American Radiator & Standard Sanitary Corporation v. L. L. Forbes

259 F.2d 147, 1958 U.S. App. LEXIS 4709
CourtCourt of Appeals for the Ninth Circuit
DecidedApril 3, 1958
Docket15651
StatusPublished
Cited by1 cases

This text of 259 F.2d 147 (American Radiator & Standard Sanitary Corporation v. L. L. Forbes) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Radiator & Standard Sanitary Corporation v. L. L. Forbes, 259 F.2d 147, 1958 U.S. App. LEXIS 4709 (9th Cir. 1958).

Opinion

259 F.2d 147

AMERICAN RADIATOR & STANDARD SANITARY CORPORATION, a Corporation, Appellant,
v.
L. L. FORBES and A. W. Bodine, Doing Business as L. L. Forbes Construction Company, and The Home Indemnity Company, a Corporation, Appellees.

No. 15651.

United States Court of Appeals Ninth Circuit.

April 3, 1958.

Fennemore, Craig, Allen & McClennen, Philip E. Von Ammon, Phoenix, Ariz., for appellant.

John A. Murphy, Stahl, Murphy & Blakley; Jennings, Strouss, Salmon & Trask, O. M. Trask, Phoenix, Ariz., for appellees.

Before STEPHENS, Chief Judge, and HEALY and FEE, Circuit Judges.

JAMES ALGER FEE, Circuit Judge.

This is an action by a materialman who furnished materials to a subcontractor, which were used in the construction of a schoolhouse in Arizona, against the principal, which was the contractor, and the surety on a bond. After trial, upon an agreed statement of facts and a stipulation, the District Court entered judgment against the materialman. This appeal followed.

The questions of law to be decided by this Court are:

Was the contract between the principal contractor and the school district intended to confer benefit upon a third party, the appellant, who supplied goods only to a subcontractor, or was the contract a statement of the obligations of the school district and the principal contractor alone?

Where the condition of the bond is that the surety shall indemnify the school district, does any statute of the state of Arizona applicable to the situation give a right of action other than to the school district?

Is liability affected by the fact (a) that the principal contractor contracted in writing with the school district to provide and pay for all materials necessary to complete the work, (b) that the principal contractor has accepted payment of the statutory retention fund without having furnished to the public authority any receipt or lien waiver evidencing payment for the materials to the supplier thereof although receipt of payment to the subcontractor has been furnished, (c) that the principal contractor has received prior actual notice that the supplier of material has not been paid?

The facts material to a solution of these questions appear in the stipulation, as follows:

On September 30, 1954, Forbes and Bodine (hereinafter referred to as "Forbes") entered into a contract with the Board of Supervisors of Maricopa County, Arizona, acting as the agents of Glendale Union High School District, for the construction of classroom additions to the high school. Simultaneously with the execution of the contract and in compliance with Section 10-610, 1939 Arizona Code Annotated (hereinafter quoted in part), Forbes furnished to the Board of Supervisors a contract bond with The Home Indemnity Company, a New York corporation, as surety.

Subsequently, Forbes subcontracted with Bachman for all plumbing materials and labor for the classroom construction. Bachman, in turn, purchased plumbing materials and supplies to install in the job from plaintiff American Radiator and Standard Sanitary Corporation (herein-after sometimes called the "Radiator Company"), a Delaware corporation. Materials supplied by plaintiff to the subcontractor Bachman were used in the classroom construction. Bachman completed his subcontract and was paid in full by Forbes.

The construction was completed July 16, 1955, at which time Forbes filed a notice of completion with the Board of Supervisors. On July 18, 1955, plaintiff mailed to the school district, Forbes, Bachman and the surety a notice claiming $10,594.52 was due plaintiff for material furnished Bachman for installation in the classrooms. Subsequent to receipt of this notice, the school district, through the Board of Supervisors, paid the final sums due on the contract to Forbes. It did not pay any sums to plaintiff.

Since the bond was conditioned upon indemnification by the principal contractor of the obligee for loss or damage directly caused by the failure of said contractor faithfully to perform the contract, the first inquiry must be whether there was a breach of any term of the agreement. There is only one breach claimed of the promises which are expressly contained in the contract. It is said there was a failure to perform the obligation contained in the following language:

"Article 3. Materials, Appliances, Employes — Except as otherwise noted, the Contractor shall provide and pay for all materials, labor, tools, water, power and other items necessary to complete the work.

"Unless otherwise specified, all materials shall be new, and both workmanship and materials shall be of good quality.

"All workmen and sub-contractors shall be skilled in their trades."

as supplemented by Article 1 of the General Conditions, which reads:

"The intent of these documents is to include all labor, materials, appliances and services of every kind necessary for the proper execution of the work, and the terms and conditions of payment therefor."

It seems clear enough that these clauses were fulfilled and faithfully performed in the event Forbes had paid Bachman, the sub-contractor, for the work and materials which went into the building. The Radiator Company trusted Bachman. By the express stipulation, the school district and the Board of Supervisors sought only that no claims could be presented to them. Therefore, if Forbes had paid Bachman, he had fulfilled this portion of the contract. Thus the language used does not imply that a supplier of material to Bachman was within the purview of the contract. There is no express indication that the parties were contemplating any third person or were attempting to make a stipulation for the benefit of the Radiator Company or anyone else. There was no evidence of such an intention. No extrinsic testimony was introduced to prove such intention. There is no clause in the stipulation to that effect. As a result, the trial court made no finding to that effect. The District Court treated the matter as one of law involving the construction of the writing. It was concluded that Forbes did not undertake any obligation toward the Radiator Company to pay for plumbing materials and supplies sold by the Radiator Company to Bachman. The doctrine announced by the Supreme Court of Arizona as to third party beneficiary contracts would go no further than this.1 We agree with the trial judge that Radiator Company had no right of action as a third party beneficiary against Forbes. The school district and the Board of Supervisors had been dismissed from the action and were therefore not liable to the Radiator Company on the contract.

Thus there is proof positive that the obligee on any bond issued could not have been injured, because no claim could be successfully asserted against either on the contract. The sub-contractor Bachman appears to have been a defendant in the action, but has disappeared in some manner, we know not how. Forbes obviously was not liable to the Radiator Company on the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Fidelity & Guaranty Company v. Long
214 F. Supp. 307 (D. Oregon, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
259 F.2d 147, 1958 U.S. App. LEXIS 4709, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-radiator-standard-sanitary-corporation-v-l-l-forbes-ca9-1958.