Ammcon, Inc. v. Kemp

826 F. Supp. 639, 1993 U.S. Dist. LEXIS 9292, 1993 WL 262619
CourtDistrict Court, E.D. New York
DecidedJuly 7, 1993
DocketCV-91-5062
StatusPublished
Cited by7 cases

This text of 826 F. Supp. 639 (Ammcon, Inc. v. Kemp) is published on Counsel Stack Legal Research, covering District Court, E.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ammcon, Inc. v. Kemp, 826 F. Supp. 639, 1993 U.S. Dist. LEXIS 9292, 1993 WL 262619 (E.D.N.Y. 1993).

Opinion

MEMORANDUM AND ORDER

GLASSER, District Judge.

Plaintiff Ammcon, Inc. (“Ammcon”) was the general contractor on a housing project located at 224-246 Kingston Avenue, Brooklyn, New York, the David Chavis Apartments, to provide housing for elderly persons. The First Baptist Church of Crown Heights Senior Citizens Housing Development Fund Corporation (“First Baptist”), an assetless, not-for-profit corporation, sponsored that housing project and owned the property upon which it was to be built. Defendant Jack Kemp was formerly the Secretary of Housing and Urban Development (“HUD”), 1 the federal agency which had advanced funds to First Baptist under § 202 of the Housing Act of 1959, 12 U.S.C. § 1701q, to aid in the construction of those apartments. HUD extended a mortgage in the amount of $8,786,000 to First Baptist pursuant to a Building Loan Agreement between First Baptist and HUD, dated December 21, 1981 and a Mortgage, Mortgage Note and Regulatory Agreement, dated December 23, 1981. Exs. J, K, and L to Aff. of Anthony Mazzucca, dated February 14, 1992 (“Mazzucca Aff.”).

HUD was integrally involved in the housing project. It required First Baptist and Ammcon to enter written agreements on HUD-approved forms. For example, on December 23, 1981, Ammcon and First Baptist entered into a Construction Contract, FHA Form No. 2442A (“Construction Contract”). That agreement required HUD’s prior writ *641 ten approval before any changes in drawings or design specifications (that would increase construction costs) could be implemented. Construction Contract Art. 1(E). Similarly, Ammcon was entitled to obtain payment for each month of work provided it submitted FHA Form No. 2448, a HUD-approved request for payment form. Id. Art. 3(B). In addition, HUD was to become First Baptist’s attorney-in-fact in the event that the latter did not discharge its contractual obligations to HUD under the Building Agreement. Id. Art. 9(D).

The project was completed by March 30, 1983 in accordance with Art. 2(A) of the Construction Contract. Complaint ¶ 5. Thereafter, Ammcon submitted a request for payment in the amount of $404,720. HUD reviewed that request and determined that Ammcon was only entitled to receive $182,-076 at final closing on the property. On January 29, 1986, Ammcon served a demand for arbitration against First Baptist in accordance with the mandatory arbitration provision of the Construction Contract. See Construction Contract Art. 1(A) (incorporating Rule 7.9.1 of AIA Document A201). In its demand for arbitration, Ammcon characterized the dispute as “[First Baptist’s] failure to pay [Ammcon] for work performed under a written construction contract, for extra and additional work ordered by [First Baptist], and for damages sustained by [Ammcon] due to a suspension of work by [First Baptist].” Consequently, Ammcon sought “a monetary award in the approximate sum of $750,-000.00.” Ex. B to Mazzueca Aff. However, HUD was not served with the demand for arbitration.

First Baptist participated in the arbitration proceedings which were held on May 7 and 29, July 1 and 2, November 5, 6 and 18, and December 2, 1986. At that hearing, First Baptist offered documentary evidence, presented the testimony of witnesses, and cross-examined Ammcon’s witnesses; thereafter, it submitted post-hearing memoranda. Mazzueca Aff. ¶¶ 10, 11. On or before May 5, 1987, the arbitrators ruled in favor of Ammcon and awarded it $479,932.00 against First Baptist to be reduced by any additional payments made after February 2,1987. The arbitral award included $309,239.00 representing “Change orders issued by [First Baptist], some of which were approved by [HUD] and others [i.e., change orders] which were unapproved.” Ex. D to Mazzueca Aff.

