Anderson v. Hobbs

Procedural entryThis page is a short order in Anderson v. Hobbs. Read the opinion of the Court — 196 Mont. 31
Montana Supreme Court·Decided December 7, 1981·No. 81-097·Published

Opinion

No. 81-97 IN THE SUPREME COURT OF THE STATE OF MONTANA 1981

LEN ANDERSON, d/b/a LEN ANDERSON CONSTRUCTION COMPANY, Plaintiff and Respondent,

NORMAN D. HOBBS, individually and NORMAN D. HOBBS, d/b/a C. D. VENTURES, Defendant and Appellant.

Appeal from: District Court of the Fifth Judicial District, In and for the County of Beaverhead. Honorable Frank Blair, Judge presiding. Counsel of Record: For Appellant: Harrison, Loendorf and Poston, Helena, Montana For Respondent: Drysdale, McLean, Screnar & Cok, Bozeman, Montana

Submitted on briefs: August 27, 1981

Filed: gkc. - 'T [h!8;i

Clerk Mr. Justice John Conway Harrison delivered the Opinion of the Court. This appeal arises from a contract for construction on appellant's nursing home in Dillon, Montana. The parties entered into the written agreement in January 1977, and the work was completed sometime in the late summer of 1977. Respondent filed a mechanics' lien against appellant's property on October 19, 1977. After trial without a jury, the District Court of the Fifth Judicial District upheld the lien and issued a judgment for $15,687.92 plus interest and attorney fees. This appeal followed. In December 1976, at the request of appellant, respondent, a general contractor doing business as Len Anderson Construction Co., a sole proprietorship, began work on Park View Acres in Dillon, Montana, a nursing home owned by appellant, Norman D. Hobbs, doing business as C. D. Ventures. In January 1977 the parties entered into a written contract whereby respondent would renovate the existing fifty-four-bed facility of Park View Acres and add a fifty- four-bed wing to the building. The contract provided appel- lant would pay respondent all costs plus an eight percent contractor's fee. Costs included all costs necessarily incurred in the proper performance of work paid by the con- tractor; all wages paid for labor in the direct employ of the contractor; all salaries of contractor's employees; a portion of reasonable transportation, traveling and hotel expenses of the contractor, its officers and employees incurred in the discharge of their duties; the cost of all materials, supplies and equipment incorporated into the work; all payments made by the contractor to subcontractors for work performed according to subcontracts under this agreement; and costs, including transportation and main- tenance, of all materials, supplies, equipment, temporary facilities and hand tools not owned by the workmen, which are consumed in the performance of the work, and the costs less salvage value on such items used but not consumed which remained property of the contractor. Respondent concluded construction on the project in the summer of 1977. On October 19, 1977, respondent filed a lien in the amount of $31,218.27. On the lien application respondent stated his final day of performance on the project was July 21, 1977. At trial respondent testified his last full-time work on the project was in the middle of August 1977. Respondent also introduced a "punch list" prepared by appellant's employees and dated September 23, 1977. Respondent argued the "punch list" established the last day respondent spent any time on the job was in September. The costs claimed by respondent were supported almost exclusively at trial by cancelled checks. The District Court found the lien was filed within the ninety-day period required by Montana statute. The court also found respondent's lien valid and enforceable and made the following determination of the amount owing: Costs for Anderson's out-of-pocket expenses. . . . . . .$150,362.72 Defendant's payments to date for expenses. ....... 139,633.00 $ 10,729.72 Due Plaintiff for costs. ....... .$ 10,729.72 Contractor's fee as a portion of 8% of contract and total costs on contract . .... .$366,977.56 Contractor's fee equals 8% of $366,977.56, for a total of. .. . . . .. . ..... 29,358.28 Defendant's payment to date for contractor's fee. . . . . . . . 12,600.00 Due Plaintiff for contractor's fee ............... . $ 16,758.28

