Andrew C. Sisman Co. v. Miller

184 N.W. 456, 215 Mich. 425, 1921 Mich. LEXIS 780
CourtMichigan Supreme Court
DecidedOctober 3, 1921
DocketDocket No. 40
StatusPublished
Cited by2 cases

This text of 184 N.W. 456 (Andrew C. Sisman Co. v. Miller) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Andrew C. Sisman Co. v. Miller, 184 N.W. 456, 215 Mich. 425, 1921 Mich. LEXIS 780 (Mich. 1921).

Opinion

Stone, J.

This case is here upon the appeal of the defendant William H. Miller from a decree for plaintiff for $2,100.25. The sworn bill of complaint was filed July 18, 1917, to enforce a mechanic’s lien against the leasehold interest of defendant Miller in the premises described in the bill of complaint. The lien claim arises under the following circumstances: The defendant Harriet E. Whitbeck is the owner, and defendant Miller has a leasehold interest in said premises, which interest commenced May 1, 1911, and expires May 1, 1931. The premises are generally [426]*426known and described as the “Miller building,” Detroit, Michigan. Plaintiff, a Michigan corporation, was for some years engaged in the general contracting and building business in Detroit, first under the name of Schmied-Sisman Company, and later under the name of Andrew C. Sisman Company. At the time the work commenced, for which a lien is claimed, plaintiff was operating under the name of Schmied-Sisman Company, and thereafter, and before the filing of the bill, its name was changed.

Owing to the irreconcilable conflict in the testimony, it is difficult to state more than the claim of the parties as to the facts in the case. It is the claim of the plaintiff, supported by testimony, that one Harry L. Hulburt, during the year 1916, and for years prior thereto, was employed as an outside superintendent for the plaintiff; and one George D. Hulburt, his brother, was, at or about the same time, an architect in Detroit, having had an office at one time in the Miller building. Prior to, and in 1916, defendant Miller had employed George D. Hulburt as an architect. In June, 1916, George D. Hulburt, as architect for defendant Miller, ordered certain labor and materials from the plaintiff for the repair of the Miller building, and such labor and materials were furnished by the plaintiff, under the supervision of George D. Hulburt, prior to July 6, 1916.

On July 6, 1916, a fire occurred in the said Miller building, resulting in considerable damage thereto. The plaintiff at that time was engaged in making a specialty of fire losses, appraising the loss and repairing damages. Harry L. Hulburt, plaintiff’s superintendent, was told by George D. Hulburt that defendant Miller wanted to see him, and accordingly Harry L. Hulburt met defendant Miller and was requested by the latter to act as an appraiser for defendant Miller, in determining the amount of the fire loss. [427]*427And Harry L. Hulburt was asked by defendant Miller how much the plaintiff would charge for the services of Harry L. Hulburt in making an appraisal of the loss. He advised defendant Miller that plaintiff generally charged $50 to $100 to make an appraisal, but that in the event that the work of repairing the building was done by the plaintiff, it would make no charge for his services as an appraiser. Following this, at the direction of defendant Miller, Harry L. Hulburt acted as an appraiser on behalf of defendant Miller without charge, and with the appraiser appointed on behalf of the insurance company, determined the amount which the insurance company should pay to Miller under the policies, which was $3,936.52. Soon after, defendant Miller requested plaintiff, through Harry L. Hulburt, to take a contract to repair the loss, for the same amount as was allowed by the appraisers, but Miller was then informed that, because parties in making repairs often wanted extra things done, plaintiff would not take a contract on a fire loss at a definite amount, but that plaintiff would take the job on a time and material basis, plus ten and ten. Defendant Miller, in reply, told Harry L. Hulburt that he would like to have the plaintiff do the work, and also said that he, Miller, would have George D. Hulburt prepare certain drawings for partitions and changes, and later plaintiff was furnished with such drawings, and George D. Hulburt advised Harry L. Hulburt that Miller had instructed him to let plaintiff have the work. It may be well to say here that defendant Miller denies this claimed arrangement. He claims that he said to Harry L. Hulburt that he, Miller, had made up, his mind to have the plaintiff do the work, and gave as i reason that, while he did not know the firm, he knew them as large contractors, but that Harry L. Hulburt [428]*428said to him, that the plaintiff was pretty busy, that it was their busy time, and they were short of workmen and foremen, and that he, Miller, should give the contract to George D. Hulburt, and plaintiff would assist George D. Hulburt with workmen and materials, thereby giving George D. Hulburt an opportunity “to get on his feet.”

It appears in evidence that the appraisal was completed July 7th, and on the same day George D. Hulburt wrote a letter to the plaintiff, and sent a copy of the same to defendant Miller:

“Phones: Maine 4123,
Res. East 1132-M.
George D. Hulburt,
Architect and Engineer,
320 Broadway Market Bldg.,
Detroit, Michigan.
“Schmied-Sisman Co., July 7, 1916.
285 Beaufait, Detroit, Michigan,
“Gentlemen: You will please proceed to furnish all labor and material required to make the necessary repairs and alterations, etc., required in a six-story brick building located on the corner of State and Shelby streets, and held under lease by Wm. H. Miller, all to be done on a time and material basis. All materials to be charged net plus ten and ten; all labor to be charged net at your scheduled rate; all bills to be rendered to this office semi-monthly. You will instruct your foreman to keep for the benefit of this office time cards which I will furnish. These cards to be delivered to me weekly.
“Very truly yours,
“Geo. D. Hulburt.
“Note to the owner:
“If the above does not meet with your approval kindly notify this office at once.
“G. D. H. *G.”

Following the receipt of this letter the plaintiff wrote a letter to William H. Miller as follows:

[429]*429“Louis C. Schmied,
President.
Andrew S. Sisman,
Vice-Pres.-Treas.
SCHMIED-SlSMAN COMPANY.
Builders.
387-401 Beaufait Avenue
Lumber, Lath, interior Wood Trim, General Factory Work.
Phone East 2916.
Detroit, Mich., July 12, 1916.
“Wm. H. Miller,
“Cor. State & Shelby Sts.,
“Detroit, Mich.
“Dear Sir: — We are in receipt of the following order from Mr. Geo. D. Hulburt, your architect, and are pleased to accept the same:
‘“You will please proceed to furnish all labor and material required to make the necessary repairs and alterations, etc., required in a six-story brick building located on the corner of State and Shelby streets, and held under lease by Wm. H. Miller, all to be done on a time and material basis.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

STURGIS SAVINGS AND LOAN ASS'N v. Italian Village, Inc.
265 N.W.2d 755 (Michigan Court of Appeals, 1978)
Moss v. Torosian
104 N.W.2d 777 (Michigan Supreme Court, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
184 N.W. 456, 215 Mich. 425, 1921 Mich. LEXIS 780, Counsel Stack Legal Research, https://law.counselstack.com/opinion/andrew-c-sisman-co-v-miller-mich-1921.