the amount the owner still owed to the general contractor. I.C. § 32-8-8-9. Two of the Subcontractors, Abram and Proficient, who were. not petitioners of the motion to compel arbitration, filed cross-claims against Angell asserting other theories for relief in addition to the Owner's Liability Statute. During the hearing on the motion for arbitration, the parties agreed to submit the claims under the Owner's Liability Statute to an arbitrator. The court entered an order reflecting this agreement. Following the unrecorded arbitration proceedings, the arbitrator awarded the Subcontractors a total of $260,-013, setting forth a schedule apportioning specific amounts to each particular subcontractor. The arbitration award of September 3, 1993, stated that it was a full settlement of all claims submitted for arbitration. On December 2, 1998, Angell filed a motion requesting the trial court to vacate the arbitration award and to remand for further arbitration, claiming that the arbitrator exceeded its authority and also failed to provide a written determination of all questions submitted for arbitration. The trial court denied Angell's motion and confirmed the arbitration award.

DISCUSSION AND DECISION

I. Authority

Angell argues that the arbitrator exceeded its scope of authority in deciding issues other than those under the Owner's Liability Statute. Angell presents that based upon its calculations, the maximum liability under the Owner's Liability Statute without allowance of Angell's set-offs was $158,817.45. Thus, Angell concludes that the award for $260,018 reflects that the arbitrator exeeeded his powers. Hence, we must decide which claims were submitted to arbitration.

Indiana's Uniform Arbitration Act does not declare which issues are subject to arbitration. Instead, the parties' agreement governs the conditions, limitations, and restrictions upon an arbitrator's seope of review. Brougher Agency, Inc. v. United Home Life Ins. Co. (1993), Ind.App., 622 N.E.2d 1013, 1017, trans. denied. The parties are free to define for themselves what questions may be arbitrated. Fort Wayne Educ. Ass'n v. Bd. of School Trustees (1991), Ind.App., 569 N.E.2d 672, 676. A court may vacate an award that extends beyond the contractual seope of arbitration. IND.CODE § 34-4-2-18(8); International Bhd. of Elec. Workers v. Citizens Gas & Coke Util. (1981), Ind.App., 428 N.E.2d 1320, 1326.

Angell maintains that the only issues in arbitration were the Subcontractors' claims pursuant to the Owner's Liability Statute. As a preliminary matter, we address the Subcontractors' arguments that Angell waived this argument on appeal because it did not object to arbitration at the time the trial court ordered it. An order compelling arbitration is a final, appealable order if severable from other claims in the lawsuit. Albright v. Edward D. Jones & Co. (1991), Ind.App., 571 N.E.2d 1329, 1331, cert. denied, - U.S. -, 113 S.Ct. 61, 121 L.Ed.2d 29. Thus, a party may not contest arbitrability for the first time in its petition to vacate an arbitration award. However, Angell does not deny that it had agreed to submit the claims under the Owners' Liability Statute to arbitration. Since an agreement as to those claims existed, Angell did not have any basis to appeal the arbitration when it was entered because the submission of any other claims was not contemplated in the parties' agreement. See Kelly v. Adams (1889), 120 Ind. 340, 344, 22 N.E. 317, 318-19 (parol agreement to arbitrate made in court is enforceable). We do not find waiver under the circumstances.

[365]*365We now turn to the substantive argument that the arbitrator could decide only the Subcontractors' claims under the Owner's Liability Statute IND.CODE § 34-4-2-1 refers to a written agreement to submit to arbitration. It is uncontroverted that Angell and the Subcontractors never entered any written contract providing for arbitration of disputes. The parties disagree as to whether a written arbitration agreement between the General Contractor and Angell applied to the Subcontractors as well. Generally, only those who are parties to a contract, or those in privity with a party, have a right to recover under the contract. Barth Elec. Co. v. Traylor Bros., Inc. (1990), Ind.App., 553 N.E.2d 504, 506. I.C. § 32-8-3-9 places the Subcontractors in privity with the General Contractor, but only to the extent specifically provided within that statute. See Blade Corp v. American Drywall, Inc. (1980), Ind.App.,

Angell Enterprises, Inc. v. Abram & Hawkins Excavating Co., 643 N.E.2d 362, 1994 WL 680209 (Ind. Ct. App. 1995).

643 N.E.2d 362 (Angell Enterprises, Inc. v. Abram & Hawkins Excavating Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

American Arbitration Ass'n v. North Miami Community Schools
866 N.E.2d 296 (Indiana Court of Appeals, 2007)
Daimler Chrysler Corp. v. Franklin
814 N.E.2d 281 (Indiana Court of Appeals, 2004)
North Miami Education Ass'n v. North Miami Community Schoools
746 N.E.2d 380 (Indiana Court of Appeals, 2001)
North Miami Education Ass'n v. North Miami Community Schools
736 N.E.2d 749 (Indiana Court of Appeals, 2000)
Groves v. Groves
704 N.E.2d 1072 (Indiana Court of Appeals, 1999)
Hooker Builders, Inc. v. Smalley
691 N.E.2d 1256 (Indiana Court of Appeals, 1998)
Bopp v. Brames
677 N.E.2d 629 (Indiana Court of Appeals, 1997)
Poindexter Excavating, Inc. v. Downey
198 B.R. 292 (S.D. Indiana, 1996)