Angeles Gravel & Supply Co. v. Clallam County Hospital District No. 2

259 P.2d 366, 42 Wash. 2d 827, 1953 Wash. LEXIS 516
CourtWashington Supreme Court
DecidedJuly 2, 1953
Docket32297
StatusPublished

This text of 259 P.2d 366 (Angeles Gravel & Supply Co. v. Clallam County Hospital District No. 2) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Angeles Gravel & Supply Co. v. Clallam County Hospital District No. 2, 259 P.2d 366, 42 Wash. 2d 827, 1953 Wash. LEXIS 516 (Wash. 1953).

Opinion

Finley, J.

In this lawsuit the plaintiff, Angeles Gravel and Supply Company, sued the defendant J. G. Watts Construction Co. for the sum of $3,595.18, alleging that the sum represented a balance due for mixed concrete delivered to the construction company for use by it in the erection of the Olympic Memorial Hospital in Port Angeles, Washing *828 ton. The building contractor’s bonding company was made a party defendant, as well as the Clallam County Hospital District No. 2, for which the hospital was being built. After the complaint was filed, the contractor made a payment on account in the sum of $1,661.33, under an agreement that such payment would not affect the right of the plaintiff to proceed with its lawsuit. The defendants contended that there were shortages in the deliveries of mixed concrete by the plaintiff. It is further contended by the defendants that timely complaint was made respecting the shortages. The plaintiff denied that there were shortages and that timely complaint was made by the defendants, and furthermore, urged that defendants were estopped to assert any claim of shortage. The trial court awarded judgment for the plaintiff, stating that his decision was on the theory of estoppel or waiver, and this appeal followed.

First, we note that the construction company concedes that all of its assignments of error are predicated on the single issue of whether there were shortages in the deliveries of mixed concrete by the plaintiff. The trial court made no specific finding as to whether or not there were shortages, and no finding as to the specific number of yards of concrete delivered. No assignment of error specifically emphasizes the absence of a finding of fact on the latter mentioned aspects of the case. Apparently, this is because the trial court’s decision turned on the question of estoppel rather than on the issue of shortages.

The facts, as we see them, are as follows: The construction company held a contract with the Clallam County Hospital District No. 2 for the erection of the Olympic Memorial Hospital in Port Angeles, Washington, pursuant to which a subcontract was entered into with the Angeles Gravel & Supply Company for mixed concrete. The initial order was for 8,000 yards, but subsequently was reduced to 3,000 yards. The actual amount delivered was 2,381 yards. After 1,750 yards of mixed concrete had been delivered, the construction company wrote a letter to plaintiff on January 5, 1951, which, in part, read as follows:

*829 “In reviewing our records it has become apparent that throughout our pours we are continually being shorted in volume of concrete in an amount totaling approximately eight per cent. To date we have poured approximately 1750 yards and are 125 yards over our estimate. . . .

“Upon checking with your plant the total weight of sand and gravel now being used amounted to 3305 lbs. per c.y. . . . It has been our experience in operating our own batch plant that to obtain a full yard of concrete by volume the weight of the concrete must equal approximately 3600 lbs. ...”

Upon receipt of the above quoted letter, Mr. A. E. Nailor, the cement company’s manager, checked the scales used at the mixing plant, and also checked with the workmen in charge of the mixing operations. He talked with the construction company’s foremen on the hospital job. Mr. Nailor testified as follows:

“Q When you had this complaint of the shortage made what did you do about it? A I went up to see the foreman. [Jack Clark was foreman on this job until January 18, 1951.] . . . He maintained that we were short and I said we weren’t short. It’s pretty hard to argue a thing out after it’s poured.”

When questioned as to whether Jack Clark (foreman for the construction company during part of the job) had stated that he was satisfied about the delivery of mixed concrete, Mr. Nailor said:

“A Yes and no. When this argument came up Jack couldn’t understand it. He said he thought it was all right, but Watts wasn’t satisfied with it. . . . when I talked to him [Clark] he would seem to agree with me and when Watts was there he agreed with Watts. It was pretty hard to pin him down one way or the other.”

Nailor’s testimony concerning his conversation with John Shelman, the foreman who succeeded Mr. Clark, was:

“A I talked to Mr. Shelman. Clark was there until February or March and then Shelman came down and I went up to meet him. Of course, he knew we were theoretically shorting him. The first pour he made he was rather indignant and said we had shorted him and evidently we had been shorting him right along and we checked the pour *830 and found he made a wrong measurement. It checked out all right. Before he left I asked him what he thought about it and he said he had poured approximately 500 yards since he was there and it checked out very fine.”

On April 20, 1951, Mr. Nailor wrote the construction company a letter, reading in part as follows:

“We were surprised to receive your letter of April 11 concerning the concrete for the Memorial Hospital, as our understanding with Jack Clark before he left was that he believed the situation had been cleared up, and that you were satisfied no shortage existed.

“We have checked our Plant since our talk with you in January, and also checked with other contractors, and we are positive we are giving a little over, rather than short measure. We have also checked with your men in charge at the job, and they have told us the small pours checked out correctly, but that the large pours were short. This doesn’t make sense. All our concrete is made in the same machine, using the same scales, and by the same mixerman. And we certainly cannot be held responsible for the manner in which the concrete is placed after it is delivered to the job.

“We have made every effort to cooperate with your men on this job and to give you the best service possible, and hope that we may continue to do so. However, since we are absolutely sure that our measure is correct, we would appreciate a check in full of your account at once, ...”

After the construction company raised the question of shortages, and after some discussion óf the matter between Mr. Nailor and the foremen for the construction company on the hospital job, the construction company, without making them subject to protest, made payments on account as follows:

Jan. 11, 1951.............. $4,680.51

Feb. 10, 1951.............. 1,273.33

Feb. 12, 1951.............. 5.75

Mar. 12,1951.............. 3,086.77

After the payment of March 12, 1951, of $3,086.77, the balance due on the account with the cement company was only $115.00. Thereafter, delivery of mixed cement was continued. No further payments on account were made; after the construction was completed, the cement company sued for the alleged contract price of the mixed concrete, *831 apparently delivered after March 1, 1951. The trial judge’s memorandum opinion reads, in part, as follows:

“The situation we have here is this: The testimony of Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Payne v. Vinecore
246 P.2d 448 (Washington Supreme Court, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
259 P.2d 366, 42 Wash. 2d 827, 1953 Wash. LEXIS 516, Counsel Stack Legal Research, https://law.counselstack.com/opinion/angeles-gravel-supply-co-v-clallam-county-hospital-district-no-2-wash-1953.