Amsouth Erectors, Llc v. Skaggs Iron Works, Inc.

CourtCourt of Appeals of Tennessee
DecidedApril 22, 2003
DocketCH-01-0585-2
StatusPublished

This text of Amsouth Erectors, Llc v. Skaggs Iron Works, Inc. (Amsouth Erectors, Llc v. Skaggs Iron Works, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Amsouth Erectors, Llc v. Skaggs Iron Works, Inc., (Tenn. Ct. App. 2003).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON Assigned On Brief April 22, 2003

AMSOUTH ERECTORS, LLC v. SKAGGS IRON WORKS, INC., ET AL.

Direct Appeal from the Chancery Court for Shelby County No. CH-01-0585-2 Floyd Peete, Jr., Chancellor

No. W2002-01944-COA-R3-CV - Filed August 5, 2003

This appeal concerns a subcontractor’s (AmSouth) claims for non-payment arising from the construction of the Peabody Place Retail and Entertainment Center in Memphis. The Appellees are the owner (Peabody), and the management firm they hired to oversee the project (Tri-Tech). The Appellant is a subcontractor in privity of contract with neither Appellee. The trial court granted summary judgment to Peabody on AmSouth’s claims of Breach of Contract (under a Third-Party Beneficiary theory), Negligence, Negligent Misrepresentation, Unjust Enrichment/Quantum Meruit, and a claim to enforce a mechanics’ and materialmen’ s lien. Summary judgment was likewise granted to Tri-Tech on AmSouth’s claims against it for Breach of Contract (under a Third-Party Beneficiary theory), Negligent Misrepresentation, and Negligence.1 We affirm in part, reverse in part, and remand.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed in part; Reversed in part; and Remanded

DAVID R. FARMER , J., delivered the opinion of the court, in which W. FRANK CRAWFORD , P.J., W.S., and HOLLY M. KIRBY, J., joined.

Richard D. Bennett, Collierville, Tennessee and Samuel C. Kelly and Cheri T. Atlin, Ridgeland, Mississippi, for the appellant, Amsouth Erectors, LLC.

Michael I. Less, Joseph T. Getz and John D. Willet, for the appellee, Peabody Place Centre, L.P.

John McQuiston, II, Memphis, Tennessee for the appellee, Tri-Tech Planning and Engineering, Inc.

OPINION

1 W hile the negligence claim is not mentioned in the Order granting Tri-Tech summary judgment, the Order granting Peabod y summary judgment stated that “all of AmSouth’s claims against Peabody Place and against Tri-Tech, which are based on negligence and negligent misreprese ntation a re dism issed with prejudice .” The parties to this dispute were all involved in the construction of the Peabody Place Retail and Entertainment Center (“the Project”) in downtown Memphis. Peabody Place Centre, L.P. (“Peabody”), the owner of the project, entered into a contract with Tri-Tech Planning Consultants, Inc. (“Tri-Tech”) whereby Tri-Tech agreed to serve as the program manager on the Project. Peabody also entered into a contract with Skaggs Iron Works, Inc. (“Skaggs”) whereby Skaggs agreed to serve as the prime contractor on the Project in the areas of structural steel fabrication and erection. Skaggs subsequently entered into a contract with AmSouth Erectors, LLC, (“AmSouth”) whereby AmSouth agreed to provide the erection services for the project. Neither Peabody nor Tri-Tech entered into a contractual agreement with AmSouth.2 Despite this fact, AmSouth claims that it is a third-party beneficiary of both the Peabody/Tri-Tech contract as well as the Peabody/Skaggs contract. As such, AmSouth sued both Peabody and Tri-Tech for breach of contract asserting, inter alia, that Peabody’s failure to pay Skaggs, per the Peabody/Skaggs contract, had resulted in Skaggs not paying AmSouth.

Additionally, AmSouth exercised its rights to assert a mechanics’ and materialmen’s lien3 against Peabody’s property to secure payment for its performance. Peabody subsequently recorded a bond to indemnify against the lien, the effect of which was to discharge the lien.4 AmSouth sought to enforce this lien as part of their claim. Peabody argued that, as the lien had been discharged, there was no lien to enforce and, therefore, the claim should be dismissed.

AmSouth also claimed that both Peabody and Tri-Tech were guilty of negligence in the performance of their duties which caused damage to AmSouth. The Appellee’s asserted that, as the damages claimed by AmSouth were economic damages only, the “economic loss doctrine” barred recovery. AmSouth asserted that they fell within an exception to the doctrine, in that they were claiming damages for negligent misrepresentation, not merely simple negligence. Appellees, while acknowledging this exception, insisted that AmSouth had failed to properly plead this cause of action.

Finally, AmSouth asserted that, although they lacked privity of contract with Peabody, they were nonetheless entitled to recover for services performed which benefitted Peabody under the quasi-contractual theory of unjust enrichment. Peabody asserted that AmSouth could not seek recovery from them under this theory until AmSouth had exhausted its remedies against the party with whom they had contracted, Skaggs.

