Amfac Foods, Inc. v. Fred A. Snyder Roofing & Sheet Metal Corp.
This text of 602 P.2d 321 (Amfac Foods, Inc. v. Fred A. Snyder Roofing & Sheet Metal Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinions
In this contract action arising out of a dispute over he condition of a roof on a newly constructed building, he trial court granted defendant summary judgment ased upon the statute of limitations contained in ORS 2.135(1). We reverse.
Plaintiff Amfac Foods, Inc., dba Lamb-Weston lereinafter "Lamb-Weston”) brought this breach of warranty action against defendant Snyder Roofing Company (hereinafter "Snyder”) for the cost of repair-ng a roof. The roof had been built by Snyder as a ubcontractor in the construction of a food processing lant. After completion, Snyder executed, on July 30, 973, a two-year guarantee of workmanship and mate-ials. Specifically, the guarantee provided:
"WHEREAS, at the inception of such work the Contractor [Snyder Roofing] agreed to guarantee the aforesaid roof against faulty materials or workmanship for a limited period and subject to the conditions herein set forth;
"NOW, THEREFORE, the Contractor hereby Guarantees, subject to the conditions herein set forth, that dining a period of two (2) years from the date of completion of said roof, it will, at its own cost and expense, make or cause to be made such repairs to said roof resulting solely from faults or defects in material or workmanship applied by or through the Contractor as may be necessary to maintain said roof in watertight condition.”
In its complaint, Lamb-Weston alleged that the efects of which it now complains were discovered and otice of them was given to Snyder within the two ears provided in the guarantee. The trial court grant-d summary judgment to defendant on the theory that laintiff’s action here was one in tort and was there-ore not timely filed under ORS 12.135(1).1 Plaintiff [110]*110acknowledges that this proceeding was not brought within the two-year period provided in ORS 12.135(1) but contends that the correct statute to be applied is ORS 12.080(1),2 the statute of limitations for contract actions. ORS 12.080(1) is a six-year statute of limitations; plaintiff’s action is timely if it applies.
Plaintiff is correct. Where, as here, the gravamen of the complaint is not the failure of defendant to properly install a roof in the first instance but, rather, the failure of defendant to abide by its express contractual duty to alleviate such unsatisfactory conditions as might appear during the two-year guarantee period, the complaint sounds in contract and ORS 12.080(1) governs. See Housing Authority of Portland v. Ash National, Inc., 36 Or App 391, 584 P2d 776 (1978).3
Defendant argues that, even if ORS 12.080(1) is the appropriate statute of limitations, the trial court was nonetheless correct in granting summary judgment to defendant because defendant is entitled to prevail under one or more of defendant’s alternative theories, viz., (1) that defendant has performed all of its obligations under the guarantee; (2) that the claim advanced by plaintiff has been satisfied; and (3) that, under its own terms, the guarantee has become null and void.
[111]*1111. PERFORMANCE
Defendant first argues that its only obligation inder the guarantee was to maintain the roof in watertight condition, and it has done so. To the con-rary, as we read the record, defendant has stopped eaks as they appear but the roof has continued to evelop new ones. There remains a factual issue as to whether the roof has been maintained in a watertight ondition. Defendant was not entitled to summary udgment on this theory.
2. ACCORD AND SATISFACTION
Defendant next argues that any claim between jamb-Weston and defendant has been compromised nd settled, with defendant having fully performed nder the terms of the settlement.
The guarantee in question covered the period from uly 30, 1973, to July 30, 1975. On June 9, 1975, epresentatives from Hoffman Construction Company the general contractor), Lamb-Weston, Snyder Roof-ng and Johns-Manville (the roofing manufacturer) let and reviewed the problem. There was a further leeting on June 26, 1975.
Thereafter, Hoffman Construction Company pre-ared a "memorandum of agreement” expressing its nderstanding of the verbal agreements of the respecive parties. A copy of the Hoffman memorandum was lade a part of the motion for summary judgment.
The question is whether the documents submitted y the parties in connection with the motion for sum-lary judgment establish the existence of an accord nd satisfaction. They do not.
" '* * * An accord is a contract * * * between creditor and debtor for the settlement of the claim by some performance other than that which is due * * *. Satisfaction takes place when [the] accord is performed * * Restatement, Contracts § 417, Comment a. at 787-788.” Capps v. Georgia-Pacific, 253 Or 248, 453 P2d 935 (1969).
[112]*112The documents establish that, among other things, a dispute exists between the parties as to whether such repair work as defendant did on the roof was satisfactory. What was done and how well it was done remains an unresolved issue of fact. It would have been error to grant summary judgment on this theory.
3. GUARANTEE NULLIFIED
Finally, defendant argues that its guarantee has been rendered null and void by the occurrence of a condition subsequent. The warranty was given subject to the condition, inter alia, that:
« * * * * *
" * * * No work shall be done on said roof, including, but without limitation, openings made for flues, vents, drains, sign braces or other equipment fastened to or set on the roof, unless the Contractor shall be first notified; shall be given the opportunity to make the necessary roofing application recommendations with respect thereto, and such recommendations are complied with. Failure to observe this condition shall render this guarantee null and void * * (Emphasis supplied.)
The affidavits filed in this case make it clear that Lamb-Weston did install some equipment on some portions of the roof without prior approval by defendant. However, in a portion of an affidavit filed by Lamb-Weston, one of Lamb-Weston’s engineers stated that:
"Regarding the subsequent conditions referred to in this motion [for summary judgment], Lamb-Weston replaced fans and installed small equipment over the manufacturing area on the [roof of the] plant. Snyder was informed of this. Where openings were required, Snyder Roofing Co. did the work and was paid extra. Furthermore, the leaking problem was not in the manufacturing area. Snyder Roofing Co.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
602 P.2d 321, 43 Or. App. 107, 1979 Ore. App. LEXIS 3364, Counsel Stack Legal Research, https://law.counselstack.com/opinion/amfac-foods-inc-v-fred-a-snyder-roofing-sheet-metal-corp-orctapp-1979.