Total due to Plaintiff by Defendant for costs ........ 10,729.72 Total due to Plaintiff by Defendant for fees. . . . . . . . . 16,758.20 TOTAL. . . . . . . . . . . . . . . . . .$ 27,487.92 LESS THE FOLLOWING OFFSETS: Liquidated damages. . . . . . . . . 8,000.00 Lumber from personal stock. . . . . 3,800.00 TOTALOFFSETS. . . . . . .$11,800.00 TOTAL DUE TO PLAINTIFF . . . . . . . . . $ 15,687.92 Four issues are before this Court: 1. Was the lien filed by respondent within the statutory ninety-day period? 2. Are there gross and substantial exaggerations in claims made which constitute fraud and void the filed lien? 3. Did the District Court err in failing to make certain deductions to the amount of the lien? 4. Did the District Court err in determining in the memorandum supporting its findings of fact and conclusions of law that Exhibit K was inadmissible as hearsay? To perfect a mechanics' lien it must be filed within ninety days after material or machinery is furnished or work or labor performed. Section 7-3-511(1), MCA. Appellant argues there is no credible evidence on the record to support the District Court's finding that the lien was filed within the statutory period. Respondent filed the lien on October 19, 1977, and on the lien stated the last work had been done on July 21, 1977. Appellant claims that the last work was performed by respondent on July 15, 1977, which was when the nursing home opened. At trial, respondent testified the date listed on the lien was incorrect and that, in fact, h i s l a s t f u l l t i m e o n t h e j o b was i n t h e m i d d l e o f A u g u s t

and t h a t he r e t u r n e d i n S e p t e m b e r t o c o m p l e t e t h e p r o j e c t .

Respondent a l s o s u b m i t t e d i n t o e v i d e n c e a "punch l i s t " p r e -

p a r e d by a p p e l l a n t ' s employee c o n t a i n i n g t h e d a t e S e p t e m b e r

23.

The District Court found the lien had been filed

w i t h i n t h e n i n e t y - d a y p e r i o d and s p e c i f i e d r e s p o n d e n t ' s work

was c o m p l e t e d on A u g u s t 1 9 , 1 9 7 7 .

The s t a n d a r d of t h i s C o u r t on r e v i e w i s w h e t h e r t h e

D i s t r i c t C o u r t ' s f i n d i n g s and c o n c l u s i o n s a r e s u p p o r t e d by

s u b s t a n t i a l c r e d i b l e evidence. T o e c k e s v . Baker ( 1 9 8 0 ) , - Mont . , 6 1 1 P.2d 609, 37 S t . R e p . 948. If substantial

evidence e x i s t s , t h i s Court w i l l n o t o v e r t u r n t h e D i s t r i c t

C o u r t . Schuman v . S t u d y Comm'n o f Y e l l o w s t o n e County ( 1 9 7 8 ) ,

176 Mont. 3 1 3 , 578 P . 2 d 291.

It is apparent from the record and the District

C o u r t ' s f i n d i n g s t h a t t h e c o u r t gave c o n s i d e r a b l e weight t o

r e s p o n d e n t ' s t e s t i m o n y a t t r i a l t h a t h i s l a s t f u l l - t i m e work

on t h e p r o j e c t was i n mid-August 1977. In its supporting

memorandum, t h e D i s t r i c t C o u r t c h o s e A u g u s t 1 9 , 1 9 7 7 , a s t h e

final date. The r e c o r d makes no m e n t i o n o f that specific

d a t e i n August. T h e r e f o r e , t h e f i n d i n g of August 19 c a n n o t

be a f f i r n e d . T h i s C o u r t w i l l , however, g i v e c r e d e n c e t o t h e

weight t h e D i s t r i c t Court obviously gave r e s p o n d e n t ' s t e s t i -

mony.

"The c r e d i b i l i t y and w e i g h t g i v e n t h e w i t n e s s e s ... is n o t f o r t h i s Court t o determine. T h i s is a p r i m a r y func-

tion of a trial judge sitting without a jury; it is of

Free access — add to your briefcase to read the full text and ask questions with AI

Anderson v. Hobbs, (Mo. 1981).

Anderson v. Hobbs (Anderson v. Hobbs) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Hellickson v. Barrett Mobile Home Transport, Inc.
507 P.2d 523 (Montana Supreme Court, 1973)
Morgen & Oswood Construction Co. v. Big Sky of Montana, Inc.
557 P.2d 1017 (Montana Supreme Court, 1976)
Morrison v. City of Butte
431 P.2d 79 (Montana Supreme Court, 1967)
Eskestrand v. Wunder
20 P.2d 622 (Montana Supreme Court, 1933)
Audit Services, Inc. v. Brasel & Sims Construction Co.
575 P.2d 908 (Montana Supreme Court, 1978)