Final closing on the property was held at HUD’s office on June 4, 1987. At closing, First Baptist gave Ammcon a $221,425.22 cheek and a $28,940.78 note (“Note”) to be paid from future rents. Ex. F to Mazzueca Aff. Ammcon’s principal, Anthony Mazzucca, signed a letter confirming “that at closing today the unpaid items shown as due to [Ammcon] on [First Baptist’s] Certificate of Actual Cost are being paid.” Ex. F to Mazzucca Aff. Attached to that exhibit is a two-page handwritten note between Ammcon and First Baptist, reserving Ammcon’s right to enforce the arbitration award and merely crediting the amounts paid at closing to the balance due under the arbitration award. See id. This document was not found in HUD files and HUD personnel have no knowledge of its veracity. See Aff. of Edwin Sprenger, dated April 9, 1992, ¶¶ 15-16 (“Sprenger Aff.”)'. Subsequently, Ammcon commenced an Article 75 proceeding in state court to confirm the arbitral award. Only First Baptist was served in that action; HUD was not notified of the confirmation proceeding. In March 1988, the state court entered a judgment in the amount of $384,-192.65 because First Baptist did not oppose the confirmation of the arbitral award. When HUD declined to pay that amount to Ammcon, Ammcon commenced this action on December 23, 1991, to enforce the judicial confirmation of the arbitral award against HUD as the alter ego of First Baptist, as well as to recover the amount of the Note.

Ammcon moves for summary judgment on the ground that the Article 75 proceeding confirms the amount of damages for which HUD is liable as a matter of law because HUD is precluded from relitigating the validity of that award. HUD cross-moves for summary judgment on the grounds that: (1) the action is time-barred; (2) that certain construction cost increases were improvi *642 dently granted by the arbitrators; and (3) sovereign immunity. For the following reasons, Ammcon’s motion is denied and HUD’s cross-motion is denied.

DISCUSSION

This action is the “identical twin” of an earlier action before this Court, C.H. Sanders v. BHAP Housing Dev. Fund Co., 750 F.Supp. 67. In that case, as in this case, a contractor sued HUD to recover monies due for work performed on an elderly housing project based on an arbitration award which ordered the non-profit corporate sponsor of the housing project to pay a sum certain to the contractor. The Court of Appeals determined that this Court had subject matter jurisdiction over that controversy because the gist of the contractor’s claim was predicated on unjust enrichment and on HUD’s failure to discharge its duties under 12 U.S.C. § 1701q. C.H. Sanders v. BHAP Housing Dev. Fund Co., 903 F.2d 114, 118 (2d Cir.1990). In addition, the court noted that the plaintiffs recovery, if any, would be limited to funds within HUD’s control; that is, the plaintiff in Sanders could not otherwise recover funds from the United States Treasury. Id. at 120. The court also affirmed that part of this Court’s decision, holding that HUD was precluded from relitigating the arbitration award either on the ground that the asset-less, non-profit corporate sponsor was HUD’s alter ego or because HUD declined to participate in the arbitration proceeding despite being invited to do so. Id. at 121.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Donald Dean & Sons, Inc. v. Xonitek Systems Corp.
656 F. Supp. 2d 314 (N.D. New York, 2009)
United American, Inc. v. N.B.C.-U.S.A. Housing, Inc. Twenty Seven
400 F. Supp. 2d 59 (District of Columbia, 2005)
Crystalline H2O, Inc. v. Orminski
105 F. Supp. 2d 3 (N.D. New York, 2000)
Auction Company Amer v. FDIC
132 F.3d 746 (D.C. Circuit, 1998)
Messina v. Mazzeo
854 F. Supp. 116 (E.D. New York, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
826 F. Supp. 639, 1993 U.S. Dist. LEXIS 9292, 1993 WL 262619, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ammcon-inc-v-kemp-nyed-1993.