2 AmSouth argues that since the Peabody/Skaggs contract was “incorporated herein and made a part of” the contract betwe en Skaggs and A mSo uth, that this bolsters the ir third-party beneficiary claim. We disagree. To the contrary, the effect o f this provision was to bind AmSouth to the provision that “[n]othing contained in the Contract Do cuments or otherwise shall create any contractual relationship between the Owner [Peabody] and any subcontractor or sub -subco ntracto r.”

3 See Tenn. Co de A nn. § 6 6-11 -101 , et seq.

4 Tenn. Cod e Ann. § 66-11-142 (a) (Supp. 2002).

-2- The trial judge granted summary judgment to the Appellees (Defendants below) on all the aforementioned claims. For the following reasons, we affirm in part, reverse in part, and remand for further proceedings not inconsistent with this opinion.

Standard of Review

As indicated, this is an appeal from a grant of summary judgment. The standard for review of a motion for summary judgment is set forth in Staples v. CBL & Assocs., 15 S.W.3d 83 (Tenn. 2000):

The standards governing an appellate court's review of a motion for summary judgment are well settled. Since our inquiry involves purely a question of law, no presumption of correctness attaches to the lower court's judgment, and our task is confined to reviewing the record to determine whether the requirements of Tenn. R. Civ. P. 56 have been met. See Hunter v. Brown, 955 S.W.2d 49, 50-51 (Tenn. 1997); Cowden v. Sovran Bank/Central South, 816 S.W.2d 741, 744 (Tenn. 1991). Tennessee Rule of Civil Procedure 56.04 provides that summary judgment is appropriate where: (1) there is no genuine issue with regard to the material facts relevant to the claim or defense contained in the motion, see Byrd v. Hall, 847 S.W.2d 208, 210 (Tenn. 1993); and (2) the moving party is entitled to a judgment as a matter of law on the undisputed facts. See Anderson v. Standard Register Co., 857 S.W.2d 555, 559 (Tenn. 1993). The moving party has the burden of proving that its motion satisfies these requirements. See Downen v. Allstate Ins. Co., 811 S.W.2d 523, 524 (Tenn. 1991). When the party seeking summary judgment makes a properly supported motion, the burden shifts to the nonmoving party to set forth specific facts establishing the existence of disputed, material facts which must be resolved by the trier of fact. See Byrd[], 847 S.W.2d at 215.

To properly support its motion, the moving party must either affirmatively negate an essential element of the nonmoving party's claim or exclusively establish an affirmative defense. See McCarley v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robins Dry Dock & Repair Co. v. Flint
275 U.S. 303 (Supreme Court, 1927)
Owner-Operator Independent Drivers Ass'n v. Concord EFS, Inc.
59 S.W.3d 63 (Tennessee Supreme Court, 2001)
Staples v. CBL & Associates, Inc.
15 S.W.3d 83 (Tennessee Supreme Court, 2000)
McCarley v. West Quality Food Service
960 S.W.2d 585 (Tennessee Supreme Court, 1998)
Robinson v. Omer
952 S.W.2d 423 (Tennessee Supreme Court, 1997)
Trau-Med of America, Inc. v. Allstate Insurance Co.
71 S.W.3d 691 (Tennessee Supreme Court, 2002)
John Martin Co. v. Morse/Diesel, Inc.
819 S.W.2d 428 (Tennessee Supreme Court, 1991)
Cowden v. Sovran Bank/Central South
816 S.W.2d 741 (Tennessee Supreme Court, 1991)
Downen v. Allstate Insurance Co.
811 S.W.2d 523 (Tennessee Supreme Court, 1991)
Anderson v. Standard Register Co.
857 S.W.2d 555 (Tennessee Supreme Court, 1993)
Donaldson v. Donaldson
557 S.W.2d 60 (Tennessee Supreme Court, 1977)
Carvell v. Bottoms
900 S.W.2d 23 (Tennessee Supreme Court, 1995)
Paschall's, Inc. v. Dozier
407 S.W.2d 150 (Tennessee Supreme Court, 1966)
Rawlings v. John Hancock Mutual Life Ins. Co.
78 S.W.3d 291 (Court of Appeals of Tennessee, 2001)
Hamblen County v. City of Morristown
656 S.W.2d 331 (Tennessee Supreme Court, 1983)
Byrd v. Hall
847 S.W.2d 208 (Tennessee Supreme Court, 1993)
McCall v. Wilder
913 S.W.2d 150 (Tennessee Supreme Court, 1995)
Hunter v. Brown
955 S.W.2d 49 (Tennessee Supreme Court, 1997)
Norton v. Everhart
895 S.W.2d 317 (Tennessee Supreme Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
Amsouth Erectors, Llc v. Skaggs Iron Works, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/amsouth-erectors-llc-v-skaggs-iron-works-inc-tennctapp-2003.