Anekom, Inc. v. Estate of Demith

2018 IL App (3d) 160554, 102 N.E.3d 834
CourtAppellate Court of Illinois
DecidedMarch 28, 2018
DocketAppeal 3–16–0554
StatusPublished

This text of 2018 IL App (3d) 160554 (Anekom, Inc. v. Estate of Demith) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anekom, Inc. v. Estate of Demith, 2018 IL App (3d) 160554, 102 N.E.3d 834 (Ill. Ct. App. 2018).

Opinion

JUSTICE SCHMIDT delivered the judgment of the court, with opinion.

¶ 1 The Estate of Richard A. Demith (Estate) appeals the trial court's orders granting summary judgment to Carpentry by Connor Construction, Inc. (Connor), and E Trinity Construction, LLC (E Trinity), on their respective complaints to foreclose their mechanic's liens. We affirm.

¶ 2 FACTS

¶ 3 I. The Parties

¶ 4 Anekom is a general contractor. Connor and E Trinity are subcontractors. The Estate is the owner of the subject property located in Mokena, Illinois. Joette LaValley is the independent executor of the Estate. Connor and E Trinity contracted with Anekom to complete work on the Estate's property. Anekom is not a party to this appeal.

¶ 5 II. The Original Contract and the Parties' Performance

¶ 6 On May 11, 2013, Anekom entered into a contract with LaValley, in her capacity as independent executor of the Estate, to demolish the Estate's fire-damaged structure and construct a new house in its place. Pursuant to the contract, Anekom agreed to complete the work within 180 days according to the plans and specifications provided by the Estate in exchange for payment of $414,000.

¶ 7 On May 16, 2013, Anekom subcontracted with E Trinity to install footings, basement floor base, and a garage floor. E Trinity completed its work under the subcontract on September 12, 2013.

¶ 8 On September 21, 2013, Anekom subcontracted with Connor for carpentry work. Connor completed its work under the subcontract on October 21, 2013.

*837 ¶ 9 On October 28, 2013, the Estate terminated the contract with Anekom after it determined the construction of the new house was not on schedule to be completed within the contractual 180-day term.

¶ 10 On April 29, 2014, the Estate entered into a contract with a second general contractor, Peak Construction and Remodeling, Inc. (Peak). The contract provided that "Peak Construction & Remodeling will be taking over and completing the LaValley residence" for a total cost of $280,633.

¶ 11 III. Claims for Mechanic's Liens

¶ 12 On November 22, 2013, Connor filed a notice and claim for mechanic's lien against Anekom and LaValley, in her capacity as independent executor of the Estate, in the amount of $63,500. On November 27, 2013, E Trinity filed a notice and claim for mechanic's lien against the Estate and Anekom in the amount of $38,070. On January 14, 2014, Anekom filed an original contractor's claim for lien against Maywood-Proviso State Bank as trustee, the Estate, and LaValley in her capacity as independent executor of the Estate.

¶ 13 IV. Anekom's Complaints

¶ 14 On April 8, 2014, Anekom filed a six-count complaint in the circuit court of Will County. In July 2014, Anekom filed an amended complaint, adding E Trinity and Connor as defendants. Counts I, II, and III sought to foreclose its lien against Maywood-Proviso State Bank, the Estate, and LaValley, in her capacity as independent executor of the Estate. Anekom alleged it had "completely performed its obligations under the contract until October 27, 2013, at which time Joette LaValley denied Anekom access to the job and prevented it from completing its work." Anekom asserted that the value of services it performed totaled $179,790 of which $109,000 remained due. Anekom further alleged that it gave notice of its lien on January 14, 2014, and that its lien claim superseded any subsequent liens. Count IV alleged breach of contract against LaValley, individually, and in her capacity as independent executor of the Estate. Count VI advanced a quantum meruit claim. The trial court eventually dismissed Anekom's claims with prejudice for failure to appear.

