Anderson v. Proctor & Gamble Paper Products Co.

924 F. Supp. 2d 996, 2013 WL 595214, 2013 U.S. Dist. LEXIS 20966
CourtDistrict Court, E.D. Wisconsin
DecidedFebruary 15, 2013
DocketCase No. 11-C-0061
StatusPublished
Cited by3 cases

This text of 924 F. Supp. 2d 996 (Anderson v. Proctor & Gamble Paper Products Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anderson v. Proctor & Gamble Paper Products Co., 924 F. Supp. 2d 996, 2013 WL 595214, 2013 U.S. Dist. LEXIS 20966 (E.D. Wis. 2013).

Opinion

DECISION AND ORDER DENYING MOTION FOR SUMMARY JUDGMENT

WILLIAM C. GRIESBACH, Chief Judge.

Plaintiff Beverly Anderson is the administrator of the estate of her husband, Lloyd Anderson, who worked as a union electrician at various facilities in and around Green Bay, Wisconsin for more [999]*999than 40 years until his retirement in 1992. Plaintiff alleges her husband became ill as a result of occupational asbestos exposure, and she brought claims against various defendants, including a negligence claim against Defendant The Procter & Gamble Paper Products Company (P & GPPC), the owner of the Charmin paper mill where Lloyd Anderson worked as a contract electrician for a number of years. Plaintiffs action was consolidated with numerous cases into the MDL 875 Asbestos litigation, presided over by U.S. District Judge Eduardo C. Robreno in the Eastern District of Pennsylvania. P & GPPC moved for summary judgment, arguing that it is entitled to judgment in its favor because (1) it cannot be liable for harm to an employee of an independent contractor who is working on its premises, and (2) plaintiffs claims are barred by the Wisconsin statute of repose. After briefing was complete, Judge Robreno concluded that P & GPPC’s motion raised unique issues under Wisconsin law and remanded the case. This Court previously granted the plaintiffs motion to file an amended response to P & GPPC’s amended summary judgment motion, and P & GPPC subsequently filed an amended reply. The briefing is now complete, and for the reasons that follow, P & GPPC’s motion will be denied.

BACKGROUND1

Lloyd Anderson worked as a union electrician with the International Brotherhood of Electrical Workers Local 158 in Green Bay, Wisconsin. Anderson began working as an apprentice from approximately 1948, and 1952 until his retirement in 1992, Anderson worked as a journeyman electrician and foreman for numerous electrical contractors at a variety of locations, in-eluding P & GPPC’s Charmin Paper Mill in Green Bay. He estimated that approximately 50 percent of his career was spent working at the Charmin mill between 1955 and 1979, including a period of 10 years of steady work at the mill.

Plaintiffs claim against P & GPPC is based on its status as a nonemployer owner of the mill where Anderson performed electrical work on the mill’s machinery, including “speeding up” paper machines, wiring new machines, maintaining and blowing out switchgear and motors, or performing general electrical work in the warehouse. He also worked with maintenance personnel employed by P & GPPC to repair paper machines after they broke down. In addition, Anderson worked on a large expansion in the 1970s to put in two new paper machines in the Charmin mill. Generally, the crews Anderson was on spent half of their time on new construction and renovation and half of their time remodeling and updating work.

Plaintiff alleges that at P & GPPC, Anderson was exposed to asbestos in a number of ways. Plaintiff contends that the mill contained thousands of feet of insulated electrical, steam, and water pipes, all of which contained asbestos in a variety of forms. The plant was organized so that “all of the process infrastructure” was suspended under the ceilings in layers containing “racks and racks upon racks upon racks of process piping, electrical piping, steam piping, cable trays, electrical facility.” (LaHaye Dep., Ex. 4 at 137, ECF No. 76.) Plaintiff alleges the electricians regularly had to cut through the insulation in order to get to the electrical wiring. Likewise, plaintiff contends the [1000]*1000maintenance and blow-out of switchgear caused significant asbestos exposure. In addition, because the electricians worked on “maintenance days” when the machines were shut down, Anderson often worked in close proximity to pipefitters, pipe insulators, and other P & GPPC employees who were replacing steam pipe insulation, performing repairs, or cleaning up insulation and debris simultaneously. Plaintiff alleges that removing or cutting the insulation created a “plume of cloud dust” due to the brittle nature of the insulation and working in the dusty conditions created by the removal and replacement of the insulation was a “normal, everyday process” for the electricians when assigned to the mill. (Comins Dep., Ex. 3 at 78, ECF No. 76.)

Generally, Anderson’s work was not directed by P & GPPC. Instead, daily instruction and oversight of the electricians came from the electrical contractors. But while Anderson furnished his own hand tools, in general, P & GPPC furnished all materials for the electrical work, including asbestos-containing micarta, and Anderson worked on P & GPPC’s machinery. P & GPPC also controlled the scheduling of insulation teardown and switchgear maintenance. Plaintiff contends that P & GPPC employed inspectors who would check that repairs were completed correctly. These inspectors included P & GPPC’s project engineers, who directed “prestart” inspections. Plaintiff also alleges that P & GPPC provided checklists directing the maintenance work. She asserts that Anderson never received warnings from P & GPPC about the dangers of asbestos, or even that the pipe insulation contained asbestos at all.

Anderson was diagnosed with non-small cell lung cancer in July 2009. He died on November 28, 2011. Plaintiff has submitted expert opinions that Anderson’s lung cancer, asbestosis, and pulmonary fibrosis were caused by occupational exposure to asbestos.

SUMMARY JUDGMENT STANDARD

A motion for summary judgment should be granted “if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56(a). Where factual disputes do exist, the non-movant’s version of events is accepted as true at this stage of the proceedings. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 255, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). The mere existence of some factual dispute does not defeat a summary judgment motion; however, there must be a genuine issue of material fact for the cause of action to survive. Id. at 247-48, 106 S.Ct. 2505. “Material” means that the factual dispute must be outcome-determinative under governing law. Contreras v. City of Chicago, 119 F.3d 1286, 1291 (7th Cir.1997). Failure to support any essential element of a claim renders all other facts immaterial. Celotex Corp. v. Catrett, 477 U.S. 317, 323, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). A “genuine” issue of material fact requires specific and sufficient evidence that, if believed by a jury, would actually support a verdict in the nonmovant’s favor. Fed.R.Civ.P. 56(e); Anderson, 477 U.S. at 249, 106 S.Ct. 2505. Where the record taken as a whole could not lead a rational trier of fact to find for the nonmoving party, there is no genuine issue for trial. Matsushita Elec. Indus. Co. v. Zenith Radio Corp.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carol Lorbiecki v. Pabst Brewing Company
2024 WI App 33 (Court of Appeals of Wisconsin, 2024)
Holder v. Fraser Shipyards, Inc.
288 F. Supp. 3d 911 (W.D. Wisconsin, 2018)
Viola v. Wisconsin Electric Power Co.
2014 WI App 5 (Court of Appeals of Wisconsin, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
924 F. Supp. 2d 996, 2013 WL 595214, 2013 U.S. Dist. LEXIS 20966, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anderson-v-proctor-gamble-paper-products-co-wied-2013.