Anchor Pipe Company, Inc. v. Sweeney-Bronze Development, LLC

CourtCourt of Appeals of Tennessee
DecidedAugust 2, 2012
DocketM2011-02248-COA-R3-CV
StatusPublished

This text of Anchor Pipe Company, Inc. v. Sweeney-Bronze Development, LLC (Anchor Pipe Company, Inc. v. Sweeney-Bronze Development, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anchor Pipe Company, Inc. v. Sweeney-Bronze Development, LLC, (Tenn. Ct. App. 2012).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE May 22, 2012 Session

ANCHOR PIPE COMPANY, INC. v. SWEENEY-BRONZE DEVELOPMENT, LLC ET AL.

Appeal from the Circuit Court for Sumner County No. 2008CV31941 C.L. Rogers, Judge

No. M2011-02248-COA-R3-CV - Filed August 2, 2012

This appeal concerns the priority of two liens, a mechanic’s lien and a bank’s deed of trust. We have determined that the trial court erred in granting summary judgment in favor of the bank. We have further determined that the mechanic’s lien is entitled to priority and that the trial court erred in failing to grant summary judgment on that issue.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Circuit Court Reversed and Remanded

A NDY D. B ENNETT, J., delivered the opinion of the Court, in which F RANK G. C LEMENT, J R. and R ICHARD H. D INKINS, JJ., joined.

Todd E. Panther and Stephen Andrew Lund, Nashville, Tennessee, for the appellant, Anchor Pipe Company, Inc.

James Campbell Bradshaw and David Andrew Amonette, Nashville, Tennessee, for the appellee, Trust One Bank.

OPINION

F ACTUAL AND P ROCEDURAL B ACKGROUND

The facts underlying this case arose during the development of Enoch Hills subdivision in Gallatin, Tennessee. Prior to the construction of residential lots, the property was owned by JSC, LLC. Jeffrey Bronze negotiated with James Thigpen, the president of Anchor Pipe Company, Inc. (“Anchor”) about doing work on the property. It is undisputed that Anchor had a valid contractor’s license with a monetary limit of $750,000.00 throughout the relevant time period. Anchor gave a total bid of $3,521,952.00 on the work to be performed on this project. Bronze engaged Anchor to do the work, and Anchor began work on the property in February 2007.

In May 2007, JSC, LLC transferred title to the property to Sweeney-Bronze Development, LLC (“SBD”). Trust One Bank, which provided a construction loan to SBD, recorded a deed of trust on July 24, 2007. Although SBD held title to the property, a different entity—Sweeney-Bronze Holdings (“SB Holdings”)—was the grantor of the bank’s deed of trust. Anchor continued to perform work on the property. On June 27, 2008, Bronze told Anchor that he could no longer pay for the work, and Anchor stopped all work on the project. As of that date, SBD had paid Anchor $659,579.06 for work on the project.

On July 1, 2008, Anchor recorded a notice of lien against the property in the amount of $703,192.84; and, on July 25, 2008, Anchor recorded a notice of lien in the additional amount of $140,396.55. On November 12, 2008, a deed was recorded transferring title from SBD to SB Holdings. The bank recorded an amended and restated deed of trust on the same day, again (this time, correctly) listing SB Holdings as the grantor. Anchor recorded an amended lien on June 10, 2009 for a total claim of $625,864.

On June 17, 2009, Anchor filed a verified amended complaint against SBD, SB Holdings, Bronze Construction, LLC, Jeffrey Bronze, Jeffrey Sweeney, JSC, and Trust One Bank.1 In its complaint, Anchor set forth causes of action for breach of contract, unjust enrichment, enforcement of lien, and violation of the Prompt Pay Act; Anchor also sought a declaratory judgment that its lien took priority over the bank’s deed of trust. The bank and Anchor filed cross-motions for summary judgment.

The motions for summary judgment were heard in August 2011, and the court reached the following pertinent conclusions:

Contractor is found to be not licensed for the project from its inception. Contractor is allowed recover[y] of only documented expenses pursuant to T.C.A. § 62-6-103(b). Absence of a valid contractor’s license causes a forfeiture of lien rights. Counsel for Contractor relies upon case law which is distinguishable from the case at hand. In the case before this Court, the Contractor was not properly licensed at the inception of the contract not thereafter, contrary to case law relied upon by counsel.

Reasonable minds could not differ the January 20, 2007 e-mail between Contractor and Developer represents an agreement by Contractor to

1 The original complaint to enforce lien is not a part of the record on appeal.

-2- subordinate its lien to Bank. The Construction Loan, after such agreement, was thereafter made. The material e-mail facts are not disputed. Counsel for Contractor puts forth argument [that] such subordination is not enforceable because no written subordination or release was sent to or signed by his client. The Court finds no legal requirement calling for a written agreement in this case.

It is not necessary to address the dispute between Bank and Contractor as to visible commencement of work.

Based upon this analysis, the trial court determined that the bank was entitled to judgment and dismissed Anchor’s claims against the bank. Upon the bank’s subsequent motion, the trial court entered an order on September 20, 2011 making the court’s order granting summary judgment to the bank a final order.

