Anderson & Co. v. Brammer

58 So. 941, 4 Ala. App. 596, 1912 Ala. App. LEXIS 357
CourtAlabama Court of Appeals
DecidedMay 7, 1912
StatusPublished
Cited by3 cases

This text of 58 So. 941 (Anderson & Co. v. Brammer) is published on Counsel Stack Legal Research, covering Alabama Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anderson & Co. v. Brammer, 58 So. 941, 4 Ala. App. 596, 1912 Ala. App. LEXIS 357 (Ala. Ct. App. 1912).

Opinion

PELHAM, J.

This is an action for the breach of a special contract, an oral agreement entered into between the appellee and the appellants, under the terms of which, for a certain specified consideration for each house, the appellee promised and undertook so paint 50 houses for the appellants. The houses were of three kinds or classes; for one kind plaintiff was to receive $5.50 each, and $7.50 and $10 each respectively, for the other two; there being 25 houses rated at $5.50 each, 16 at $7.50 each, and 9 at $10 each. Alleging a breach of the contract and failure upon appellants’ part to allow him to complete the work under the contract, appellee sued to recover damages. The complaint also contained counts for work and labor done and money dne by account. Demurrers were filed to the complaint, and certain rulings are shown on these demurrers, but' by an agreement subsequently entered into between the counsel for both parties to the suit, with consent of the court, the case was tried on plea of the general issue with “leave to give in evidence any matter of defense which might be admissible if specially pleaded, and with like effect as if specially pleaded,” with the agreement, also, that the plaintiff might give in evidence any matter which would be admissible under special replication. No question is raised on the pleading; all of the assignments of error go to the court’s rulings on the evidence and to' charges requested by each of the parties.

The evidence introduced in behalf of the plaintiff tended to show that he was a competent painter of six years’ experience; that plaintiff entered into a verbal contract with defendants to paint the houses for the defendant at about the prices stated, the defendants to furnish the material; that, after he put the first coat, or priming, on 17 houses of the $5.50 class, the defendants- sent him off on another job, and when he returned refused to allow [599]*599him to complete the contract without giving a bond for proper performance; that nothing had been said in the original contract about furnishing a bond. Defendants refused to allow plaintiff to complete the work and paid plaintiff $17 on account of the work done and had the job finished by another painter. Plaintiff could have completed the work called for by the contract at the time he was stopped by defendants in 17 more working days with the assistance of one helper, whose services could be secured at $1.50 per day. That the work done under the contract by plaintiff and his helpers, when plaintiff was stopped by defendants, was done in a first-class, workmanlike manner, but that the materials furnished to plaintiff by defendants were inferior; that the best work that could be accomplished with the materials furnished was done.

The defendants’ evidence tended to show that the agreement or contract was for the work to be done in a good and workmanlike manner subject to the approval of an inspector; that proper material was furnished, but that it was poorly mixed, wasted, and improperly put on, and that the work was not done in a good and workmanlike manner; that it was rejected by the inspector, and that the inspector and one of the defendants notified the plaintiff of the rejection of the work, and defendants refused to allow plaintiff to complete the work unless he would give a bond that would protect defendants from loss or failure to do proper work; that no bond was furnished, and defendants paid plaintiff $17 for the work and labor performed and had the work completed by other labor at a cost of about $40 more than the contract price.

■ Confessedly the measure of damages recoverable for a breach of the contract by defendant in a suit at the hands' of the plaintiff would be the difference between the price [600]*600agreed upon and the amount it would have cost the plaintiff to complete the work. The only proof made going to show this amount is the evidence of plaintiff that the job could have been completed in 17 working days by the plaintiff giving to it his personal labor and having the help of an assistant at the rate of $1.50 per day. The value of the labor or services of the plaintiff is not shown by the testimony, and, when the defendants on cross-examination undertook to elicit such information from plaintiff, the court sustained objections interposed by plaintiff’s counsel, and on the other hand allowed the plaintiff to show, against the objection of the defendants, that the plaintiff had endeavored to obtain employment after being stopped from work on the contract, and had been unable to procure employment for a period of three months, or until after the contract would have been completed. This was clearly erroneous, as the question of plaintiff’s being able to secure or not to secure work could have no proper place in estimating the damages he might be entitled to recover for a breach of the contract; the proper measure being the contract price less the cost of completion, the profit that would accrue from the performance.—Peck-Hammond Co. v. Heifner, 136 Ala. 473, 33 South. 807, 96 Am. St. Rep. 36; Smith v. Davis, 150 Ala. 106, 43 South. 729; Bonifay v. Hassell, 100 Ala. 269, 14 South. 46; Worthington & Co. v. Gwin, 119 Ala. 44, 24 South. 739, 43 L. R. A. 382.

One of the questions at issue in the case was whether or not the work done by the plaintiff had been executed in a good and workmanlike manner. The plaintiff was allowed to show that the work done up to the time he was stopped by the defendants had been done in such a manner, and the plaintiff’s witness Bailey testified “that he considered the plaintiff a good and competent painter.” Under such circumstances, the court was in error in [601]*601sustaining the objection interposed by plaintiff’s counsel to the questions asked defendants’ witness Edwards-, a builder and contractor of 25 years’ experience, seeking, to show that be bad knowledge of plaintiff’s competency, etc., for the purpose of eliciting evidence showing that plaintiff was not a competent painter. The question sufficiently shows that the evidence sought to be elicited was competent as tending to shed light on the character of work done by plaintiff and to directly rebut the plaintiff’s testimony of the competency of plaintiff as a painter.

The court was also in error in refusing to allow the defendant to show by the witness Smith that the plaintiff had made admissions to said witness in reference to the manner he had performed the work. It is common knowledge that good and workmanlike painting cannot be done with a broom, and the question asked this witness, “state whether or not the plaintiff ever told you that he put the paint on the houses in question with a broom,” should have- been allowed. The appellee’s criticism of this question urged in brief to the effect that there were no “houses in question,” that the only thing in question was the painting, is hypercritical. This question called for an admission against interest that was relevant and material, made by a party to the suit, and such admissions are always admissible.—L. & N. R. R. Co. v. Hurt, 101 Ala. 34, 48, 13 South. 130; Moore v. Crosthwait, 135 Ala. 272, 33 South. 28; Brown v. Fowler, 133 Ala. 310, 32 South. 584; Polly v. McCall, 37 Ala. 20.

From what we have said in reference to the measure of damages, it will be seen that the court was clearly in error in refusing charge No. 7 requested by the defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Med Plus Properties v. COLCOCK CONST.
628 So. 2d 370 (Supreme Court of Alabama, 1993)
Cobbs v. Fred Burgos Const. Co.
477 So. 2d 335 (Supreme Court of Alabama, 1985)
Whiting v. Dodd
94 So. 2d 411 (Alabama Court of Appeals, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
58 So. 941, 4 Ala. App. 596, 1912 Ala. App. LEXIS 357, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anderson-co-v-brammer-alactapp-1912.