Amethyst Construction, Inc. v. J.S. Rugg Construction, Inc.

26 So. 3d 881, 2009 La. App. LEXIS 2029, 2009 WL 4641879
CourtLouisiana Court of Appeal
DecidedDecember 9, 2009
Docket44,850-CA
StatusPublished

This text of 26 So. 3d 881 (Amethyst Construction, Inc. v. J.S. Rugg Construction, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Amethyst Construction, Inc. v. J.S. Rugg Construction, Inc., 26 So. 3d 881, 2009 La. App. LEXIS 2029, 2009 WL 4641879 (La. Ct. App. 2009).

Opinion

WILLIAMS, J.

liThe plaintiff, Amethyst Construction, Inc., appeals a judgment in favor of the defendants, J.S. Rugg Construction, Inc. and Ohio Casualty Insurance Company. The trial court found that defendants were entitled to deduct from the final payment the increased cost of hiring another company to complete the job after plaintiff had left the job site. For the following reasons, we reverse and render.

FACTS

In March 2007, the general contractor for a church construction project, J.S. Rugg Construction, Inc. (“Rugg”), accepted the bid of Amethyst Construction, Inc. (“Amethyst”) for installation of an asphalt parking lot. Initially, Rugg presented a “Project Work Schedule” providing that Amethyst would install the soil cement base on July 23-25, 2007 and pei’form asphalt paving on August 9-10, 2007. However, construction was delayed over time and Rugg was not ready for Amethyst to begin work according to the original schedule.

At the end of October 2007, Rugg contacted Amethyst and said that the parking lot was ready for the soil cement. Prior to starting work, Amethyst’s asphalt superintendent, Ben Holdman, visited the job site and determined that the grading work, which had been done by another company, did not provide proper drainage and that additional work was needed. Holdman did not immediately inform Rugg about this problem. On November 12, 2007, Rugg sent a “schedule update” stating its understanding that Amethyst was to have begun work on November 1, 2007. Holdman then informed Rugg about the problem with the grade of |2the lot and the parties agreed that Amethyst would correct the grade.

On November 20, 2007, when the grading work began, Amethyst workers found chunks of cement and other debris under the soil that needed to be removed before applying the soil cement. Following removal of the debris, Amethyst completed the application of soil cement on Tuesday, December 11, 2007. Because soil cement must cure for at least 72 hours before applying asphalt, the first business day on which asphalt could have been poured was Monday, December 17, 2007. However, Amethyst had committed to start another *883 asphalt job on that date and did not go to the church site. Rugg’s principal, Steve Rugg, contacted Holdman, who said that Amethyst would not be able to do the work that week and would be closed the next two weeks for the holidays. Holdman stated that the church parking lot would be Amethyst’s first job after the new year began.

On Wednesday morning, January 2, 2008, Steve Rugg did not see an Amethyst crew at the job site and had not heard from Holdman. Steve Rugg then faxed a note to Amethyst stating:

Please consider this letter as your notice of cancellation of our agreement on the above project effective at 3:00 p.m., Friday, January 4, 2008. If you have not completed all work by this time, I will make arrangements with another asphalt company to come in and complete this project.
You were notified back in October that we were ready for you to start this project. You ignored me for two weeks and when you finally did get on site, you have been playing with the project and most recently have not shown up for the last three weeks. When I called you on the phone a week ago, you said there is no way that you would come back to work until after the 1st of the year, but when you did, I am the first on your list. Well, that day is today and there is no sign of you or anyone else that works for you. Hope you have had fun deer hunting for the last month.

|3After receiving the fax, William Hold-man checked the weather forecast and saw that the temperatures would be too cold to pour asphalt on January 2 and 3, 2008. Under DOTD specifications, the ambient temperature must be at least 50 degrees Fahrenheit (F) for pouring an asphalt surface. Since the church parking lot was a two-day job, Ben Holdman told Rugg that Anethyst would not be able to meet the deadline. Amethyst later removed its equipment from the job site.

Anethyst sent Rugg an invoice in the amount of $69,249.75 for the work which had been performed. Rugg paid Amethyst $56,945.25 after deducting $10,804.50, the additional amount paid to another contractor to complete the job, and the amount of $1,500 for the repair of a column and sidewalk allegedly damaged by Amethyst employees. Amethyst then filed a lien in the amount of $12,304.50, for which Rugg obtained a bond through Ohio Casualty Insurance Company (“Ohio Casualty”). The plaintiff, Amethyst, filed a petition for damages against defendants, Rugg and its insurer, Ohio Casualty, seeking to collect the full amount of the invoice.

After a trial, the court issued oral reasons for judgment, finding that because Rugg had attempted to make arrangements for completion of the job after faxing the notice, the plaintiffs interpretation of Rugg’s letter as a cancellation of the contract was not reasonable. The court rendered judgment awarding Amethyst $150, but dismissed all other claims against Rugg. Plaintiff appeals the judgment.

DISCUSSION

The plaintiff contends the trial court erred in finding that Amethyst |.(Unreasonably terminated the contract. Plaintiff argues that Anethyst was entitled to full payment because Rugg cancelled the contract by failing to allow a reasonable time for performance under the circumstances.

When the obligor fails to perform, the obligee has a right to the judicial dissolution of the contract, or according to the circumstances, to regard the contract as dissolved. In either case, the obligee may recover damages. LSA-C.C. art. 2013. *884 Upon a party’s failure to perform, the other may serve a notice to perform, with a warning that unless performance is completed within a certain period of time, the contract shall be deemed dissolved. The time allowed for performance must be reasonable under the circumstances. LSA-C.C. art. 2015.

The trial court’s findings of fact are subject to the manifest error standard of review. The appellate court must determine whether the trial court’s conclusion is reasonable based upon the record as a whole. Graves v. Page, 96-2201 (La.11/7/97), 703 So.2d 566.

In the present case, James Steven Rugg testified that he was a principal of Rugg Construction, Inc. and had worked as a general contractor for 30 years. Rugg stated that although he had originally scheduled plaintiff to apply the soil cement in July 2007 and pour asphalt in August 2007, the job was approximately three months behind schedule and the site was not ready for plaintiff at that time. Rugg testified that in late October 2007, he told Ben Holdman that the site was ready for soil cement. Rugg stated that he was later informed by Holdman of the problems concerning the grade of the parking lot and the debris under the soil. Rugg testified that on [.¿December 17, 2007, he called Holdman to ask about the job and was told that Amethyst would not be able to work at the church site that week and would be closed the last two weeks of the year for employee vacation. However, Holdman said that the church site would be the first job done after the start of the new year. Rugg testified that when he did not see the Amethyst crew at the site on January 2, 2008, he faxed the notice of cancellation to Holdman.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Graves v. Page
703 So. 2d 566 (Supreme Court of Louisiana, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
26 So. 3d 881, 2009 La. App. LEXIS 2029, 2009 WL 4641879, Counsel Stack Legal Research, https://law.counselstack.com/opinion/amethyst-construction-inc-v-js-rugg-construction-inc-lactapp-2009.