Andrecsik v. New Jersey Tube Co.

63 A. 719, 73 N.J.L. 664, 44 Vroom 664, 1906 N.J. LEXIS 101
CourtSupreme Court of New Jersey
DecidedJune 18, 1906
StatusPublished
Cited by12 cases

This text of 63 A. 719 (Andrecsik v. New Jersey Tube Co.) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Andrecsik v. New Jersey Tube Co., 63 A. 719, 73 N.J.L. 664, 44 Vroom 664, 1906 N.J. LEXIS 101 (N.J. 1906).

Opinion

The opinion of the court was delivered by

Dili, J.

This action is brought to recover damages for personal injuries sustained by the plaintiff, while in the defendant’s employ, through the defendant’s alleged negligence.

The plaintiff, a man twenty-eight years of age, had been employed in the defendant’s mill, for about two years prior to the accident — eighteen months as helper, about two months as an assistant upon the machine, and about three months prior to the injury in-charge of the machine at which lie was injured. When placed in charge of the machine he was instructed as to its workings.

Prior to ten o’clock, in the morning of November 11th, 1903, the day’upon which he was injured, the plaintiff discovered that the machine upon which he was working was out of order. He testified that this was very easy to- see.

About ten o’clock' he complained of this to the- superintendent, who replied: “You go right ahead with the work; we are overloaded with work, and noon hour I will fix this for you.”

What a third party understood the superintendent to say is not material to this decision. The foregoing is what the plaintiff asserts the superintendent promised him, and was the agreement to repair upon which the plaintiff relied in resuming work.

The plaintiff continued to work on the machine until the noon hour, quitting at twelve o’clock, without injury. He ate his lunch near the machine — in sight of it — and was in and about the place during the noon hour. During the noon hour, from twelve to one o’clock, the machine was not repaired, and this was apparent to the plaintiff. The defective [666]*666condition, of the machine when the plaintiff resumed work was obvious.

At one o’clock the plaintiff resumed work and continued until three o’clock, when he was injured by this defective machine.

No evidence was offered in behalf of the defence.

The Chief Justice, who tried the case below, nonsuited the plaintiff, and, holding the promise to be definite as to the time of performance, laid down this rule: “Where the master says that he will repair the machine, or have it repaired, at a specific time, the employe is entitled to continue to o]Derate the defective machine at the master’s risk until that time has elapsed; but if, after that time, the master has not made good his word, and made the repairs, and the employe still continues to operate the machine, the risk shifts, and the employe assumes it, relieving the master.”

The plaintiff in error seeks to review this ruling, and for that purpose this writ of error is prosecuted.

We are of the opinion that the rule laid down by the Chief Justice was correct, and that tire nonsuit was proper.

The questions of law decisive of the case at bar have not been heretofore passed upon by this court.

The plaintiff was engaged in operating a machine which was obviously defective. He was aware of the danger inei-, dent to such defective condition.

The servant, by accepting employment or voluntarily continuing therein, with the knowledge or means of knowing the dangers involved, is deemed to- have assumed the risk.

This rule the plaintiff seeks to avoid by proof that he notified the master of the defect, and that the master, for the purpose of inducing the plaintiff to continue in his employment, promised to remedy jt.

The question presented is whether the servant was chargeable, in spite of the promise, with the assumption of the risk in question and as a conclusion of law. The decision must, in the first place, depend upon the character of the promise to repair. Was it express or inferential as to time of fulfillment? If inferential, there may have been a question for [667]*667the jury. If express, there was no question for the jury on that point.

The words “noon hour” are definite terms: “Noon — midday and in exact use twelve o’clock.” — Cent. Dict. “Hour— a particular time; a fixed or appointed time.” — Id.

“Noon” designated the beginning of the period, i. e., twelve o’clock; “hour,” the duration of the period.

It is clearly shown by the evidence that the term “noon hour” was in common use, and was well understood by both parties to mean from twelve o’clock noon to one o’clock in the afternoon.

