AMP ELECTRICAL, INC. v. W.M. SCHULTZ CONSTRUCTION, INC. & Another; TOWN OF WEST SPRINGFIELD, Third-Party

CourtMassachusetts Appeals Court
DecidedJuly 31, 2025
Docket24-P-0941
StatusUnpublished

This text of AMP ELECTRICAL, INC. v. W.M. SCHULTZ CONSTRUCTION, INC. & Another; TOWN OF WEST SPRINGFIELD, Third-Party (AMP ELECTRICAL, INC. v. W.M. SCHULTZ CONSTRUCTION, INC. & Another; TOWN OF WEST SPRINGFIELD, Third-Party) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
AMP ELECTRICAL, INC. v. W.M. SCHULTZ CONSTRUCTION, INC. & Another; TOWN OF WEST SPRINGFIELD, Third-Party, (Mass. Ct. App. 2025).

Opinion

NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).

COMMONWEALTH OF MASSACHUSETTS

APPEALS COURT

24-P-941

AMP ELECTRICAL, INC.

vs.

W.M. SCHULTZ CONSTRUCTION, INC. & another;1 TOWN OF WEST SPRINGFIELD, third-party defendant.

MEMORANDUM AND ORDER PURSUANT TO RULE 23.0

The plaintiff, AMP Electrical, Inc. (AMP), appeals from a

summary judgment dismissing its complaint against the

defendants, W.M. Schultz Construction, Inc. (Schultz), and

Endurance Assurance Corporation (Endurance). We affirm.2

Background. We summarize the undisputed material facts on

the summary judgment record, reserving certain facts for later

1 Endurance Assurance Corporation.

2We note that Schultz brought a third-party complaint against the town of West Springfield, which was also dismissed on summary judgment. AMP's appeal does not raise any separate issues regarding the dismissal of Schultz's third-party complaint. discussion. The town of West Springfield (town) is the owner of

a public construction project identified as Wastewater Pumping

Station Improvements (project). The town's project engineer

drafted plans and specifications for public bid by general

contractors and subbid contractors pursuant to G. L. c. 149,

§ 44F, for the project.

Schultz was awarded the general construction contract for

the project.3 Thereafter, the town's project engineer held

electrical subcontractor bid meetings, which AMP attended prior

to filing its subcontractor bid. At the meetings, the town

distributed the project's specifications and drawings to the

prospective electrical subcontractors. The town informed

prospective subcontractors of project updates by releasing

addenda to them during the prebidding process, some of which

were in response to questions raised by the prospective

subcontractors.4

As relevant here, the town issued Addendum No. 2 on March

19, 2018, which included the following question and response:

Question 15: "Who is responsible for excavation and backfill of underground electrical conduits?"

3 Subsequently, the town and Schultz entered into a written contract naming Schultz as the principal and Endurance as the surety. Endurance issued Schultz a payment bond for the project.

4 AMP does not dispute that it received Addendum Nos. 2 and 3 prior to filing its subcontract bid.

2 Response: "The electrical sub-bidder is responsible for this work."

The town issued Addendum No. 3 on March 26, 2018, and it, among

other things, replaced Drawing Sheet E-401 with Sheet E-401.

The revised Sheet E-401 provided additional trench details

regarding the excavation and backfill of underground electrical

conduits for the project.

On March 29, 2018, AMP filed its electrical subcontractor

bid; it was the lowest subbidder. On July 18, 2018, Schultz and

AMP entered into a written contract (subcontract) whereby

Schultz agreed to pay AMP $1,800,000 for "all work specified in

Division 16 of the specifications for Electrical," "the plans

referred to therein," and Addendum Nos. 2 and 3.5

On June 26, 2019, AMP submitted a change order to Schultz

requesting an increase in price in the amount of $88,730.70.

Among other things, AMP sought the increase for "[e]xcavation

and concrete easement" and "[b]ackfilling and compacting trench

and affected areas [a]sphalt patching." In short, AMP believed

the subcontract did not include excavation and backfilling work

and thus, requested that it be compensated for that additional

work. The town's project engineer rejected AMP's request,

stating that Addendum Nos. 2 and 3 clarified that the work AMP

5 Division 16 described the basic electrical requirements for the project.

3 now claims as extra was part of the electrical subbidder's

responsibility. Ultimately, on August 25, 2019, AMP informed

Schultz that it would proceed with the excavation and

backfilling work under protest and it provided an updated change

order (PCO #6) for the amount of $83,490.15. Schultz rejected

AMP's request for a change order and acknowledged that AMP would

proceed with the work under protest.

In May 2021, after Schultz failed to pay AMP for the work

it completed pursuant to PCO #6, AMP filed a complaint alleging

two counts against Schultz: breach of contract and unfair and

deceptive practices in violation of G. L. c. 93A, §§ 2 & 11.6

The complaint also sought recovery on a payment bond pursuant to

G. L. c. 149, § 29, from Endurance. The defendants moved for

summary judgment on all counts. AMP cross-moved for summary

judgment on the breach of contract and payment bond claims. The

judge allowed the defendants' motion for summary judgment and

denied AMP's cross motion for summary judgment. AMP timely

appealed from the summary judgment.

6 AMP's complaint alleged breach of contract for both (1) Schultz's failure to pay for the work it completed pursuant to PCO #6 and (2) unpaid retainage. However, between the filing of the complaint and the judge's summary judgment decision, AMP received payment for the retainage. Thus, this decision only addresses the remaining breach of contract claim concerning the work completed pursuant to PCO #6.

4 Discussion. On appeal, AMP asserts that the judge erred in

granting the defendants' motion for summary judgment. We review

the grant of summary judgment de novo. See Le Fort Enters.,

Inc. v. Lantern 18, LLC, 491 Mass. 144, 149 (2023). Where, as

here, the parties filed cross motions for summary judgment, we

view the evidence in the light most favorable to the party whose

motion was denied. See Smiley First, LLC v. Department of

Transp., 492 Mass. 103, 108 (2023). Summary judgment is

appropriate where "there is no genuine issue as to any material

fact" and "the moving party is entitled to a judgment as a

matter of law." Kourouvacilis v. General Motors Corp., 410

Mass. 706, 713 n.2 (1991). We discern no error in the judge's

grant of summary judgment in the defendants' favor.

On appeal, AMP asserts that it was only required to

complete the work designated in Division 16 of the subcontract.

AMP relies on language in G. L. c. 149, § 44F, and insists that

because the excavation and backfilling work described in

Addendum Nos. 2 and 3 was "neither a 'specification' nor a

contract term" and "was not directed to the electrical subbidder

in particular," AMP was not required to complete that work.

The judge determined that "Addendum No. 2 clarified that

the electrical subcontractor is responsible for all backfilling

and excavating." Further, the judge concluded that "[t]he

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John F. Miller Co. v. George Fichera Construction Corp.
388 N.E.2d 1201 (Massachusetts Appeals Court, 1979)
Kourouvacilis v. General Motors Corp.
575 N.E.2d 734 (Massachusetts Supreme Judicial Court, 1991)
Fabre v. Walton
802 N.E.2d 1030 (Massachusetts Supreme Judicial Court, 2004)
Chace v. Curran
881 N.E.2d 792 (Massachusetts Appeals Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
AMP ELECTRICAL, INC. v. W.M. SCHULTZ CONSTRUCTION, INC. & Another; TOWN OF WEST SPRINGFIELD, Third-Party, Counsel Stack Legal Research, https://law.counselstack.com/opinion/amp-electrical-inc-v-wm-schultz-construction-inc-another-town-of-massappct-2025.