Andrew Houston Allen v. State

CourtCourt of Appeals of Texas
DecidedJuly 7, 2016
Docket14-15-00115-CR
StatusPublished

This text of Andrew Houston Allen v. State (Andrew Houston Allen v. State) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Andrew Houston Allen v. State, (Tex. Ct. App. 2016).

Opinion

Affirmed and Memorandum Opinion filed July 7, 2016.

In The

Fourteenth Court of Appeals

NO. 14-15-00115-CR NO. 14-15-00116-CR

ANDREW HOUSTON ALLEN, Appellant V.

THE STATE OF TEXAS, Appellee

On Appeal from the 300th District Court Brazoria County, Texas Trial Court Cause Nos. 66050 & 66951

MEMORANDUM OPINION Appellant Andrew Allen was charged by two separate indictments and convicted of misapplication of trust funds.1 Appellant presents three issues. We affirm.

1 Tex. Prop. Code Ann. § 162.031 (West 2009). Factual and Procedural Background

On June 19, 2008, appellant, owner of Allen Brothers Construction, entered into a $1,069,000 contract with the owner and general manager of the Texas location of SYNEO, LLC (formerly, Technical Innovations), to construct a new office building. Appellant received an initial “pre-mobilization draw” from SYNEO of $40,679.94 and a “mobilization draw” of $55,000 to begin construction. From June 2008 through May 2009, appellant made additional draws from SYNEO to cover project expenses. Appellant’s wife, Johni Jack Allen, signed the releases for these draws and was “very involved in . . . keeping the paperwork” related to the SYNEO contract.

By May 2009, appellant had drawn 84.2% of the funds allotted for the project. Gary Cordell, owner and general manager of SYNEO, hired a third party to assess appellant’s progress on the project. The third party informed Cordell that, despite the drawing of nearly 85% of the allotted funds, the project was not 85% complete. Cordell also learned that appellant’s subcontractors were not being paid for work completed. Cordell contacted each subcontractor to determine how much work was done and how much each had been paid. Cordell discovered that many of the subcontractors had not been paid commensurate with their completed work. In order to rectify the situation, Cordell paid the contractors what they were owed. These payments brought the total cost of the project to $498,549.98 over the initial contract price.

On July 14, 2008, the engineering firm of Baker and Lawson partnered with appellant to complete two projects for the City of Angleton—an addition to the City’s fire station and an addition to its City Hall. The contract for the fire station addition was worth $106,750, and the contract for the City Hall addition was worth $485,605.

2 Each project had a draw schedule that corresponded with different phases of the project. According to the schedule, appellant was to make a draw by invoicing Baker and Lawson each time the subcontractors completed a phase of the project. Appellant drew $10,750 for “mobilization” costs incurred for the fire station project—insurance, performance bonds, and equipment costs. However, appellant did not use this money to obtain any performance bonds for the project.

Appellant also received a $20,000 draw for the fire station project. However, the City later contacted Baker and Lawson to complain of the lack of performance on the fire station contract. Baker and Lawson contacted the company responsible for building the fire station’s framework and was informed that the framework had not been completed. Baker and Lawson requested that appellant refund the $20,000 draw, but appellant refused. Baker and Lawson reimbursed the City for the $20,000 draw and for $8,700 of the initial mobilization draw. The City forbade Baker and Lawson from continuing work on the fire station project.

A few months later, appellant’s subcontractors began calling Baker and Lawson to complain that appellant had not paid them for their work on the City Hall project. Appellant made multiple withdrawals—totaling as much as $450,000—from money being held in trust for the subcontractors. However, when the subcontractors invoiced appellant for the work performed, appellant either refused to pay them or issued checks that bounced.

After it became apparent that appellant was not going to pay the subcontractors, Baker and Lawson began paying the subcontractors directly. Baker and Lawson issued a check to one subcontractor, Ben Brown Electric, for $16,000 with the understanding that appellant would reimburse Baker and Lawson. Appellant presented Baker and Lawson with a reimbursement check, which the

3 firm was unable to cash due to insufficient funds. After several attempts to cash the check, Baker and Lawson learned that appellant had stopped payment on the check. Appellant never reimbursed the firm. As a result of appellant’s failure to pay the subcontractors, the City Hall project cost an additional $24,395 to $34,395 over the contract price.

