Amos v. NVR INC.

CourtDistrict Court, S.D. Ohio
DecidedMarch 31, 2022
Docket1:19-cv-00719
StatusUnknown

This text of Amos v. NVR INC. (Amos v. NVR INC.) is published on Counsel Stack Legal Research, covering District Court, S.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Amos v. NVR INC., (S.D. Ohio 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE SOUTHERN DISTRICT OF OHIO WESTERN DIVISION - CINCINNATI MICHAEL AMOS, et al., : Case No. 1:19-cv-719 Plaintiffs, 2 Judge Matthew W. McFarland v. : NVR, INC., d/b/a RYAN HOMES, et al., Defendants.

OPINION AND ORDER

This case is before the Court on three motions for summary judgment. (Docs. 35, 36, 38.) Plaintiffs Michael and Natasha Amos bring suit against Defendants NVR, Inc., otherwise known as Ryan Homes, and NVR Mortgage Finance, Inc., following the construction of a home. Each party has filed a motion for summary judgment and each motion is ripe for review. FACTS A. Plaintiffs’ Version of the Facts The following is Plaintiffs’ version of the facts from their briefing. They base most of their facts on a declaration signed by Plaintiff Natasha Amos. (Amos Decl., Doc. 37.) Facts as to Defendant Ryan Homes. In July 2017, Plaintiffs entered into a contract with Ryan Homes for the construction of anew home. The home was originally planned to be complete in December 2017. Plaintiffs claim that problems beset the construction early on. By August, they had attempted to terminate the contract. But Ryan Homes

refused to permit termination, making other offers instead. Ryan Homes promised to repair or replace defects Plaintiffs pointed out. That December, Ryan Homes told Plaintiffs the home was almost ready. Plaintiffs paid the cash deposit and arranged to move from their existing home to the new one. According to Plaintiffs, however, the new home was not complete. Upon inspection, they discovered several items that needed to be completed or fixed. They created a “punch list” of items that Ryan Homes promised to complete within ten days. The project manager assured Plaintiffs that most of the work would be done by closing. Several outdoor items were also incomplete but would need to be completed the following spring. The outdoor work included planting grass seed, laying sod, repairing the driveway, and grading the lot. Ryan Homes told Plaintiffs this work would be in March or April 2018. The punch list work, however, was not completed within ten days. The ground floor remained out of level. When Ryan Homes workers came out in late January to fix the flooring, they removed portions of the basement ceiling and cut structural floor joists. Plaintiffs hired an independent inspector, Michael Clark, to look at it. Clark noted that the repair to the floor did not comply with the building code and that it compromised the floor’s structural integrity. Ryan Homes, in Plaintiffs’ view, did not acknowledge the problem and maintained that the floor repair was successful. The building company sent a flooring expert, who concluded that the floor was up to industry standards. But, based on Clark's report, Plaintiffs sought the opinion of a structural engineer, Richard Graman. Graman found that the floor repair had done damage to the home and violated the

building code. He provided specifications for repairs and recommended the work be done immediately. In April 2018, Plaintiffs contacted Ryan Homes about laying sod and planting grass seed. In Plaintiffs’ telling, Ryan Homes would not perform any of the outdoor work until the parties reached a resolution of all the outstanding issues. Settlement proved elusive. From Plaintiffs’ perspective, Ryan Homes complicated matters with its demands. For instance, it demanded that Plaintiffs refrain from recording its employees while at Plaintiffs’ home — Plaintiffs had a security system at their home, which they were reluctant to disable because some of their property had been damaged or gone missing while Ryan Homes’ contractors were on their property. Additionally, as a part of Ryan Homes’ proposal to repair the floor, it told Plaintiffs they would have to leave their house for a period of time. The company offered to reimburse them for temporary lodging and other expenses. It also insisted that Plaintiffs sign a confidentiality agreement. In the end, the parties did not agree on the terms of the floor repair. Plaintiffs, aware that the one-year anniversary of the closing was approaching, asked Ryan Homes to address a list of items. Ryan Homes, however, told Plaintiffs that no warranty work would be done until the parties reached a comprehensive settlement of all the issues. Thus, the punch list items remained unaddressed, the yard had no grass, and the landscape had not been graded. In addition, Ryan Homes’ temporary certificate of occupancy, good for one year, had expired. Facts as to Defendant NVR Mortgage. NVR Mortgage served as the mortgage lender for Plaintiffs’ purchase of the home from Ryan Homes. According to Plaintiffs, Ryan