Anchor appeals the trial court’s decision granting summary judgment to the bank. Anchor asserts that, contrary to the trial court’s conclusions, it has lien rights and those rights take priority over the bank’s lien rights.

S TANDARD OF R EVIEW

Summary judgment is appropriate when there is no genuine issue of material fact and the moving party is entitled to a judgment as a matter of law. Tenn. R. Civ. P. 56.04. Summary judgments do not enjoy a presumption of correctness on appeal. BellSouth Adver. & Publ’g Co. v. Johnson, 100 S.W.3d 202, 205 (Tenn. 2003). In reviewing a summary judgment, this court must make a fresh determination that the requirements of Tenn. R. Civ. P. 56 have been satisfied. Hunter v. Brown, 955 S.W.2d 49, 50 (Tenn. 1997). We consider the evidence in the light most favorable to the non-moving party and resolve all inferences in that party’s favor. Godfrey v.. Ruiz, 90 S.W.3d 692, 695 (Tenn. 2002). When reviewing the evidence, we must determine whether factual disputes exist. Byrd v. Hall, 847 S.W.2d 208, 211 (Tenn. 1993). If a factual dispute exists, we must determine whether the fact is material to the claim or defense upon which the summary judgment is predicated and whether the disputed fact creates a genuine issue for trial. Id.; Rutherford v. Polar Tank Trailer, Inc., 978 S.W.2d 102, 104 (Tenn. Ct. App. 1998). To shift the burden of production to the nonmoving party who bears the burden of proof at trial, the moving party must negate an element of the opposing party’s claim or “show that the nonmoving party cannot prove an essential element of the claim at trial.” Hannan v. Alltel Publ’g Co., 270 S.W.3d 1, 8-9 (Tenn. 2008).

-3- A NALYSIS 1.

Anchor’s first argument is that the trial court erred in concluding that it was an unlicensed contractor. The pertinent facts on this issue are not in dispute: Anchor had a contractor’s license throughout its work on the project, and this license authorized Anchor to perform the type of work it performed (underground piping, grading and drainage, and base and paving work). The monetary limit on Anchor’s license, however, was $750,000, whereas Anchor’s bids exceeded two million dollars. The bank asserts, and the trial court agreed, that Anchor was unlicensed because it bid on and performed work in excess of the monetary limits of its license.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jones v. LeMoyne-Owen College
308 S.W.3d 894 (Court of Appeals of Tennessee, 2009)
Levine v. March
266 S.W.3d 426 (Court of Appeals of Tennessee, 2007)
Brown v. Tennessee Title Loans, Inc.
328 S.W.3d 850 (Tennessee Supreme Court, 2010)
Lee Medical, Inc. v. Paula Beecher
312 S.W.3d 515 (Tennessee Supreme Court, 2010)
Linda F. Seals v. H & F, Inc.
301 S.W.3d 237 (Tennessee Supreme Court, 2010)
Hannan v. Alltel Publishing Co.
270 S.W.3d 1 (Tennessee Supreme Court, 2008)
Kyle v. Williams
98 S.W.3d 661 (Tennessee Supreme Court, 2003)
Godfrey v. Ruiz
90 S.W.3d 692 (Tennessee Supreme Court, 2002)
Jordan v. Baptist Three Rivers Hospital
984 S.W.2d 593 (Tennessee Supreme Court, 1999)
Klosterman Development Corp. v. Outlaw Aircraft Sales, Inc.
102 S.W.3d 621 (Court of Appeals of Tennessee, 2002)
Bellsouth Advertising & Publishing Co. v. Johnson
100 S.W.3d 202 (Tennessee Supreme Court, 2003)
Anderson v. Durbin
740 S.W.2d 417 (Court of Appeals of Tennessee, 1987)
Gene Taylor & Sons Plumbing Co. Inc. v. Corondolet Real. Trust
611 S.W.2d 572 (Tennessee Supreme Court, 1981)
Rutherford v. Polar Tank Trailer, Inc.
978 S.W.2d 102 (Court of Appeals of Tennessee, 1998)
Cohen v. Cohen
937 S.W.2d 823 (Tennessee Supreme Court, 1996)
Gordon v. Greenview Hospital, Inc.
300 S.W.3d 635 (Tennessee Supreme Court, 2009)
Spencer Kellogg & Sons, Inc. v. Lobban
315 S.W.2d 514 (Tennessee Supreme Court, 1958)
Rice v. First Arkansas Valley Bank (In Re May)
310 B.R. 405 (E.D. Arkansas, 2004)
FOUR EIGHTS, LLC. v. Salem
194 S.W.3d 484 (Court of Appeals of Tennessee, 2005)
Kradel v. Piper Industries, Inc.
60 S.W.3d 744 (Tennessee Supreme Court, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
Anchor Pipe Company, Inc. v. Sweeney-Bronze Development, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anchor-pipe-company-inc-v-sweeney-bronze-developme-tennctapp-2012.