Appellant was charged by two separate indictments of misapplication of trust funds. The first indictment, cause number 66050, contained four counts, with one paragraph in each count and charges related to the SYNEO (Technical Innovations) project. The second indictment, cause number 66951, contained two counts, with three paragraphs in count one and one paragraph in count two and charges related to the Baker and Lawson projects.

Evidence presented at trial indicated that throughout the time he was under contract with both Baker and Lawson and SYNEO, appellant had sufficient funds to pay the subcontractors, but instead made payments to other parties. During the time he was under contract, appellant and appellant’s wife issued checks to appellant, his mother-in-law, his father, his Capital One credit card account, and a health insurance company.

The trial court granted a directed verdict for appellant on the fourth count in cause number 66050. The jury found appellant guilty on counts one, two, and three in the indictment for cause number 66050 and on counts one and two in cause number 66951.2 The jury assessed punishment at eight years’ confinement in the Texas Department of Criminal Justice, Institutional Division in both cause numbers, to be served concurrently. Additionally, the jury assessed a $10,000 fine in cause number 66050. Appellant timely appealed.

2 The trial court also granted a directed verdict for paragraph three of count one in cause number 66951. Two paragraphs remained in count one; the jury found appellant guilty of both.

4 Analysis

In three issues, appellant contends the trial court erred by (1) admitting extraneous-offense evidence during the guilt-innocence phase of trial; (2) failing to require the State to make a paragraph election for cause number 66951; and (3) including a law of parties instruction in the jury charge.

I. Extraneous-Offense Evidence

In his first issue, appellant argues the trial court erred in admitting evidence of extraneous offenses during the guilt-innocence phase of trial. Appellant complains of testimony regarding: (1) his failure to pay five subcontractors who, though under contract for the Baker and Lawson projects, were not named in the indictment; and (2) his manipulation of his business records.

Robin Crouch, the vice president of Baker and Lawson, testified that the firm began paying subcontractors directly “after it was apparent that [appellant] was not going to pay them.” Crouch continued:

A. He told us that he wasn’t paying them. I mean, he would send e- mails. Q. Tell me what you mean, “told us”. He would send e-mails that said what? A. There was one that stated he was paying this, this, and this; and after that, he was broke. So I mean - - Q. And did you - - when you were getting - - when you were corresponding with the subcontractors about not getting paid, did they show you any documents or anything? A. Well, they would show me the invoices. Some of them had where Andy paid some, but there was still a balance remaining.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Francis v. State
36 S.W.3d 121 (Court of Criminal Appeals of Texas, 2000)
Ngo v. State
175 S.W.3d 738 (Court of Criminal Appeals of Texas, 2005)
Landrian v. State
268 S.W.3d 532 (Court of Criminal Appeals of Texas, 2008)
Fleck v. State
201 S.W.3d 268 (Court of Appeals of Texas, 2006)
O'NEAL v. State
746 S.W.2d 769 (Court of Criminal Appeals of Texas, 1988)
Phillips v. State
193 S.W.3d 904 (Court of Criminal Appeals of Texas, 2006)
Hines v. State
3 S.W.3d 618 (Court of Appeals of Texas, 1999)
Johnson v. State
932 S.W.2d 296 (Court of Appeals of Texas, 1996)
Wygal v. State
555 S.W.2d 465 (Court of Criminal Appeals of Texas, 1977)
Montgomery v. State
810 S.W.2d 372 (Court of Criminal Appeals of Texas, 1991)
Gross v. State
380 S.W.3d 181 (Court of Criminal Appeals of Texas, 2012)
Clyde Edwin Hedrick v. State
473 S.W.3d 824 (Court of Appeals of Texas, 2015)
K.J. v. USA Water Polo, Inc.
383 S.W.3d 593 (Court of Appeals of Texas, 2012)
Sifuentes v. State
494 S.W.3d 806 (Court of Appeals of Texas, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Andrew Houston Allen v. State, Counsel Stack Legal Research, https://law.counselstack.com/opinion/andrew-houston-allen-v-state-texapp-2016.