Anderson Lumber Co. v. Friedlander

24 A. 434, 54 N.J.L. 375, 25 Vroom 375, 1892 N.J. LEXIS 24
CourtSupreme Court of New Jersey
DecidedMarch 15, 1892
StatusPublished
Cited by2 cases

This text of 24 A. 434 (Anderson Lumber Co. v. Friedlander) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anderson Lumber Co. v. Friedlander, 24 A. 434, 54 N.J.L. 375, 25 Vroom 375, 1892 N.J. LEXIS 24 (N.J. 1892).

Opinion

The opinion of the court was delivered by

Van Syckel, J.

This is an action upon a Mechanics’ Lieu claim.

Friedlander, the owner, made a contract with Jeroleman & Craft for the erection of a building on his lands in Passaic county, which contract was dated September 6th, 1890, and filed September 9th, 1890. The contract contained no stipulation for the production and delivery by the contractor to the owner of release and affidavit, such as are mentioned in the act of June 19th, 1890. Pamph. L., p. 479.

Jeroleman & Craft made, a sub-contract with the defendant Davenport, dated October 25th, 1890, for the mason work of said building, and Davenport, in the execution of said subcontract, purchased brick and other materials of the plaintiff for said building, amounting to the sum of $489.48.

It appeared that Davenport did not complete his contract with Jeroleman & Craft; but the materials furnished by the plaintiff had been used by him in the erection of the building before he gave up the work.

Upon this state of facts the plaintiff was non-suited in the trial court.

The Mechanics’ Lien law, as it read prior to 1890, provided :

1. Every building hereafter erected or built within this state shall be liable for the payment of any debt contracted and owing to any person for labor performed or materials furnished for the erection and construction thereof, which debt shall be a lien on such building and on the land whereon it stands, including the lot or curtilage whereon the same is erected.

“ 2. When any building shall be erected in whole or in part by contract in writing, such building, and the land whereon it stands, shall be liable to the contractor alone for work done and materials furnished in pursuance of such contract; pro[377]*377-<oided, such contract, or a duplicate thereof, be filed in the office of the clerk of the county in which such building is situate before such work done or materials furnished.”

Section 3 provides for notice to the owner to retain in his ■hands the amount due to any laborer or materialman when the contractor shall, upon demand, refuse to pay.

From the second section above quoted the supplement of 1890 strikes out the last seven words, and to it adds the following :

“And further provided, that at the time of the making of the payment of the price stipulated and agreed to be paid therein, and every installment thereof, the contractor or contractors shall produce and deliver to the owner or owners of such building the release of all persons who may then have furnished materials used in the erection of such building, and -of all journeymen employed in the erecting or construction thereof, and who may have a lien upon such building or lands by virtue of this act,„releasing their lien on such building and on the said land whereon it stands, including the said lot or -curtilage whereon the same is erected, for the payment of any ■debt contracted and owing to them for labor performed or materials furnished for the erection and construction of such ■building, in accordance with a stipulation to that effect to be inserted in such contract, which release shall have thereunto ■annexed an affidavit made and subscribed by such contractor, before any public officer of this state authorized to administer oaths and affirmations, setting forth the names, and residences of all such materialmen, journeymen and laborers, and the several sums of money due to each of them, respectively, for work done or material furnished in the erection of such building, and further setting forth that such materialmen, journeymen and laborers, and no other person or persons, have any lien upon such building or lands by reason of work done or materials furnished for the erection and construction of such building.” Paraph. L., p. 479.

The first section of the law above set forth gives a lien to the laborer and materialman in all cases.

[378]*378The second section, as it stood prior to 1890, and as now amended, provides a way in which the building may be protected from lien, except for the claims of the contractor.

The second section, neither before nor after its amendment, was intended to confer the right to lien. Its purpose was to-limit the general right to lien conferred by section 1.

The difficulty in this case arises from the peculiar phraseology of the act of 1890. It certainly is obscure and fails to-express with clearness the purpose which its draftsman had in-view, yet, I think that, without violating settled rules of interpretation, a construction may be put upon the words, “ in accordance with a stipulation to that effect to be inserted in the contract,” which will give effect to the purpose of the amended section, so far as it can be discerned in the language used.

It cannot be that, in order to make the amendment applicable and secure immunity to the owner, there must be a stipulation in the contract that a release shall be produced to the owner.

Such a reading of the statute would render it absurd. If every one who has a claim for labor or material releases the owner, the right to lien must be equally extinguished whether or not there is a contract filed, or a stipulation inserted in it that the contractor shall secure releases to the owner. Such a provision in the contract adds nothing to the force and value-of a release.

The proper antecedent to the’language above recited are the-words immediately preceding it, and it must be read as follows : “ For the payment of any debt contracted and owing to them for labor performed or materials furnished for the erection and construction of such building, in accordance with, a stipulation to that effect to be inserted in the contract.”

To discharge the liability to a lien for work done under a contract, not only must the contract be filed, but at the time-the owner makes any payment due the contractor he must procure from him a release, executed by every laborer and) materialman for such labor and materials as were requisite to* [379]*379be used in the performance of the contract work. For all labor done and materials used in doing the work specified im the contract, a release must be presented to defeat the right to-lien. If the owner makes a contract with A to do the mason work of the building, and a contract with B to do the carpenter work, then the fact that the owner makes a payment to-B on the carpenter work, without releases from those who-have been employed in such carpenter work, will not give rise-to the right to file a lien by those who were engaged in the-contract mason work, and vice versa. Of course, for all work: done outside of the contracts filed a lien attaches in virtue of the first section of the law. The language of the act is-inaptly chosen and not free from obscurity, but it is susceptible of such a construction.

The third section, allowing notice to be given to the owner to retain money due the contractor in his hands, is still in force, and, in my judgment, the controlling object of the-framer of the act of 1890 was to render this section more-effective as a protection to the laborer and materialman.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bruce v. Pearsall
34 A. 982 (Supreme Court of New Jersey, 1896)
Bradley & Currier Co. v. Berns
51 N.J. Eq. 437 (New Jersey Court of Chancery, 1893)

Cite This Page — Counsel Stack

Bluebook (online)
24 A. 434, 54 N.J.L. 375, 25 Vroom 375, 1892 N.J. LEXIS 24, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anderson-lumber-co-v-friedlander-nj-1892.