¶ 15 V. Counterclaims of Connor and E Trinity

¶ 16 In September and November 2014, Connor and E Trinity filed their respective answers to Anekom's amended complaint. They also filed counterclaims against Anekom and the Estate. Connor and E Trinity (1) sought to foreclose their respective mechanic's lien (count I), (2) alleged breach of contract against Anekom (count II), and (3) sought relief from Anekom and the Estate under section 28 of the Mechanics Lien Act (Act) ( 770 ILCS 60/28 (West 2012) ) (count III). Specifically, Connor alleged it entered into a contract with Anekom on September 21, 2013, to perform carpentry work; by the time Connor completed its obligations under the contract on October 21, 2013, it provided labor and materials totaling $63,500 that neither Anekom nor the Estate paid. Similarly, E Trinity alleged it entered into a contract with Anekom on May 16, 2013, to perform concrete work; it provided labor and materials totaling $38,070.10 that neither Anekom nor the Estate paid.

¶ 17 VI. The Estate's Counterclaim

¶ 18 On September 10, 2015, the Estate filed a counterclaim against Anekom, alleging breach of contract and damages "in an amount to be established at trial." The counterclaim alleged, in part, that Anekom "failed to diligently prosecute the work in a timely manner and in accordance with the schedule agreed by the parties." The Estate further alleged that Anekom "failed to perform its work in a reasonably workmanlike *838 manner and in accordance with the plans and specifications, including, but not limited to" failure to (1) properly pour foundation walls, (2) install proper ceiling joists, (3) install hurricane clips and exterior fasteners, (4) properly construct bathroom pocket doors, and (5) construct the dining room archway as specified by the plans. The Estate also sought indemnification from Anekom for E Trinity's and/or Connor's lien claims.

¶ 19 VII. Connor's Motion for Summary Judgment

¶ 20 On October 15, 2015, Connor filed a motion for summary judgment on its claim to foreclose its mechanic's lien. In support of its motion, Connor attached the affidavit of its president, Nicholas Connor, which essentially repeated the counterclaim's allegations. Connor asserted that it sent a 90-day notice of lien to all interested parties and recorded the mechanic's lien within four months of completing its work. Connor maintained that it complied with all procedural requirements of the Act and was entitled to judgment on its lien claim as a matter of law.

¶ 21 The Estate responded that summary judgment was inappropriate because (1) it could not be compelled to pay more for the completion of the residence than the amount of its original contract with Anekom and (2) an issue of fact existed as to the value of Connor's work.

¶ 22 Following a January 13, 2016, hearing, the trial court granted Connor's motion for summary judgment and awarded damages in the amount of $78,131.09, plus court costs. The court subsequently denied the Estate's motion for reconsideration.

¶ 23 VIII. E Trinity's Motion for Summary Judgment

¶ 24 On January 28, 2016, E Trinity filed a motion for summary judgment on its claim to foreclose its mechanic's lien. In support of its motion, E Trinity attached the affidavit of its president, John Flaherty, which essentially repeated the counterclaim's allegations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

New Hampshire v. Maine
532 U.S. 742 (Supreme Court, 2001)
Gluth Brothers Construction, Inc. v. Union National Bank
518 N.E.2d 1345 (Appellate Court of Illinois, 1988)
Lempa v. Finkel
663 N.E.2d 158 (Appellate Court of Illinois, 1996)
Altom v. Hawes
380 N.E.2d 7 (Appellate Court of Illinois, 1978)
Gluth Bros. Construction, Inc. v. Union National Bank
548 N.E.2d 1364 (Appellate Court of Illinois, 1989)
Seymour v. Collins
2015 IL 118432 (Illinois Supreme Court, 2015)
Seymour v. Collins
2015 IL 118432 (Illinois Supreme Court, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
2018 IL App (3d) 160554, 102 N.E.3d 834, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anekom-inc-v-estate-of-demith-illappct-2018.