Anderson v. Irving Park District

209 Ill. App. 350, 1918 Ill. App. LEXIS 629
Appellate Court of Illinois·Decided January 30, 1918·No. Gen. No. 23,218·Published

Opinion

Mr. Justice O’Connor

delivered the opinion of the court.

H. M. Anderson brought suit against the Irving Park District to recover $1,393.97, claimed as damages for breach of a contract. There was a finding and judgment in his favor for one cent, to reverse which he prosecutes this appeal.

The record discloses that the defendant was desirous of constructing a building in its park, and for that purpose entered into a written agreement with the plaintiff and William E. Gibb. The contract provided, inter alia, that Anderson and Gibb were to furnish suitable plans and specifications for the proposed building, and perform all architectural services, including superintendency, in and about the construction of the building. Gibb was to perform all architectural services, except superintendency, and Anderson was to superintend 'the construction of the building under the supervision of Gibb. In consideration of the services to be rendered by Anderson and Gibb, the defendant agreed to pay a sum not to exceed 5 per cent, of the aggregate amount of all contracts let for the construction of the building, one half to be paid when the work on the building was actually commenced, one quarter when it was under roof, and the remaining quarter when the building was completed. Gibb, who was an architect, prepared plans and specifications for the building. These were revised and amended to meet the suggestions of the defendant. The estimated cost of the building, under the final draft of the plans and specifications, was $55,758.80. The defendant was dissatisfied on the ground that the cost was too high, and refused to permit Anderson and Gibb to do anything further towards carrying out the contract. Shortly thereafter, however, defendant employed another architect under whom the proposed building was constructed at a cost of about $57,000. Gibb brought suit in the Municipal Court of Chicago to recover the reasonable value of the services which he had rendered in the preparation of the plans and specifications and recovered judgment for $1,393.97. On appeal to this court by the defendant the judgment was affirmed, and the Supreme Court denied certiorari. (Gibb v. Irving Park District, 197 Ill. App. 480.) Afterwards Anderson instituted the instant case.

Plaintiff contends that as Gibb recovered one half of the 5 per cent, of the estimated cost of the building, he was entitled, under the contract, to the other half, the amount for which he brought suit. In support of this contention it is argued that under the contract the defendant agreed to pay 5 per cent, of the estimated cost of the building; that the estimated cost was $55,-758.80, 5 per cent, of which is $2,787.94; that as Gibb had performed all services required of him and had recovered one-half of the 5 per cent., plaintiff was entitled to the balance. We cannot agree that Gibb had performed all the services required of him. He had only prepared the plans and specifications, and under the contract his services would be required until the building was completed. Anderson and Gibb were required during the course of construction of the building to issue certificates or vouchers to the building contractors from time to time. There was a further provision that if Anderson and Gibb should, at any time after the actual work on the building commenced, refuse or fail to carry out the terms of the contract they should receive only a pro rata share of the compensation. It is common knowledge that where an architect is employed to perform the architectural work on a building, his services are not only required| in the preparation of plans and specifications, but are; required during the construction of the building and until it is completed, unless there is found a provision dispensing with such services after the plans and specifications are prepared, and there is no such provision in the contract in question; but on the contrary, by its express terms, Gibb was required to perform services until the building was completed. There is no provision for a division between Anderson and Gibb of the compensation to be paid them. In the Gibb case, supra, another division of this court held that the contract in question constituted two " separate and wholly distinct subject-matters, * * * one, the provision for all services except superintendency by Gibb, and the other, the superintendency by Anderson under the supervision of Gibb.”

In the instant case, which is brought for breach of a contract (the proper remedy, Doherty v. Schipper & Block, 250 Ill. 128), the damages, if any, accrued to the benefit of Gibb and Anderson jointly, since both were prevented from performing services under the contract, and no part of the compensation for the services yet to be rendered was to be paid to either Gibb or Anderson, but was to be paid to both jointly.

Free access — add to your briefcase to read the full text and ask questions with AI

Anderson v. Irving Park District, 209 Ill. App. 350, 1918 Ill. App. LEXIS 629 (Ill. Ct. App. 1918).

209 Ill. App. 350 (Anderson v. Irving Park District) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United Press v. . New York Press Co.
58 N.E. 527 (New York Court of Appeals, 1900)
Doherty v. Schipper & Block
95 N.E. 74 (Illinois Supreme Court, 1911)
United Press v. New York Press Co.
54 N.Y.S. 807 (Appellate Division of the Supreme Court of New York, 1898)
Gibb v. Irving Park District
197 Ill. App. 480 (Appellate Court of Illinois, 1916)