American West Construction, LLC

CourtArmed Services Board of Contract Appeals
DecidedDecember 19, 2017
DocketASBCA No. 61094
StatusPublished

This text of American West Construction, LLC (American West Construction, LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American West Construction, LLC, (asbca 2017).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of-- ) ) American West Construction, LLC ) ASBCA No. 61094 ) Under Contract No. W912HY-10-D-0039 )

APPEARANCE FOR THE APPELLANT: Ryan J. Klein, Esq. Sherman & Howard L.L.C. Colorado Springs, CO

APPEARANCES FOR THE GOVERNMENT: Thomas J. Warren, Esq. Acting Engineer Chief Trial Attorney Katharine S. Talbot, Esq. Alexandria P. Tramel, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Fort Worth

OPINION BY ADMINISTRATIVE JUDGE PROUTY

This appeal is before us pursuant to the expedited proceedings provided for by Board Rule 12.3 1• In this appeal, the government seeks to recover, from a contractor, cost savings that the contractor realized by performing a construction contract using less expensive means than those specified by the contract. Here, we find in favor of appellant, American West Construction, LLC (American West), because even though the government did have the right to insist upon compliance with its specifications, it waived that right.

SUMMARY FINDINGS OF FACT

The above-captioned contract is a multiple award task order contract (or "MATOC," as such vehicles are often known) for design-build construction services in the southwestern United States (R4, tab 1 at 3). It was awarded by the United States Army Corps of Engineers (the government or the Corps) to American West on 27 September 2010 (id. at 2). Amongst the MATOC's provisions was the standard "Changes clause," Federal Acquisition Regulation (FAR) 52.243-4, CHANGES (JUN 2007) (id. at 198). On 13 August 2015, the Corps issued Delivery Order 02 (D02) on the MATOC, in the

1 Appellant originally sought to proceed pursuant to Board Rule 12.2, but waived that request in order to proceed with a mediation that was ultimately cancelled. At the subsequent hearing on the merits, appellant requested to proceed via Rule 12.3, which we allowed. amount of $2,599,430, to American West (R4, tab 2 at 503). D02 is the central contractual document in this dispute.

D02 was for the construction of bridges over irrigation canals in El Paso County, Texas, near the border with Mexico (R4, tab 2 at 502-07). To access the site of one of those bridges, "the Herring bridge," D02 provided for the construction of two temporary bridges over another canal and a drainage ditch (R4, tab 2 at 550, 763; tr. 1117-21). These temporary bridges were to be disassembled and removed after completion of the Herring bridge that was one of the objectives ofD02 (R4, tab 2 at 763).

American West was concerned that it would not have enough time to complete the project in the time required by D02 if it built the temporary bridges, especially given seasonal constraints related to use of the irrigation ditches based upon agricultural needs. Instead, it sought access to the construction site via a levee on property held by the El Paso County Water Improvement District (the Water District, also known as "the Ditch Company"), which it and J.D. Abrams, the subcontractor that would perform much of the work for American West, 2 believed would be quicker, safer, and more efficient. (Tr. 11176-77, 237-38) Because it could not be sure that it would obtain the easement until the negotiations were successful, J.D. Abrams made preparations to use temporary bridges ifthe easement was not approved (tr. 11250). J.D. Abrams incurred costs of approximately $20,000 to ensure the availability of temporary bridges (id. at 252).

The first indication in the record that American West gave to the government that it intended to utilize the levee route, instead of the temporary bridges contemplated in the contract, was in the Construction Site/Traffic Control Plan that it submitted to the Corps on 23 September 2015 (see R4, tab 3). The government reviewer of this plan noted on the accompanying form that, "Haul roads provided in this submittal have not been approved by the government as provided in the contract documents. Provide required permits and approvals for using these roads." (Id. at 3293) In the agenda for a meeting between the parties held on 27 October 2015, American West noted, "Permits in hand except access road, but we can use USACE dictated routing till licensed by Ditch Co for Herring (forthcoming)" (ex. A-4 at 1).

The necessary permit was, indeed, forthcoming. J.D. Abrams paid the Water District $1,000 on 13 October 2015 to consider its request for an easement and to price it, then paid the Water District the $13,200 it ultimately wanted for the easement on 30 October 2015 (supp. R4, tab 18, tr. 11207-08, 242-43). The easement was executed by a representative from J.D. Abrams on 28 October 2015, and by the Water District

2 J.D. Abrams's contract with American West was a firm-fixed-price contract and it passed neither its cost savings nor increased expenses to American West (tr. 11251).

2 on 10 November 2015 (R4, tab 9 at 3501; tr. 1/209-11 ). The agenda for the parties' weekly construction meeting, held on 3 November 2015, noted that American West had obtained the easement from the Water District (app. supp. R4, tab 23 at 4).

Although the Corps never explicitly approved a plan using the Water District levee in lieu of the bridges (see tr. 1161-63 ), this lack of approval did not ultimately prevent American West from proceeding with and completing the construction without using, or ever constructing, the temporary bridges (tr. 1198, 102).

Mr. Ramon Macias was the resident engineer and administrative contracting officer assigned to the project for the Corps (tr. 1153). He had oversight responsibilities for all Corps construction in the geographically extensive El Paso office area of responsibility (tr. at 52). Mr. Macias testified that he was aware of the proposal to use the levee instead of the temporary bridges in the Fall of 2015 and that he did not object so long as it was ''equitable to the government" (tr. 1161), by which he meant the costs would be about the same (tr. 1164 ). He further testified that he had a brief, in-person, discussion with the American West project manager, Mr. Jude Kolb, to that effect in late October 2015 (tr. 1162-63). Mr. Kolb testified that he did not recall such a conversation (tr. 11215).

Mr. Macias also testified that he raised the issue of a government credit for waiver of the temporary bridge requirement with American West (primarily, Mr. Kolb) monthly, starting in the mid-December 2015 timeframe (tr. 1/79-80). Mr. Macias did not contemporaneously document these discussions, but testified that he directed the project's quality assurance representative (QAR), Mr. Arturo Aranda, to make notes of important discussions in the daily reports that he kept (tr. 1199-100). There are no notes in these daily reports touching upon the temporary bridges issue until 2 March 2016 (tr. 11112-13; see supp. R4 at 3825). Mr. Kolb testified that, to his recollection, this was the first time that the subject of a credit for the temporary bridges was raised with him (tr. 11215).

The hearing judge closely observed the demeanor of both Mr. Kolb and Mr. Macias during their testimony at the hearing and found both to appear credible: more likely than not, both testified truthfully regarding their recollections. We reconcile the disparity in testimony by consideration of the daily reports, which did not reflect the discussions recalled by Mr. Macias until 2 March 2016. The most likely cause of this is that, even if Mr. Macias did raise the credit issue on occasion before 2 March 2016, it was done in an off-hand manner that neither registered with Mr. Kolb, nor Mr. Aranda, who did not find it noteworthy.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Miller Elevator Co. v. United States
39 Cont. Cas. Fed. 76,635 (Federal Claims, 1994)
Gresham & Co. v. United States
470 F.2d 542 (Court of Claims, 1972)
Rixon Electronics, Inc. v. United States
536 F.2d 1345 (Court of Claims, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
American West Construction, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-west-construction-llc-asbca-2017.