Andrew J. Robinson Co. v. Security Mutual Life Insurance

167 A.D. 880, 154 N.Y.S. 3, 1915 N.Y. App. Div. LEXIS 9692
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJune 4, 1915
StatusPublished
Cited by1 cases

This text of 167 A.D. 880 (Andrew J. Robinson Co. v. Security Mutual Life Insurance) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Andrew J. Robinson Co. v. Security Mutual Life Insurance, 167 A.D. 880, 154 N.Y.S. 3, 1915 N.Y. App. Div. LEXIS 9692 (N.Y. Ct. App. 1915).

Opinion

Laughlin, J.:

This action was brought to recover a balance alleged to be due and owing to the plaintiff under and by virtue of the provisions of a contract in writing made by the parties to this action on the 1st day of March, 1904, by which the plaintiff, therein designated as the contractor, agreed to furnish and provide all materials and perform all the work necessary for the erection of an office building on premises owned by defendant, likewise designated owner, in the city of Binghamton, N. Y., according to plans, drawings and specifications to be furnished by the architects of the owner, the building to be completed on or about the 1st day of March, 1905, or within such additional time after that date as would equal the period that the contractor might be delayed by the owner in commencing the excavation after the 1st of April, 1904. The contract was construed by the parties as constituting the plaintiff superintendent of construction for defendant, notwithstanding certain general provisions designed to insure completion within the time specified, and such it was in effect, at least as between the parties, for the owner agreed to reimburse the contractor for “the total necessary actual cost of all labor and material,” and to pay it, evidently as compensation for its services, five per cent in addition thereto, it being provided that the contractor should not receive a percentage on the cost price of any material which the owner might have and which might be used in the building, but only upon the expense in laying and using the same, and that in no event should the five per cent exceed the sum of $25,000; and it was provided that the materials should be purchased pursuant to competitive bidding, and [883]*883from vendors and at prices approved by the owner, and that unless otherwise agreed by the owner, all labor and services should also be employed pursuant to competitive bidding approved by the owner. The contract contained other provisions to the effect that the owner should pay the contractor monthly for the actual cost of labor and materials and the five per cent in addition thereto, upon statements and vouchers to be submitted to the owner by the contractor; that the owner should have the right to retain out of any payments due an amount sufficient to indemnify it against any lien or claim chargeable to the contractor, for which, if established, the owner might become liable, and that if after final payment the owner should be obliged to discharge any such lien the contractor should reimburse it therefor, and that the owner should be at liberty to terminate the employment of the contractor and to take possession of the work if the contractor should at any time refuse or neglect to supply a sufficiency of properly skilled workmen, or materials of proper quality, or fail in any respect to prosecute the work with promptness and diligence, or fail in the performance of any of its agreements, and such refusal, neglect or failure should be certified by the architects as therein provided, and it was provided that the contractor should pay as liquidated damages the sum of $100 per day for each and every day after March 15, 1905, until the building should be completed; but it was provided, among other things, that the contractor was to be allowed for delays caused by the owner or its architects, or by any other contractor, or by strikes or lockouts caused by acts of employees.

There is no controversy with respect to the cost of the work, or the amount of plaintiff’s percentage thereon or the balance unpaid on either item. The only questions arise with respect to a claim made by the defendant to an offset against the amount claimed by the plaintiff, on account of two items of expenditure which it claims it was obliged to make, owing to acts of the plaintiff in violation of its duty under the contract.

On the 15th day of October, 1901, the plaintiff, pursuant to the provisions of the contract, let the work mentioned in the specifications and shown on the drawings ” for the “ Plain and Ornamental Plastering ” to McNulty Brothers, who agreed to [884]*884complete it by the 28th day of November, 1904. By the provisions of the contract with McNulty Brothers the plaintiff was at liberty to terminate it for, among other things, their failure to prosecute the work with due diligence. On the 1st day of November, 1904, the architects employed by the owner wrote the plaintiff complaining of the manner in which the plastering work was being done; and on the twenty-third day of the same month the architects made a certificate in writing to the effect that McNulty Brothers had ‘ ‘ failed to prosecute the work provided for under and hy the terms of their contract, with sufficient promptness and diligence to enable them to complete said work within the time and according to the terms of their contract, to wit, November 28th, 1904, and that they have failed in the performance of the agreements contained in. their said contract,” and that with the force of men employed by them it would be impossible to finish their work in less than six weeks, and that such failure “to furnish the necessary number of men and quantity of materials to finish said job within time agreed upon, is sufficient ground to terminate the employment of the said sub-contractors on said job,” and on that day the defendant notified the plaintiff that it had, on the certificate of the architects, elected to terminate McNulty Brothers’ contract and directed the plaintiff to terminate it by a formal notice inclosed, and to finish the work in accordance with the provisions of article Y of the contract with McNulty Brothers, which in such case authorized the plaintiff to take over the work and finish it for the account of McNulty Brothers, accounting to them for any difference between the cost of completion and the balance unpaid on the contract and holding them liable for any excess of such costs. On the twenty-fifth day of that month the plaintiff delivered a notice to McNulty Brothers, under date of the twenty-third, to the effect that it would on the twenty-ninth, which was the day after the day on which McNulty Brothers were required to complete their work, take possession and finish the plastering pursuant to article Y of the contract, and also delivered therewith the architects’ certificate and the defendant’s notice of its election to terminate the contract. The plaintiff took possession of the work covered by the McNulty Brothers’ contract on or about the 29th [885]*885day of November, 1904, and completed the same by day labor. The actual and necessary cost of completion was duly certified by the architects to be the sum of $2,376.17 in excess of the amount for which McNulty Brothers agreed to perform the work, which was $14,856, no part of which had been paid, " thus making the cost of completion $17,232.17. It thus appears that if the contract was rightfully terminated, McNulty Brothers could not have recovered for any work done by them and would have been liable for the excess of the cost of completion over and above the amount for which they agreed to do the work; and it was admitted by the pleadings that they were financially responsible. This item of $2,376.17 is one of the offsets claimed by defendant.

On the 27th day of February, 1905, McNulty Brothers filed a mechanic’s lien against the premises for $11,000.93 on the agreed price and value of the labor and materials performed and furnished by them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

130 Cedar Street Corp. v. Court Press, Inc.
267 A.D. 194 (Appellate Division of the Supreme Court of New York, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
167 A.D. 880, 154 N.Y.S. 3, 1915 N.Y. App. Div. LEXIS 9692, Counsel Stack Legal Research, https://law.counselstack.com/opinion/andrew-j-robinson-co-v-security-mutual-life-insurance-nyappdiv-1915.