Homes told Plaintiffs that certain parts of the work on the home would not be complete by closing. When they heard this, they passed on the information to NVR Mortgage and requested that funds be held in escrow proportionate to the value of the incomplete work. Their plan was that funds would be paid over to Ryan Homes when the work was completed. NVR Mortgage agreed to escrow funds covering a portion of the work. It executed an escrow holdback agreement with Plaintiffs. (Doc. 36-1.) This agreement, however, only pertained to certain outdoor work, such as grading, sod, and grass seed. Plaintiffs had sought an escrow for interior work as well. Thus, according to Plaintiffs, NVR Mortgage, a subsidiary of Ryan Homes, did not create an escrow for all of the outstanding incomplete items. B. Defendants’ Version of the Facts Defendant Ryan Homes. Ryan Homes agrees that, in July 2017, it contracted with Plaintiffs to construct anew home. In the Purchase Agreement the parties executed, they agreed to a provision that limits the amount of time a party may bring suit: Claims and Disputes. You and We agree that any and all claims arising out of or relating to this Agreement, Settlement hereunder, or improvements to the Property, regardless of legal theory, except any claims under the Limited Warranty (“Claims”), shall be subject to a one (1) year limitation of action period and bar date. Such claims based on matters occurring before the Settlement Date shall be deemed to have arisen and accrued, if at all, and the one-year limitation of action period for all such claims shall begin to run on the Actual Settlement Date. All application of the so-called “discovery rule” is mutually waived by the parties. By executing this Agreement, You acknowledge Your understanding and agreement to these terms and that the said one (1) year period is completely reasonable in all respects. Notwithstanding the foregoing, these bar date terms shall not apply to claims for indemnity and/or contribution by Us against You and/or any other person. These

rights may only be enforced by You and Us and nothing herein shall be construed to create any third party beneficiary rights in any other person or entity. (Ex. A to Compl., Doc. 10-1, Pg. ID 294 (emphasis added).) Ryan Homes states that the term “Actual Settlement Date” is defined in the Purchase Agreement as being the date of settlement, meaning the date of closing. The closing date was December 15, 2017. (Michael Amos Dep., Doc. 34-1, Pg. ID 499.) Ryan Homes does not deny that Plaintiffs’ allegations began in the summer of 2017. By April 2018, Plaintiffs had engaged counsel to negotiate on their behalf with Ryan Homes. In May 2018, the parties participated in a joint inspection of the home. They discussed possible ways to resolve the dispute. These discussions broke down. However, Ryan Homes refers to a letter dated July 3, 2018, in which it proposed addressing the warranty issues, among other issues. (Exhibit, Amos Decl., Doc. 37-8, Pg. ID 1182.) About a year later, Plaintiffs filed this lawsuit in the Common Pleas Court of Clermont County, Ohio. Defendant NVR Mortgage.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jack Henry & Associates, Inc. v. BSC, INC.
753 F. Supp. 2d 665 (E.D. Kentucky, 2010)
Heimeshoff v. Hartford Life & Accident Ins. Co.
134 S. Ct. 604 (Supreme Court, 2013)
Daniels v. Woodside
396 F.3d 730 (Sixth Circuit, 2005)
Ball v. Ohio State Home Services, Inc.
861 N.E.2d 553 (Ohio Court of Appeals, 2006)
Frey v. Vin Devers, Inc.
608 N.E.2d 796 (Ohio Court of Appeals, 1992)
Neel v. A. Perrino Constr., Inc.
2018 Ohio 1826 (Ohio Court of Appeals, 2018)
Colvin v. Globe American Casualty Co.
432 N.E.2d 167 (Ohio Supreme Court, 1982)
Miller v. Progressive Casualty Insurance
635 N.E.2d 317 (Ohio Supreme Court, 1994)
Taylor Building Corp. of America v. Benfield
884 N.E.2d 12 (Ohio Supreme Court, 2008)
Lansing Dairy, Inc. v. Espy
39 F.3d 1339 (Sixth Circuit, 1994)
Betkerur v. Aultman Hospital Ass'n
78 F.3d 1079 (Sixth Circuit, 1996)
Traxler v. PPG Industries, Inc.
158 F. Supp. 3d 607 (N.D. Ohio, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Amos v. NVR INC., Counsel Stack Legal Research, https://law.counselstack.com/opinion/amos-v-nvr-inc-ohsd-2022.