The plaintiff says he quit work at twelve o’clock and went to work at one o’clock.

Again; he was asked if he worked “before the noon hour” on the day on which he was injured. “Yes, sir,” he answered, “I started at seven and worked until twelve.”

The words “noon hour” are used by the plaintiff and his witnesses, and always as meaning from twelve o’clock noon to one o’clock in the afternoon.

In King-Ryder Lumber Co. v. Cochran, 71 Ark. 55, the plaintiff, who was running an edging machine in a lumber mill, discovered a defect in the machine in the morning and informed the foreman, who told him “to go on and run it until noon, when he would have it repaired.”

The court treated this as a promise to repair at a definite time, and it is cited by subsequent authorities as a definite promise. Otherwise the case is not in point.

In the case before' us, we1 are of the opinion that the promise to repair was not general, but specific, as to time of performance.

The time when the promise to repair should have been fulfilled is too clear for reasonable controversy. There was no need of submitting that question to the jury, or any other question bearing upon the subject.

In discussing the further questions involved it should be noted that in this case:

First. The promise to repair, made after the work was begun, was definite as to the time of performance.

[668]*668Second. The accident did not occur between the time of the making of the promise and before the end of the period fixed for its fulfillment.

Third. The injury was subsequent to (a) the complaint, (&) the promise, (e) the agreed time of performance;, and (d) the master’s default.

In resuming work under these circumstances, was the risk the servant’s or the master’s ?

The two recent cases in the Supreme Court (Dowd v. Erie Railroad Co., 41 Vroom 451, and Dunkerley v. Webendorfer Machine Co., 42 Id. 60), have not heretofore been before this court.

In both the master’s agreement was indefinite as to the time when the repair was to be made.

In the Dowd case the promise was to have it attended to “as soon as he could.”

In the Dunlcerley case the agreement was to remedy the fault “at the first opportunity.”

In the Dowd case, Mr. Justice Swayze states the law to be as follows:

“The rule that the servant assumes not only the ordinary risks incident to the employment, but also- such special features of danger as are plain and obvious, and also^ such as he would discover by the exercise of ordinary care for his personal safet3r, is well established in this state [citing cases].

“The servant assumes, as well, those risks which arise or become known to him during the service as those in contemplation at the original hiring. Dillenberger v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cole v. Mamer Brick Co.
149 N.W. 1044 (Michigan Supreme Court, 1914)
Johnson v. Utah Consolidated Mining Co.
125 P. 407 (Utah Supreme Court, 1912)
Riverside & Dan River Cotton Mills, Inc. v. Carter
74 S.E. 183 (Supreme Court of Virginia, 1912)
Pavan v. Worthen & Aldrich Co.
78 A. 658 (Supreme Court of New Jersey, 1911)
American Tobacco Co. v. Adams
125 S.W. 1067 (Court of Appeals of Kentucky, 1910)
Pankow v. Swift & Co.
74 A. 669 (Supreme Court of New Jersey, 1909)
Comer v. Meyer
74 A. 497 (Supreme Court of New Jersey, 1909)
Elie v. C. Cowles & Co.
73 A. 258 (Supreme Court of Connecticut, 1909)
Haines v. Spencer
167 F. 266 (Third Circuit, 1909)
Morgan v. Rainier Beach Lumber Co.
98 P. 1120 (Washington Supreme Court, 1909)
Crosby v. Cuba R. Co.
158 F. 144 (U.S. Circuit Court for the District of New Jersey, 1908)
Fox v. Kinnear Pressed Radiator Co.
67 A. 1011 (Supreme Court of New Jersey, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
63 A. 719, 73 N.J.L. 664, 44 Vroom 664, 1906 N.J. LEXIS 101, Counsel Stack Legal Research, https://law.counselstack.com/opinion/andrecsik-v-new-jersey-tube-co-nj-1906.